Will H Hall & Son, Inc v. Ace Masonry Construction, Inc

677 N.W.2d 51, 260 Mich. App. 222
CourtMichigan Court of Appeals
DecidedMarch 19, 2004
DocketDocket 239772
StatusPublished
Cited by9 cases

This text of 677 N.W.2d 51 (Will H Hall & Son, Inc v. Ace Masonry Construction, Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Will H Hall & Son, Inc v. Ace Masonry Construction, Inc, 677 N.W.2d 51, 260 Mich. App. 222 (Mich. Ct. App. 2004).

Opinions

Murphy, P.J.

Plaintiff appeals as of right from a judgment granting defendant Capitol Indemnity Corporation’s motion for summary disposition, which was brought pursuant to MCR 2.116(C)(7)(release) and (10), in this action involving a construction project and a performance bond. We affirm.

Plaintiff was the general contractor for a government Job Corps construction project, and defendant Ace Masonry was a subcontractor providing cement and masonry work on the project. The construction project required that Ace furnish a performance bond intended to protect plaintiff, and one was issued by Capitol. Subsequently, a dispute arose between plaintiff and Ace concerning the masonry work, and the project was not fully completed.

The complaint filed by plaintiff alleged breach of contract, fraud, and misrepresentation with respect to Ace. The complaint also included a claim against Capitol seeking recovery on the performance bond. Ace filed a counterclaim against plaintiff alleging breach of contract, and a third-party complaint against plaintiff’s surety United States Fidelity & Guaranty Company.

The trial court granted Capitol’s motion for directed verdict during a jury trial in regard to the performance bond claim. The trial court granted the directed [225]*225verdict, finding a “failure of proof regarding compliance with conditions precedent, including failure to declare default.” Immediately after the trial court granted the directed verdict, plaintiff requested and obtained a brief recess to discuss a possible settlement with Ace. Following the recess, and on the record, plaintiff and Ace stipulated the release and dismissal of any claims the parties had against each other.1 The following colloquy took place regarding the settlement:

Plaintiff’s Counsel: [W]e have had an opportunity to [discuss] this matter amongst ourselves, in light of the [court] . .. granting Capitol Indemnity’s motion for directed verdict, the remaining parties in the case have discussed this matter and they’re willing to settle this case by mutual release of all claims against each other.
Judge: All right, Mr. Schaffer [counsel for Ace], do you wish to be heard on this?
Ace’s Counsel: I would just concur in that settlement— my client is here I just would ask that, on the record, he indicate that is his wish to do that. . . .

Ace’s representative proceeded to approve the settlement and release. The record does not reflect any statements by counsel for Capitol during discussion of the settlement. Further, the record does not indicate whether Capitol’s counsel remained in the courtroom after the directed verdict was granted and when the settlement and release were placed on the [226]*226record.2 Subsequently, plaintiff pursued an appeal of the directed verdict to this Court.

This Court, in an unpublished per curiam opinion, reversed the trial court’s order granting the directed verdict, holding:

Viewing [the] evidence in a light most favorable to plaintiff, we conclude that a reasonable factfinder could find that defendant received notice that the subcontractor committed a material breach, that plaintiff regarded the subcontractor to have failed to meet its contractual duties, and that plaintiff was asking defendant to perform under the terms of the bond.
To the extent the trial court found plaintiffs notice to defendant untimely, we note that the only time frame provided in the performance bond is the two-year limitations period for filing a lawsuit. Where the time of performance is indefinite, performance may be required to be rendered within a reasonable time. The question regarding the reasonableness of plaintiff’s claim, which was filed less than three months after Ace walked off the job, should have been submitted to the jury. [Hall & Son, Inc v Capitol Indemnity Corp, unpublished opinion per curiam of the Court of Appeals, issued June 15, 2001 (Docket No. 222262) (citations omitted).]

On remand, Capitol filed a motion for summary disposition, arguing that, in light of plaintiff’s decision to dismiss the action against Ace, an action on the performance bond could no longer be maintained. Capitol claimed that the release of the principal, Ace, by plaintiff, the obligee, acted as a discharge of Capitol, the surety. On the basis of Capitol’s argument, the [227]*227trial court granted the motion for summary disposition and dismissed the action. Plaintiff appealed.

Plaintiff argues on appeal that principles of res judicata require that a party raise in an initial appeal all issues that were then present and could have and should have been raised. Therefore, because Capitol did not raise in the previous appeal the issue that plaintiff stipulated the release and dismissal of Ace, thereby arguably denying this Court the opportunity to reject plaintiffs first appeal, Capitol effectively waived the issue on remand. We disagree.

Plaintiff relies on VanderWall v Midkiff, 186 Mich App 191; 463 NW2d 219 (1990). The VanderWall panel ruled:

[W]e conclude that the principles of res judicata require that a party bring in the initial appeal all issues which were then present and could have and should have been raised. That is, just as plaintiff was required in the initial appeal to present all arguments why the trial court had erred in granting judgment notwithstanding the verdict, defendants were also required to bring their challenges to the underlying judgment, whether it had been by way of argument in the appellee’s brief defending the trial court’s action or by way of cross appeal raising issues separate from the issue of the granting of judgment notwithstanding the verdict. [Id. at 201.]

Here, there is a distinction because Capitol was not able to validly argue in the first appeal that the trial court properly granted its motion for directed verdict on the alternative basis that Ace had been dismissed as a party. Considering the sequence of events, the settlement had not yet occurred when the trial court directed a verdict in Capitol’s favor, and was thus not part of an argument made by Capitol in support of [228]*228the motion for directed verdict. Whether as part of an argument in Capitol’s appellee brief or in a cross-appeal, there was no “ruling” on which the argument could be predicated with respect to the effect of the settlement and release on the performance bond claim. We acknowledge that Capitol technically had the ability to argue anything it pleased in the first appeal and could have argued that, in light of the settlement and release, no action on the bond could be maintained. However, it is likely that this Court, if faced with such an argument, would have declined to address the issue because there had been no ruling by the trial court on the subject and no arguments by the parties to the trial court on the issue. Moreover, considering that the trial court had already granted a directed verdict, it would not have entertained, in all likelihood, additional arguments as to why plaintiff’s action on the bond should be rejected; the settlement was premised on the directed verdict. We conclude that Capitol was not required to raise the issue in the first appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacOmb Mechanical Inc v. Lasalle Group Inc
Michigan Court of Appeals, 2015
Northline Excavating, Inc. v. Livingston County
839 N.W.2d 693 (Michigan Court of Appeals, 2013)
State Bar of California v. Statile
168 Cal. App. 4th 650 (California Court of Appeal, 2008)
City of Ferndale v. Florence Cement Co.
712 N.W.2d 522 (Michigan Court of Appeals, 2006)
McGirt v. Royal Insurance Co. of America
399 F. Supp. 2d 655 (D. Maryland, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
677 N.W.2d 51, 260 Mich. App. 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/will-h-hall-son-inc-v-ace-masonry-construction-inc-michctapp-2004.