Fidelity & Deposit Co. v. Robertson

136 Ala. 379
CourtSupreme Court of Alabama
DecidedNovember 15, 1902
StatusPublished
Cited by32 cases

This text of 136 Ala. 379 (Fidelity & Deposit Co. v. Robertson) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. Robertson, 136 Ala. 379 (Ala. 1902).

Opinion

SHAP-PE, J.

Adams, Wright & Gossett contracted in writing with plaintiff to build for the latter according to certain specifications a, dwelling house, to furnish material therefor, to finish the work and deliver the building on or before the first of September, 1897, for which they were to be paid |3,450.20 in installments as the work progressed on certificates of the architect, fifteen per cent, thereof to be reserved until the completion and delivery of the building free from liens chargeable to the1, contractors. In the contract it Avas stipulated that “the old house on the lot shall become the property of the contractor and materials that are passed upon by the architects and accepted may be used in the neAV building;” also that “should the*OAvner at any time during the progress of the Avork require any alterations of, deviations from, additions to, or omissions in the said contract, he shall have the right and power to make [407]*407such change or changes, and the same shall in no way injuriously affect or make void the contract, but the difference shall be added to or deducted from the amount of the contract as the case may be, by a fair and reasonable valuation;” also that “should the contractors at any time during the progress refuse to supply a sufficiency of workmen or materials, or cause any unreasonable delay or suspension of the work, or fail or refuse to comply with any of the articles of agreement, the owner or his agent shall have the right and power to enter upon and take possession of the premises, and provide materials and workmen sufficient to finish the work, after giving three days notice in writing directed, and delivered to the party of the second part; and the expense of finishing the various works shall 'be deducted from the amount of the contract.” By another clause the contractors agreed that in the event of their failure “to deliver the works completed on the date above mentioned”, they would forfeit to plaintiff five dollars for each day thereafter that the same remained unfinished, such forfeitures “to be deducted from the amount to be paid under this contract.”

After the execution of this contract Adams, Wright & Gossett as principals together with this defendant as surety executed a bond conditioned for the compliance by the contractors “with all the terms, covenants and conditions” of the building contract which contract is expressly referred to as forming part of the bond, and the latter contains certain provisions looking to the. protection of defendant as a surety, one of which is “that said surety shall be notified in writing of any act on the. part of the said principals or their agent or employes which may involve a loss for which the said surety is responsible hereunder, immediately after the occurrence of such act shall have come to the knowledge of the duly authorized representative or representatives of said W. T. Kobertson who shall have sunervisi'on of the completion of said contract,” etc. Another proviso of the bond was “that if the said principals shall fail to comply with all the conditions of said contract to such an extent that the same shall be forfeited, then said surety shall have [408]*408the right and privilege to assume said contract, and to sub-let, or complete same whichever said surety may elect to do, provided it is done in accordance with said contract.”

On the 7th of July, 1897, after Adams, Wright & Gos-sett had partly built the house, using therein mainly new material, but some timbers of the old house, plaintiff. served them with the following notice: “T. J. Adams, W. C. Wright, A. J. Gossett, Adams, Wright & Gossett, Sir: Notice is hereby given you that yon have breached the contract entered into with the undersigned' in this: 1st, Yon have failed or refused to provide all manner of material and labor, etc. needful for the due performance of the several works incident to building my house as provided in 4th paragraph of contract of April 26th, 1897. 2nd, That you have refused to supply sufficiency of workmen and material and caused an unusual delay or suspension of the work, or failed or refused to comply with said articles of agreement of April 26th, 1897, as provided by section 6, and other provisions in contract of said date. Now in compliance with said stipulations, I notify you that said contract is forfeited, and I shall exercise my rights in the premises as I may see proper. W. T. Robertson.”

