Farrow Group Inc v. Ethan D Dunn

CourtMichigan Court of Appeals
DecidedAugust 17, 2023
Docket361465
StatusUnpublished

This text of Farrow Group Inc v. Ethan D Dunn (Farrow Group Inc v. Ethan D Dunn) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrow Group Inc v. Ethan D Dunn, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

FARROW GROUP, INC., UNPUBLISHED August 17, 2023 Plaintiff-Appellant,

v No. 361465 Wayne Circuit Court ETHAN D. DUNN, JOSHUA C. CASTMORE, and LC No. 20-010870-NM MAXWELL DUNN, PLC,

Defendants-Appellees.

Before: REDFORD, P.J., and K. F. KELLY and RICK, JJ.

PER CURIAM.

Plaintiff, Farrow Group, Inc., appeals by right the trial court’s order granting defendants, attorneys Ethan D. Dunn, Joshua C. Castmore, and law firm Maxwell Dunn, PLC, summary disposition of plaintiff’s legal malpractice claim brought after plaintiff accepted the case evaluation award in its underlying lawsuit against North Corktown Venture, LLC (NCV), because defendants recommended plaintiff accept it and incorrectly advised plaintiff that its equitable claims in that action would remain for adjudication but were dismissed with prejudice upon acceptance. Defendants admitted in this action that they provided incorrect advice in the underlying action and breached the applicable standard of care, but defended on the ground that plaintiff could not prove that defendants’ malpractice proximately caused it damages. Because we conclude there are numerous questions of fact, the trial court erred when it granted defendants’ motion for summary disposition. We therefore reverse.

I. BACKGROUND FACTS

Plaintiff contracted with NCV to demolish buildings located at 3300 Trumbull, Detroit, Michigan, remove debris, and clean the site. The contract identified Odell Jones, III, of DH Construction Management, LLC, as the dispute resolution “Initial Decision Maker” and as the owner’s representative, and Michael Farrow as plaintiff’s representative. Section 14 of the contract permitted NCV to terminate for cause or for convenience. Section 14.1.3 provided the consequence of termination for convenience:

-1- If the Owner terminates the Contract for convenience in accordance with Article 14 of AIA Document A201-2017, then the Owner shall pay the Contractor a termination fee as follows:

* * *

Contractor shall be entitled to fifteen percent (15%) of the costs to complete the Work, in accordance with the same requirements imposed prior to termination, as estimated by the Owner’s Representative or an agreed upon third-party.

Article 16 of the contract enumerated the contract documents and § 16.1 specified that the agreement had multiple documents including under § 16.1.3 that AIA Document A201-2017, General Conditions of the Contract for Construction applied. The AIA Document A201-2017, General Conditions of the Contract for Construction document provided in Article 10, that the contractor shall take reasonable precautions for safety and shall protect against damage, injury, or loss to persons who may be affected and other adjacent properties such as walks, pavements, roadways, structures, and utilities. § 10.2.1.1-.3. Further, the contractor had an ongoing obligation to comply with all “applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities bearing on the safety of persons or property or their protection from damage, injury or loss. § 10.2.2. Under § 14.3 of the AIA Document A201-2017, General Conditions of the Contract for Construction document, the owner could give notice in writing and “suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.” Section 14.4 provided that the owner could terminate the contract for convenience and stated as follows:

§ 14.4.1 The Owner may, at any time, terminate the Contract for the Owner’s convenience and without cause.

§ 14.4.2 Upon receipt of written notice from the Owner of such termination for the Owner’s convenience, the Contractor shall

.1 cease operations as directed by the Owner in the notice;

.2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work; and

.3 Except for Work directed to be performed prior to the effective date of termination stated in the notice, terminate all existing subcontracts and purchase orders and enter into no further subcontracts and purchase orders.

§ 14.4.3 In case of such termination for the Owner’s convenience, the Contractor shall be entitled to receive payment for Work executed, and costs incurred by reason of such termination, along with reasonable overhead and profit on the Work not executed.

The City of Detroit Buildings, Safety Engineering and Environmental Department issued a wrecking permit for plaintiff’s demolition, debris removal, and backfilling to grade level of the 3300 Trumbull property, on August 16, 2017, with an expiration date of February 16, 2018.

