M D Marinich, Inc v. Michigan National Bank

484 N.W.2d 738, 193 Mich. App. 447, 1992 Mich. App. LEXIS 133
CourtMichigan Court of Appeals
DecidedApril 6, 1992
DocketDocket 132193
StatusPublished
Cited by14 cases

This text of 484 N.W.2d 738 (M D Marinich, Inc v. Michigan National Bank) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M D Marinich, Inc v. Michigan National Bank, 484 N.W.2d 738, 193 Mich. App. 447, 1992 Mich. App. LEXIS 133 (Mich. Ct. App. 1992).

Opinion

Connor, J.

Defendant Michigan National Bank appeals as of right from the trial court’s judgment of August 9, 1990, declaring that plaintiff had a valid construction lien against real property and that the lien was superior to defendant’s mortgage under the priority provisions of the Construction Lien Act, MCL 570.1101 et seq.; MSA 26.316(101) et seq. The trial court decided this case without a jury after hearing testimony on April 12 and 17, 1990. We affirm the trial court’s decision.

i

The competing liens in this case were for a construction project involving the White Swan Building on Catherine Street in Ann Arbor, Michigan, space in which was leased for commercial use. The building was owned by White Swan Limited Partnership (wslp). Catherine Street Construction Company (cscc) initially served as the general contractor on the project beginning in January 1985.

Defendant agreed to finance the construction of the building. The senior loan officer involved in *449 the negotiations described the project proposed by wslp as a rehabilitation of the existing building and an addition to the existing building on the north side, wslp requested $1.2 million for the entire project, but defendant approved a loan of only $500,000 to cover the cost of rehabilitating the existing structure. Defendant postponed approval of the remainder of the loan request until the initial work was completed and the space in the existing structure was leased. Work on the basement was not included in defendant’s agreement to finance construction. Defendant relied on a contract between wslp and cscc, dated April 1, 1985, to close on the loan. It was conceded by defendant’s representative, however, that this contract included a provision for changes to be made in the agreement and that such changes in contracts were not unusual in the construction business. Moreover, at the time defendant was negotiating this loan, its representative did inspect the property and, although he could not recall conclusively, he believed that work had probably already begun on the construction. Defendant filed and recorded its mortgage on the property for $500,000 on June 4, 1985.

Plaintiff, a general contractor, was contacted sometime in November 1985 to take over and complete this project in place of cscc and correct work already performed. Plaintiffs contract with the owners was an oral one.

Plaintiffs president, Michael Marinich, who had participated in the negotiations, testified regarding the terms of the contract and the work plaintiff agreed to perform. According to Marinich, the agreement was for plaintiff to do the entire project, including weatherproofing the building, repairing work already done that was in violation of building codes or did not please existing tenants, *450 working on the architectural plans for feasibility, proceeding with plans to build an addition to the north end of the building, and completing the building as economically as possible. Work actually performed by plaintiff on the addition was primarily limited to preparing new architectural drawings and building plans when the old ones were not feasible. The majority of work on the construction project had been completed by June 1986, with the first and third floors being leased. Only minor work was done on the basement at that point.

Although the original plans called for the basement to be used as leased retail space in late 1986, plaintiff was informed that the basement would instead be used as additional leased office space for a then current tenant. Plaintiff performed the necessary work to accomplish this change, which included revising the floor plans, partitioning areas, and accommodating mechanical services in the basement. While the revisions made in the basement plans required a new building permit, Marinich indicated that it was common for plans to change during the course of work, and this change was merely part of the entire construction project. In Marinich’s opinion, it was consistent with industry practice to honor modifications in the scope of the work to be performed pursuant to contract.

Work was still in progress on the basement when plaintiff stopped working some time in February 1987 because the entire project appeared to be "dead in the water.” The work was interrupted before plaintiff could build the addition.

Plaintiff filed a construction lien against the property on April 2, 1987, in the amount of $55,647.19.

