Bd. of Governors of Wayne State Univ. v. Building Systems Housing Corp.

233 N.W.2d 195, 62 Mich. App. 77, 1975 Mich. App. LEXIS 1031
CourtMichigan Court of Appeals
DecidedJune 10, 1975
DocketDocket 20196
StatusPublished
Cited by6 cases

This text of 233 N.W.2d 195 (Bd. of Governors of Wayne State Univ. v. Building Systems Housing Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bd. of Governors of Wayne State Univ. v. Building Systems Housing Corp., 233 N.W.2d 195, 62 Mich. App. 77, 1975 Mich. App. LEXIS 1031 (Mich. Ct. App. 1975).

Opinion

M. F. Cavanagh, J.

The plaintiff of a breach of contract action, Board of Governors of Wayne State University (hereafter the "University”), appeals from the grant of a summary judgment in Wayne County Circuit Court in favor of the defendants Building Systems Housing Corporation (hereafter "Building Systems”) and American Insurance Company.

In May of 1972 the board of governors of the University authorized the construction of a 257-unit apartment structure to be built on the campus. Bids were solicited and received. The scheduled closing time for receiving bids was 2 p.m., July 25, 1972. The defendant Building Systems *79 submitted the low bid of $4,824,000. In accordance with the plaintiffs advertisements, Building Systems submitted a surety bond executed by American Insurance Company in the amount of five percent of the bid.

The bid provided, in pertinent part:

(a) "The bidder understands that the Owner reserves the right to reject any or all bids and to waive any informalities in bidding.
(b) "The bidder agrees that this bid shall be good and may not be withdrawn for a period of thirty calendar days after the scheduled closing time for receiving bids.
(c) "Upon receipt of written notice of acceptance of this bid, bidder will execute the formal contract attached within ten days and deliver a surety bond or bonds as required by Paragraph 29 of the General Conditions.”

On August 10, 1972, the board of governors passed a resolution awarding the general contract to Building Systems "subject to review and concurrence by the Department of Housing and Urban Development (HUD), and to the sale and delivery of bonds * * * ”. That same day a letter was sent to Building Systems informing it of the board’s decision including the two conditions. The letter stated further:

"As soon as the University receives approval from the Department of Housing and Urban Development in the award of this contract, we will be in touch with you to make the final arrangements for executing the necessary contract documents.”

Although Building Systems advertised for the submission of subcontractor bids, it thereafter decided not to continue with the project. By a letter dated August 30 and received August 31, 1972, *80 Building Systems informed the board that it was withdrawing its bid "pursuant to the terms of the bid proposal and the advertisement for bidders”. The letter concludes:

"Since more than 30 calendar days have passed since the submission of the bid, and since the contract was not unconditionally approved nor executed, we are exercising our rights under the bid procedures to withdraw our bid.”

At that time, the University had not received approval of defendant’s bid from HUD.

Thereafter, the plaintiff almost immediately informed Building Systems that it considered the corporation’s conduct to be an anticipatory breach of the contract. On September 8, 1972, the board awarded the general contract to the second lowest bidder for $5,090,000. Subsequently, the University demanded payment from defendants of $266,000 damages measured by the difference between the defendant’s bid and that of the next lowest bidder. Upon a refusal to pay, the plaintiff instituted this suit. On April 19, 1974, the trial court entered an order granting final summary judgment in favor of the defendant surety, American Insurance Company, and partial summary judgment in favor of defendant Building Systems. From this order, plaintiff appeals.

The plaintiff contends that the trial court erred in granting summary judgment because there were genuine issues of material fact 1 and because *81 the defendant surety was not entitled to a judgment as a matter of law. Plaintiff theorizes that when the University informed Building Systems of the contract award, a "preliminary construction contract” was formed. The University’s acceptance was unconditional since the conditions of HUD approval and the sale and delivery of financing bonds had been stated in the bid invitation, specifications, and conditions. The plaintiff’s claim is that the bid was an offer impliedly proposing that the offeree (the University) make a conditional promise as part of its acceptance. This preliminary contract contemplated the execution of a subsequent formal contract between the parties. Thus, plaintiff contends that the "withdrawal” of Building Systems’ bid was actually a breach for which the appellee American Insurance Company as suretor was also liable.

The defendant surety naturally has a considerably different way of looking at the transaction. First, there were no genuine issues of material facts. Building Systems, as the bidder, offered to perform work for the University and to keep its offer open for 30 days. The University "accepted” the offer subject to the concurrence of HUD and the preparation and sale of bonds to finance the work. This conditional acceptance, since it was not identical to the offer, amounted to a counteroffer and had the effect of rejecting the bidder’s offer. After 30 days had elapsed but before either of the two conditions had been met, Building Systems revoked its offer. Defendant contends that there *82 was nothing in' the preliminary documents which the University made available to all bidders to indicate that the two conditions were to be attached to an acceptance.

The trial court adopted the defendant surety’s legal theory and granted summary judgment in its favor. According to the court’s review of the records, the bidding documents contained no information indicating that the bid was to be conditioned on the two above-stated events. As a result, the defendant’s acceptance was conditional and Building Systems was not bound by a preliminary contract when it made a timely withdrawal of the bid.

It is axiomatic that appellate courts reviewing the grant of a summary judgment for the defendant assume that every well-pleaded allegation in the plaintiffs complaint is true and consider these allegations in a light most favorable to the plaintiff. Bielski v Wolverine Insurance Co, 379 Mich 280, 283; 150 NW2d 788 (1967).

Since no Michigan appellate court appears to have passed on a situation similar to that of the present case, both parties primarily utilize Federal cases. Plaintiff relies extensively upon United States v National Optical Stores Co, 407 F2d 759 (CA 7, 1969). In that case, the Federal government brought an action for the defendant’s alleged failure to perform under a contract to purchase surplus property. Included in the bid information provided to the defendant were the terms that the sale woúld be subject to antitrust clearance by the Attorney General and to a credit approval by the General Services Administration. After acceptance of the defendant’s bid and within the allotted time limit, the defendant attempted to withdraw its bid by relying on the conditional nature of the government’s acceptance.

*83

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Will H Hall & Son, Inc v. Ace Masonry Construction, Inc
677 N.W.2d 51 (Michigan Court of Appeals, 2004)
Echols v. Nimmo
586 F. Supp. 467 (W.D. Michigan, 1984)
Camelot Excavating Co. v. St. Paul Fire & Marine Insurance
280 N.W.2d 491 (Michigan Court of Appeals, 1979)
Cheboygan County Road Commission v. Auto-Owners Insurance
277 N.W.2d 176 (Michigan Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
233 N.W.2d 195, 62 Mich. App. 77, 1975 Mich. App. LEXIS 1031, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bd-of-governors-of-wayne-state-univ-v-building-systems-housing-corp-michctapp-1975.