About t’li e time of this notice plaintiff notified the defendant that the contractors had failed to comply with their contract, and defendant declined to undertake the completion of the work, whereupon plaintiff employed Smith & Graves to complete the building according to the original plans except that two rooms were added extra. These last contractors under their contract with the plaintiff received and used in the building certain new material which had been provided therefor by Adams, Wright & Gossett and under the same contract the remaining timbers of the old house went into their possession and were used partly in completing the house and partly in structures of their own. The building in question was not finished until several months after the time fixed therefor by the contract with Adams, Wright & Gossett. The defendant is here sued alone as an obli-[409]*409gor on tlie bond whereby it guaranteed the performance by Adams, Wright & Gossett of their contract.

The demurrer to count 3 of the complaint ivas properly overruled. That count set out in full the bond sued on including the building contract, and avers the latter ivas in specified particulars, unperformed, that the damages ela.ipied resulted, and that settlement thereof was¡ demanded of defendant and refused. These averments pointed with sufíicient definiteness to a breach of the bond and contained the essentials of a cause of action.

The court’s action in sustaining demurrers to pleas was free from error. The provision of the building contract referred to in plea 4 Avhieh authorized the temporary reseiwation from payments of 15 per cent, of estimated earnings, Ave construe as being solely for the plaintiff’s benefit, and consequently as one Avhieh he, in the absence of any prohibition in the bond, ivas privileged to waive Avithout prejudice to his rights against the defendant.

If after the execution of the bond additions to the building Averé agreed upon and made as averred in plea 9, that fact may have importance as tending to show a Avaiver by plaintiff of the stipulation as to time for completion of the house Cornish v. Suydam, 99 Ala. 620) ; but it is not inconsistent with his right to insist on the performance of others. The original contract having expressly provided for making, “alterations of, deviations from, additions to or omissions in said contract” without avoidance of the same and upon the basis of a corresponding change in the original contract price, it does not folloiv that the facts averred in either plea 9 or plea 10 had effect to release the defendant from its undertaking.

Pleas 12, 14, 15 and 16 as first filed Avere merely to the purpose of showing there had been an adjudication of the plaintiff’s present claim under a plea setting up a counter-claim by him in a suit on the original contract brought against him by Adams. Wright & Gossett. Neither of these pleas shows that defendant was a party to that suit, or that it stands here as the representative of Adams, Wright & Gossett in respect to the matters [410]*410there determined; hence it does not appear that the judgment in that suit is binding on the parties in this.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Maryland Cas. Co.
204 F.2d 912 (Fifth Circuit, 1953)
Griffin v. Bozeman
173 So. 857 (Supreme Court of Alabama, 1937)
Interstate Electric Co. v. Fidelity & Deposit Co.
153 So. 427 (Supreme Court of Alabama, 1934)
Lawrence v. United States Fidelity & Guaranty Co.
145 So. 577 (Supreme Court of Alabama, 1933)
Bell v. Jones
136 So. 826 (Supreme Court of Alabama, 1931)
National Loan & Exchange Bank v. Gustafson
154 S.E. 167 (Supreme Court of South Carolina, 1930)
Blackwood v. Gurley
121 So. 76 (Supreme Court of Alabama, 1929)
Red Star Motor Drivers' Ass'n v. City of Detroit
221 N.W. 622 (Michigan Supreme Court, 1928)
Crum Et Ux. v. Jenkins
143 S.E. 21 (Supreme Court of South Carolina, 1928)
Little v. Fidelity & Deposit Co. of Maryland
3 Tenn. App. 157 (Court of Appeals of Tennessee, 1926)
Clark v. Whitfield
105 So. 200 (Supreme Court of Alabama, 1925)
Maryland Casualty Co. v. State
87 So. 521 (Supreme Court of Alabama, 1921)
Smith Sons Lumber Co. v. Steiner, Crum Weil
85 So. 758 (Supreme Court of Alabama, 1920)
McVitty v. Flentge
169 P. 666 (California Court of Appeal, 1917)
Terrell v. Nelson
74 So. 929 (Supreme Court of Alabama, 1917)
Garey v. City of Pasco
154 P. 433 (Washington Supreme Court, 1916)
Doyle v. Faust
153 N.W. 725 (Michigan Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
136 Ala. 379, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-robertson-ala-1902.