Plaintiff filed this action, seeking foreclosure and *451 sale of the property in satisfaction of its lien among other remedies. The parties stipulated to many facts, and most of the issues were resolved by summary disposition. It remained for the court to determine which of the two liens, plaintiffs construction lien or defendant’s mortgage, had priority. The trial court conducted an evidentiary hearing and held that plaintiffs construction lien related back to the first actual physical improvement made on the project in January 1985, which gave plaintiff priority under MCL 570.1119(3); MSA 26.316(119)(3) over defendant’s subsequently recorded mortgage.

ii

The primary issue raised before this Court is whether plaintiffs construction lien had priority over defendant’s mortgage. The resolution of this issue depends on whether plaintiffs construction lien, when determining priority, relates back to the date of the commencement of construction by the first general contractor in January, 1985. Defendant contends that its mortgage, which was recorded on June 4, 1985, should take priority over plaintiffs lien because plaintiff, the second general contractor, did not personally contract to take over the project until November 1985 and did not personally commence building until 1986. Defendant additionally argues that plaintiff had more than one contract for work on this project and that plaintiffs liens only have priority over defendant’s mortgage from the date plaintiffs work began with regard to each of the contracts and only to the extent that plaintiff completed the work.

hi

Resolution of the issue raised on appeal requires *452 this Court to interpret and apply the Construction Lien Act, as enacted by 1980 PA 497 and as amended by 1981 PA 191, MCL 570.1101 et seq.; MSA 26.316 et seq. The cardinal rule of statutory construction is to give effect to the Legislature’s intent. Melia v Employment Security Comm, 346 Mich 544, 562; 78 NW2d 273 (1956); Kizer v Livingston Co Bd of Comm’rs, 38 Mich App 239, 246; 195 NW2d 884 (1972). In order to ascertain and give effect to legislative intent, the changes in the act must be construed in light of preceding statutes and the historical legal development of mechanics’ or construction liens.

The development of this area of the law before 1958 was discussed by the Michigan Supreme Court in Williams & Works, Inc v Springfield Corp, 408 Mich 732, 740-743; 293 NW2d 304 (1980). Under prior statutes and case law, the commencement of a building provided notice to all parties of the existence of mechanics’ liens emanating from work performed in the construction of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farrow Group Inc v. Ethan D Dunn
Michigan Court of Appeals, 2023
C D Barnes Associates Inc. v. Star Heaven, LLC
834 N.W.2d 878 (Michigan Court of Appeals, 2013)
Jeddo Drywall, Inc. v. Cambridge Investment Group Inc.
810 N.W.2d 633 (Michigan Court of Appeals, 2011)
Michigan Pipe & Valve-Lansing, Inc. v. Hebeler Enterprises, Inc.
808 N.W.2d 323 (Michigan Court of Appeals, 2011)
Cameron v. Auto Club Ins. Ass'n
687 N.W.2d 354 (Michigan Court of Appeals, 2004)
Advanta National Bank v. McClarty
667 N.W.2d 880 (Michigan Court of Appeals, 2003)
B & D Drywall Supply, Inc. v. Eyde Construction Co.
287 B.R. 676 (E.D. Michigan, 2001)
In Re Brown
287 B.R. 676 (E.D. Michigan, 2001)
Pitsch v. Ese Michigan, Inc
593 N.W.2d 565 (Michigan Court of Appeals, 1999)
Old Kent Bank v. Whitaker Construction Co.
566 N.W.2d 1 (Michigan Court of Appeals, 1997)
Vugterveen Systems, Inc. v. Olde Millpond Corp.
560 N.W.2d 43 (Michigan Supreme Court, 1997)
Indenbaum v. Michigan Board of Medicine
539 N.W.2d 574 (Michigan Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
484 N.W.2d 738, 193 Mich. App. 447, 1992 Mich. App. LEXIS 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-d-marinich-inc-v-michigan-national-bank-michctapp-1992.