Doyle v. Faust

153 N.W. 725, 187 Mich. 108, 1915 Mich. LEXIS 563
CourtMichigan Supreme Court
DecidedJuly 23, 1915
DocketDocket No. 35
StatusPublished
Cited by16 cases

This text of 153 N.W. 725 (Doyle v. Faust) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doyle v. Faust, 153 N.W. 725, 187 Mich. 108, 1915 Mich. LEXIS 563 (Mich. 1915).

Opinion

The Faust-Scheel Company, a copartnership, contracted with plaintiffs to construct for them, furnishing all material and labor, a certain building for $9.-945—

“subject to additions and deductions as provided in the general conditions of the specifications and that such sum shall be paid by the owner to the contractor, in current funds, and only upon certificates of the architect, as follows:
“Ninety per cent, of the value of the. completed work, upon estimates made by the architects, every two weeks as the work progresses until it is entirely completed.
“The final payment including the ten per cent., previously withheld, shall be payable within 30 days after the entire completion and acceptance, by the architect, of the work covered by this contract.”

The general specifications provided that:

“The architect shall have the power to require alterations in the work as shown or described in the said drawings or specifications, and the contractor shall proceed and make such changes without causing delay. In every such case the price agreed to be paid for the work under the contract shall be increased or decreased as the case may require, according to a fair and reasonable valuation of the work, added or omitted, and the value of such work shall be fixed by fair ad-[111]*111measurement and valuation made by the architect or some competent person appointed by him. Such alterations or variations shall in no way render void the contract, and no claim for variations or alterations or the increased or decreased price thereof shall be valid unless done in pursuance of an order from the architect and notice of such claim made to him in writing before the commencement of such work.”

Another specification is:

“Should the contractor become insolvent or at any time refuse or neglect to-supply a sufficiency of properly skilled workmen or of materials of the proper quality or fail in any respect to prosecute the work with promptness and diligence or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty after 48 hours’ written notice to the contractor to provide any such labor or materials and to deduct the cost thereof from any money then due, or thereafter to become due, to the contractor, under the contract, and if the architect shall certify that such refusal, negletít or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work, and to enter upon the premises and take possession, for the purpose of completing the work included under the contract, of all materials, tools, and appliances thereon and to employ any other person or persons to finish the work and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor the contractor shall not be entitled to receive any further payment under the contract until the said work shall be wholly finished, at which time if the unpaid balance of the amount to be paid under the contract shall exceed the expense incurred by the owner in finishing the work, such expense shall be paid by the owner to the contractor; but if such expense shall exceed such unpaid balance the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided either for furnishing material or for finishing the work, or any damage incurred through such default, shall be audited and certified by the arch[112]*112itect whose certificate thereof shall be conclusive upon the parties.”

The contract was dated July 27, 1910, and contained the further provision that the whole of the work should be completed on or before the 1st day of November, 1910, that time was an important element, and that for every day the work remained unfinished beyond the date fixed for its completion the contractors should pay the owners as stipulated damages $6.50 a day, and if completed before November 1, 1910, the owners should pay the contractors a like sum for each day saved, as a bonus.

The contractors as principals and the defendant surety company made and delivered to the owners an undertaking, in writing, which recited the entering into of the said contract for construction by the said principals, by which the said principals and the surety were bound to the owners in the sum of $5,000, and in which the surety—

“guarantees that said principals * * * shall fully pay, discharge and liquidate all claims, accounts and indebtedness of the said principals, * * * for or on account of all labor performed and materials furnished in fulfilling said contract. * * *”

The general condition of the bond is that the contractors shall fully pay, discharge, and liquidate all claims, accounts, and indebtedness of the principals for or on account of all labor performed and materials furnished in fulfilling the said contract and performing the several conditions as the same may become due and payable. The premium paid the surety company for its undertaking was based upon the contract price. The bond was prepared by the architect, acting for the owners. The original plans and specifications were submitted to various bidders for construction, and upon them the bid of the contractors was based.

There were prospective tenants of the proposed new [113]*113building, and there was a building on the site to be occupied by it. The purpose of the owners was to use the south wall thereof as the south wall of the new building and to use a party wall already erected on the north side of the new building. After the work was begun, there was a failure of the owners and the prospective tenants to agree, and the owners instructed the architect to make amended plans, and such plans were prepared. The building is 98 feet and 7 inches long and 37% feet wide. The original plans divided it by cross-partitions into three rooms; the new plans made of it two separate store buildings, divided lengthwise of the building by a 12-inch brick wall constructed from the bottom of the cellar to the ceiling of the first story. This wall is 106 feet long and 21 feet high. It was found, too, that the party wall on the north was not strong enough to carry the building and an additional wall, 4 inches thick, was built, from the floor of the basement to the roof. The south wall of the old structure was found to be defective, was removed, and a new 16-inch brick wall built the entire length of the building on the south side. An extra chimney 43 feet high was built on the north side of the building and an outside entrance stairway to the second floor in place of an inside stairway as originally planned. Twelve extra windows were placed on the south side of the building. The front windows as planned were changed in the second story. Other considerable changes from the original plans were made. Some of these changes were made after the work called for by the original plans had been installed. All were made without the knowledge and without notice to the surety company. Payments were made to the contractors by the owners without first having received certificates from the architect, the amount so paid exceeding the amount of the judgment. And, after having notice that unpaid demands against the contractors existed, [114]*114the owners paid’ directly to the contractors considerable sums of money, although the contract provides that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Gene
207 B.R. 861 (W.D. Michigan, 1997)
Bd. of Governors of Wayne State Univ. v. Building Systems Housing Corp.
233 N.W.2d 195 (Michigan Court of Appeals, 1975)
Moore v. CONTINENTAL CASUALTY COMPANY
353 F. Supp. 105 (W.D. Oklahoma, 1973)
Maryland Casualty Co. v. City of South Norfolk
54 F.2d 1032 (Fourth Circuit, 1932)
Hollerman Mfg. Co. v. Standard Accident Insurance
239 N.W. 741 (North Dakota Supreme Court, 1931)
City of Portsmouth v. Nicola Building Co.
106 Ohio St. (N.S.) 550 (Ohio Supreme Court, 1922)
Sandusky Grain Co. v. Borden's Condensed Milk Co.
183 N.W. 218 (Michigan Supreme Court, 1921)
Southern Surety Co. v. Nalle & Co.
231 S.W. 402 (Court of Appeals of Texas, 1921)
Morrow Transfer & Storage Co. v. Wells Bros.
106 S.E. 200 (Court of Appeals of Georgia, 1921)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)
Harvey v. George
175 N.W. 140 (Michigan Supreme Court, 1919)
Fellows v. Errington
186 Iowa 322 (Supreme Court of Iowa, 1919)
Hileman & Gindt v. Faus
178 Iowa 644 (Supreme Court of Iowa, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
153 N.W. 725, 187 Mich. 108, 1915 Mich. LEXIS 563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doyle-v-faust-mich-1915.