Fellows v. Errington

186 Iowa 322
CourtSupreme Court of Iowa
DecidedJanuary 27, 1919
StatusPublished
Cited by3 cases

This text of 186 Iowa 322 (Fellows v. Errington) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fellows v. Errington, 186 Iowa 322 (iowa 1919).

Opinion

Per Curiam.

1. Principal and surety: suretyship and indemnity contrasted. On April 28, 1914, the plaintiff entered into a written contract with the defendant Errington, by ■ the terms of which the latter undertook to furnish the materials and labor and construct a residence building for the plaintiff, to be completed on or before February 1, 1915, at the aggregate price of $18,868. To secure the performance of such contract, Errington, with [324]*324the defendant Maryland Casualty Company, made and delivered to plaintiff a bond. This bond is in the usual form of such instruments. It is not a mere undertaking to hold plaintiff harmless against loss or damage from any failure by Errington to perform the contract, but the Casualty Company thereby expressly takes upon itself the obligation of surety for the full performance of the contract, according to its terms. To make this plain beyond doubt or equivocation, it annexes, the contract to the bond, and declares, in so many words, that such contract is made a. part of the bond “as fully as if recited at length therein and to make the company’s relation to the contract and to the plaintiff doubly sure, the bond further declares that “the obligation of the surety is and shall be construed as one of suretyship only.”

The contract provided certain terms and times of payment to the contractor, and also contained the following stipulation:

2. principal and surety : liabinty on unadjudicated claims. “If at any time there shall be evidence of any lien or claim for which, if established, the owner of said premises might become liable, and , ,, which is chargeable to the contractor, the owner shall have the right to retain, out of any payment then due or thereafter to become due, an amount sufficient to completely pay and discharge such' lien or claim; and furthermore, the owner shall have the right to fully pay and discharge or purchase any such lien or claim, and to charge any and all amounts so expended to the contractor, and to deduct the same from the amount of any estimate or payments already due or to become due to the contractor under and by virtue of this contract. Should there prove to be any such claim after all payments are made, the contractor shall refund to the owner all moneys the latter may be compelled to pay in discharging any lien or claim on said premises made obligatory in consequence of the contractor’s default.”

[325]*325Errington proceeded with the performance of his contract, bnt abandoned it before completion. At the time of such abandonment, there remained unpaid on the contract price the sum of $2,868, and for extra labor and materials, there was a further claim by the contractor of $670.

Thereafter, this action was brought on the bond. As a cause of action, after reciting the contract and bond, the plaintiff alleges that Errington, in prosecuting such work, contracted debts or claims which were or might be made

liens upon the property, as follows:

Hawkeye Lumber Company ............$1,452.88

Louis Hanssen’s Sons Company......... 467.00

H. T. Barber Lumber Company ........ 64.69

Des Moines Marble Company............ 320.00

T. W. McClelland Company ............ 2,333.50

Total $4,638.07

For this sum, less the amount unpaid on the contract, he demands judgment. He also makes a claim for $1,000 damages on account of imperfect work in construction.

The defendant Errington makes no defense. The Casualty Company answered, and, after generally denying what is not admitted, first, admits the contract and bond; second, alleges that plaintiff made payments to Errington in excess of the architect’s estimates; third, alleges that plaintiff failed to have the work done undey supervision of the architect; fourth, alleges failure of the plaintiff to have the matter of his damages audited by the architect; fifth, alleges that plaintiff made several changes in the plan of the building, without the written approval of the architect.

The issues were tried to a jury, which, after finding the amount of claims due the plaintiff, and crediting thereon the unpaid remainder of the contract price and tlm value of the extras furnished by Errington, returned a verdict against defendant for $2,797.99. From the judgment ren[326]*326dered on this verdict, the defendant Casualty Company alone appeals.

Keeping in mind the defenses pleaded by the appellant, and above particularly stated, the case presents no serious difficulties. None of the special or affirmative defenses pleaded have any substantial support in the testimony, and may be passed without further special comment.

We have, therefore, only to consider the plaintiff’s claim, in connection with the defendant’s admissions and denials and the testimony bearing thereon. ' The evidence tends to show that, when Errington abandoned the work, he left unpaid claims held by dealers who had sold him materials for the building, and that such dealers had already filed, or did immediately thereafter file, liens therefor, as indicated in the list hereinbefore set out. Of these claims plaintiff paid without suit all except the one filed by T. W. McClelland Company for $2,338.50. This claim, it was shown, had been sued, and the lien foreclosed against the plaintiff; but Errington was not a party to the action. There was no showing that this claim has yet been paid.

The first and most serious contention on the part of the defense is that the bond is one of indemnity only, and not of suretyship, and that the only liability of the defendant is to pay the plaintiff such damages as he has, in fact, suffered. From this standpoint, it is argued that, until plaintiff has paid the McClelland claim, he has not been-damaged, and no recovery can be predicated thereon. It is further objected that, as Errington was not a party to the foreclosure of the McClelland lien, the adjudication does not bind the surety.

If the contract in this case were strictly one of indemnity, like an insurance contract or an ordinary fidelity bond, there would be room for -fair argument in support of this defense; but that the bond is strictly and clearly one of suretyship, and that the liability of the Casualty Company is1 [327]*327that of a surety, who is hound with his principal in all respects even as he is hound, and not as a mere indemnitor, who is bound to restore to plaintiff his actual losses occasioned by the principal’s fault, is too evident for dispute. By its express terms, the bond is not only made to include the contract as a part thereof, but the company, in express terms, declares that it assumes “the obligation of surety-ship.” So far as the plaintiff and the company are concerned, the contract, and bond are one agreement, and the company is bound with Errington; and, subject only to its right to be released because of some act or omission of plaintiff’s, it is bound to the same extent that Errington is bound, upon each and every stipulation of the building agreement. Leiter v. Dwyer Plumbing Co., 66 Ore. 477 (133 Pac. 1180); Doyle v. Faust, 187 Mich. 108 (153 N. W. 725). Its obligation as between the plaintiff and itself is not secondary, but original.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Employers Mutual Casualty Co. v. United Fire & Casualty Co.
682 N.W.2d 452 (Court of Appeals of Iowa, 2004)
Clapp v. Wallace
866 N.W. 493 (Supreme Court of Iowa, 1936)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
186 Iowa 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fellows-v-errington-iowa-1919.