Strom Construction Co. v. Raymond

95 N.W.2d 879, 356 Mich. 79, 1959 Mich. LEXIS 357
CourtMichigan Supreme Court
DecidedApril 13, 1959
DocketDocket 71, 72, Calendar 47,763, 47,764
StatusPublished
Cited by3 cases

This text of 95 N.W.2d 879 (Strom Construction Co. v. Raymond) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Strom Construction Co. v. Raymond, 95 N.W.2d 879, 356 Mich. 79, 1959 Mich. LEXIS 357 (Mich. 1959).

Opinion

Dethmers, C. J.

Defendant William Raymond owned real estate on which he desired to build a track and facilities for conducting automobile races. Defendants Wierenga put in the race track. In pay *81 ment, Raymond and wife gave them 2 mortgages on the property, the first dated June 12, 1953, recorded June 24, 1953, and the second dated September 12, 1953, recorded October 1, 1953. Raymond engaged plaintiff Strom Construction Company, hereinafter called plaintiff, to construct a shell consisting of a concrete crash wall along the track, 2 concrete end walls and a side wall of concrete blocks. The shell was to serve as the foundation or base for a grandstand, to consist of steel bleachers on a steel framework.

Plaintiff commenced work on the shell on June 8, 1953, and finished it on July 7, 1953. The end walls of the shell were not of a uniform height from one end to the other, but were stepped up to permit a passageway at the foot of the grandstand. There was to be no roof over the shell, partly because that would have increased insurance rates. After completion of the shell a roof could not have been added without major changes on the walls. Raymond had no intention of making a building of it.

On September 1, 1953, plaintiff filed its statement of account and lien in the office of the register of deeds and on October 20, 1953, filed its bill of complaint to forclose that lien.

After plaintiff had completed the shell, Raymond abandoned the idea of erecting a steel grandstand on it. Instead, he had wooden bleachers built on the opposite side of the track. After that, there was nothing further to be done on the project as Raymond planned it at that time. He opened the gates and conducted races there.

Later in the fall of 1953 an auctioneer proposed to Raymond that the shell be converted into a building by covering it with a roof and installing windows, doors, a heating system and other details, so that it could be used as a place for selling automobiles at auction. Raymond decided to do so. For that pur *82 pose defendant Cascade Lumber Company, hereinafter called defendant, furnished materials between November 28, 1953, and January 12, 1954. Sievers, plaintiff in the second suit, performed the labor, from December 18, 1953, to February 5, 1954, in constructing the roof and building and installing window frames, doors, et cetera. In order to build the roof, it was necessary to run a beam across the 200-foot length of the shell supported by the end walls and 4 upright timbers set upon concrete footings in the ground. The joists used to support the ceiling or roof could not have been used to support bleachers in a grandstand.

Defendant filed with the register of deeds a statement of account and lien on March 9, 1954, and Sievers did likewise on March 15, 1954. On June 28, 1954, Sievers brought suit to foreclose his lien. The 2 cases were consolidated for trial.

The trial court held the mentioned liens and mortgages, together with another mortgage given defendant Hulbert after plaintiff’s lien had attached, to be simultaneous mortgages under the mechanics’ liens act and decreed that the premises be sold and the proceeds distributed pro rata among the holders of them.

Plaintiff alone appeals, contending that its lien is entitled to priority over the other claims. There is no cross appeal on file in this Court. Briefs have been filed only on behalf of plaintiff and defendant.

Controlling provisions of the statute are contained in parts First and Fourth of CL 1948, § 570.9 (Stat Ann 1953 Rev §26.289), which read:

“First, As between persons claiming liens under this statute, the several liens upon the same property attaching by reason of work, labor or materials furnished in carrying forward or completing the same building or buildings, machinery, structure or im *83 provement, shall he deemed simultaneous mortgages. * #

“Fourth, The liens for such labor or materials furnished, including those for additions, repairs and betterments, shall attach to the buildings, machinery, erection, structure, or improvement for which they are furnished or done, subject to any prior recorded title, claim, lien, incumbrance, or mortgage to or upon the land upon which such building or buildings, machinery, erection, structure or improvement belongs or is put. Any person holding a lien for such labor or materials furnished upon any premises subject to any prior recorded lien, incumbrance or mortgage may pay off any such prior lien, incumbrance or mortgage, and shall thereupon he subrogated to all the rights of the prior holder of such lien, incum-brance or mortgage.”

As presented on appeal here, the only issue is whether plaintiff’s lien takes precedence over the other liens and mortgages. This gives rise to the question whether plaintiff’s construction of the shell and Sievers’ and defendant’s furnishing of labor and materials for converting it into a building constituted “labor or materials furnished in carrying forward or completing the same building, * * * structure or improvement.” In its opinion the trial court said that “the structure was the same although its purpose and use were drastically altered.” It based its holding on what it denominated the spirit and principle of the mechanics’ lien law as expressed in McClintic-Marshall Co. v. Ford Motor Co., 254 Mich 305, 311 (77 ALR 807), in the following dicta:

“The mechanics’ lien law * * * is framed upon the theory that those who perform work or furnish material which enters into and enhances the value of improvements on real estate are entitled to a preferred claim against and a lien upon the specific property presumably bettered by the performance' of such labor and the furnishing of such materials ? *84 the security of attaching creditors and mortgagees being so enhanced in value thereby that they are not prejudiced.”

It was the court’s view that both plaintiff and defendant had contributed to the improvements and “presumably bettered” them, and that the value thereof was presumably enhanced, by defendant’s furnishing of materials, in an amount equal to the total of its claim therefor, and, hence, that plaintiff is not prejudiced by treating the liens of both as simultaneous. Indiscriminate application of that “presumably bettered” doctrine as the basis for holding subsequent liens simultaneous with prior ones would render meaningless the provision of part Fourth of the above section of the statute which makes subsequent liens subject to prior liens. We may not so emasculate it. The problem, then, is whether plaintiff’s lien was “prior,” within the meaning of part Fourth, or “simultaneous,” under part First. It was prior in the respect that it had attached, upon plaintiff’s commencement of work, and a statement thereof had been filed before defendant’s lien came into being. It was prior, therefore, unless made simultaneous by the provisions of part First. That brings us back to the question whether the liens attached by reason of labor or materials furnished in carrying forward or completing the same building, structure or improvement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M D Marinich, Inc v. Michigan National Bank
484 N.W.2d 738 (Michigan Court of Appeals, 1992)
Hodgins v. Marquette Iron Mining Co.
503 F. Supp. 88 (W.D. Michigan, 1980)
Williams & Works, Inc. v. Springfield Corp.
257 N.W.2d 160 (Michigan Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.W.2d 879, 356 Mich. 79, 1959 Mich. LEXIS 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/strom-construction-co-v-raymond-mich-1959.