Sandusky Grain Co. v. Borden's Condensed Milk Co.

183 N.W. 218, 214 Mich. 306, 1921 Mich. LEXIS 660
CourtMichigan Supreme Court
DecidedJune 6, 1921
DocketDocket No. 88
StatusPublished
Cited by21 cases

This text of 183 N.W. 218 (Sandusky Grain Co. v. Borden's Condensed Milk Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sandusky Grain Co. v. Borden's Condensed Milk Co., 183 N.W. 218, 214 Mich. 306, 1921 Mich. LEXIS 660 (Mich. 1921).

Opinion

Fellows, J.

On April 12, 1917, defendant Borden’s Condensed Milk Company entered into a contract with defendant Covell Construction Company for the erection of a condensing plant at Sandusky. The contract price was $65,400; there were extras to. the amount of $443.48. The Covell company was to furnish the material and do the work. The specifications, made a part of the contract, contained the following:

“Bond.
“The contractor is to' give a bond payable to the company for the full amount of his contract to assure the carrying out of all the work contracted for. Also insuring the Borden’s Condensed Milk Co. against any loss due to defective materials or workmanship for a period of one (1) year.
[310]*310“All- work covered by these specifications- to be completed within four (4) months from date of signing contract.”

Defendant Maryland Casualty Company became surety on the Covell company’s bond. It was a contractor’s bond running to the Borden company. It contained among others the following clause:

"Fourth. That the obligee shall faithfully perform all the terms, covenants and conditions of such contract on the part of the obligee to be performed; and shall also retain that proportion, if any, which such contract specifies the obligee shall or may retain of the value of all work performed or materials furnished in the prosecution of such contract (not less, however, in any event, than ten per centum of such value) until the complete performance by the principal of all the terms, covenants and conditions of said contract on the principal’s part to be performed, and until the expiration of the time within which liens or notices of liens may be filed, and until the discharge of such liens, if any; and the obligee shall at all times observe and' conform to the laws relating to liens of the State wherein said contract is to be performed. That the plans and specifications mentioned in said contract are not in any respect defective, and are and at all times will be kept adequate for the complete performance of such contract, and that no change shall be made in such plans and specifications which shall increase the amount to be paid the principal more than ten per centum of the penalty of this instrument, without the written consent of the surety.”

The Covell company commenced the work of constructing the plant and continued such work until October 12th when a receiver was appointed for it and the job abandoned. The Borden company had at that time paid the Covell company $48,141.33, but $39,095.41 of which was used on the Borden job by the Covell company, and but $37,610.41 of which had gone to pay for material and labor. All the payments had been made by the Borden company without re[311]*311quiring of the contractor the affidavit provided for by the mechanic’s lien law (3 Comp. Laws 1915, § 14799). There was no provision in the contract for payment upon architect’s certificates but the contract provided for payment on the first of each month of 90 per cent, of the labor performed and material delivered and erected. The Borden company completed the building. Numerous liens were filed. One of the lienors, plaintiff Sandusky Grain Company, filed its bill. Within a f éw days another lienor, Ionia Hardware Company, did likewise. The two suits were consolidated. The other lienors came into the case asserting their liens by proper pleadings, and defendant Borden Company brought the casualty company into the case. A decree in favor of numerous lienors, and in favor of the Borden’company and against the casualty company is here reviewed by the Borden company and the casualty company. The claims of the respective parties and the facts necessary to their understanding will be given only in so far as it becomes important to an understanding of the case and the grounds upon which it is disposed of.

Appeal of Maryland Casualty Co. The casualty company is a corporation engaged in the business of becoming surety for compensation. It is not a gratuitous surety and may not invoke the rule of strictissimi juris. People v. Bowen, 187 Mich. 257; People v. Traves, 188 Mich. 415; Ladies of Maccabees v. Surety Co., 196 Mich. 27. But it is not deprived of the right to contract or to the benefit of contracts made. Courts may not arbitrarily read provisions out of or into its contracts in order to make it liable, or make new contracts for it and the obligees. Its business is in the nature of insurance and courts in the construction of its contracts usually invoke rules applicable to contracts of insurance. The bond in the instant case was a contractor’s bond, a builder’s [312]*312bond, the obligee was the owner; it was not a material-man’s or laborer’s bond. The Borden company is here seeking to recover upon it for its own benefit.

We shall consider but one claim of the casualty company which may be thus summarized: By the terms of the fourth clause of the bond above quoted the obligee Borden company was to observe and conform to the mechanic’s lien laws of the State; it did not do so; it did not require the contractor to furnish the affidavit provided for in section 14799, 3 Comp. Laws 1915; nor did the money paid by it all go to liquidate the claims of the materialmen and laborers, but upwards of $10,000 of the sum so paid was not so applied; that this was a voluntary payment, beyond what the contractor was entitled to receive or the owner obliged to pay and released the surety.

We have spent considerable time in independent research upon this question and in order that such labor shall not be entirely lost to the profession, we shall at the expense of prolixity consider a number of the cases which such research has revealed together with those to which our attention has been called by counsel. Our attention is challenged by counsel to numerous decisions arising under Act No. 187, Pub. Acts 1905 (3 Comp. Laws 1915, § 14827). A brief consideration of some of these cases will suffice. In People v. Finn, 162 Mich. 481, the “use” plaintiff was held to be a sub-contractor, the notice required under section 2 (§ 14828) had not been given, the sureties were gratuitous sureties, and liability was denied. In People v. Connell, 195 Mich. 77, the surety was a compensated one; a notice not in all regards complying with section 2 had been given but the surety was in no way injured by such failure and liability was sustained. People v. Traves, supra, was quite similar. The object of section 2 was regarded as conjectural, the surety was a [313]*313compensated one, and was not harmed by the failure to give timely notice and liability was sustained.

In Doyle v. Faust, 187 Mich. 108, one angle of the question now before us was expressly reserved. It was there said:

“What the rule should be in a case, where it appeared that payments made to the contractors were in the nature of profits and retained by them, we need not decide. -It does not appear that all money paid was not used to liquidate demands for which, if unliquidated, the appellant would be liable.”

In Marquette Opera House Building Co. v. Wilson, 109 Mich. 223, it was said by this court, speaking through Mr. Justice Montgomery:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Donna Walker v. Otis M Underwood Jr
Michigan Court of Appeals, 2017
Coburn v. Coburn
583 N.W.2d 490 (Michigan Court of Appeals, 1998)
Georgia-Pacific Corp. v. Central Park North Co.
228 N.W.2d 380 (Michigan Supreme Court, 1975)
Georgia-Pacific Corp. v. Central Park North Co.
204 N.W.2d 321 (Michigan Court of Appeals, 1972)
Lake States Engineering Corp. v. Lawrence Seaway Corp.
167 N.W.2d 320 (Michigan Court of Appeals, 1969)
Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)
Strom Construction Co. v. Raymond
95 N.W.2d 879 (Michigan Supreme Court, 1959)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
Hot Springs Plumbing & Heating Co. v. Wallace
27 P.2d 984 (New Mexico Supreme Court, 1933)
Horne-Wilson, Inc. v. . Wiggins Bros., Inc.
164 S.E. 365 (Supreme Court of North Carolina, 1932)
Maxwell Lumber Co. v. Connelly
287 P. 64 (New Mexico Supreme Court, 1930)
Usiak v. Kubiak
225 N.W. 168 (Wisconsin Supreme Court, 1929)
Park v. Brunswick-Balke-Collender Co.
209 N.W. 188 (Michigan Supreme Court, 1926)
Fidelity & Casualty Co. v. Livingston
208 N.W. 446 (Michigan Supreme Court, 1926)
Sterling Bank of Sleeper & Chamberlain v. Scott
204 N.W. 135 (Michigan Supreme Court, 1925)
Hamtramck Lumber & Supply Co. v. United Home Builders
192 N.W. 575 (Michigan Supreme Court, 1923)
Ypsilanti Lumber & Coal Co. v. Leslie
188 N.W. 395 (Michigan Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
183 N.W. 218, 214 Mich. 306, 1921 Mich. LEXIS 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sandusky-grain-co-v-bordens-condensed-milk-co-mich-1921.