-2- Plaintiff commenced work and proceeded with the project. On January 24, 2018, Jones told Farrow that NCV issued a stop work order to plaintiff because of budget issues. Barry Ellentuck, who owned ADR Consultants, Inc., a company retained by plaintiff to assist with project management, corresponded with Jones via e-mail advising him that, because of the demolition permit, plaintiff had the obligation to complete the work to Detroit’s specifications. Ellentuck stated that work on the site had to resume on Monday February 19, 2018. Plaintiff resumed working on-site and NCV terminated the contract for convenience. Jones e-mailed Farrow to advise him of the contract’s termination. Ellentuck corresponded with Jones regarding issues related to unpaid invoices, the condition of the site, and that plaintiff could not simply abandon the site without consequences to itself and NCV. Plaintiff worked until it considered the site safe for its demobilization and departure from the site. Plaintiff invoiced NCV for work performed at the property but NCV did not pay. Plaintiff and NCV disputed whether plaintiff should have continued under the circumstances and what NCV owed plaintiff. On April 16, 2018, plaintiff asserted a claim of lien against the 3300 Trumbull property and recorded a construction lien in the amount of $536,778.65.

In May 2018, plaintiff sued NCV to foreclose its construction lien against the 3300 Trumbull property related to NCV’s failure to pay the balance due for the labor and materials to perform demolition services on the property. In addition to its lien foreclosure claim, plaintiff also asserted a claim for unjust enrichment and a breach of contract claim. Plaintiff alleged that NCV owed it $536,778.65, plus 15% of the costs to complete the work required under the contract, pursuant to § 14.1.3 of the contract.

The court required the case be submitted to case evaluation. Just before the case evaluation hearing, defendants substituted into the case as plaintiff’s counsel in the underlying action. Castmore represented plaintiff at the case evaluation hearing. The case evaluators issued their case evaluation decision and awarded plaintiff $175,000. Defendants advised plaintiff to accept the case evaluation award. Plaintiff did so, believing defendants’ advice that its equitable claims would remain for adjudication after acceptance of the case evaluation award. NCV also accepted the case evaluation decision. The court in the underlying action dismissed plaintiff’s case in its entirety with prejudice.

On August 24, 2020, plaintiff filed this legal malpractice action against defendants alleging that, based upon defendants’ professionally negligent advice that it could accept the case evaluation award in the underlying action and pursue its equitable claims against NCV, plaintiff accepted the case evaluation award. Plaintiff alleged that the court ruled that the mutual acceptance of the award ended the underlying litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph v. Auto Club Insurance Association
815 N.W.2d 412 (Michigan Supreme Court, 2012)
Loweke v. Ann Arbor Ceiling & Partition Co, LLC
809 N.W.2d 553 (Michigan Supreme Court, 2011)
Allison v. AEW CAPITAL MANAGEMENT, LLP
751 N.W.2d 8 (Michigan Supreme Court, 2008)
Holton v. A+ Insurance Associates, Inc
661 N.W.2d 248 (Michigan Court of Appeals, 2003)
Patterson v. Kleiman
526 N.W.2d 879 (Michigan Supreme Court, 1994)
Walker & Company v. Harrison
81 N.W.2d 352 (Michigan Supreme Court, 1957)
M D Marinich, Inc v. Michigan National Bank
484 N.W.2d 738 (Michigan Court of Appeals, 1992)
Skinner v. Square D Co.
516 N.W.2d 475 (Michigan Supreme Court, 1994)
Weymers v. Khera
563 N.W.2d 647 (Michigan Supreme Court, 1997)
Dalley v. Dykema Gossett PLLC
788 N.W.2d 679 (Michigan Court of Appeals, 2010)
Charles Reinhart Co. v. Winiemko
513 N.W.2d 773 (Michigan Supreme Court, 1994)
Baker v. Arbor Drugs, Inc
544 N.W.2d 727 (Michigan Court of Appeals, 1996)
Colbert v. Conybeare Law Office
609 N.W.2d 208 (Michigan Court of Appeals, 2000)
Omnicom of Michigan v. Giannetti Investment Co.
561 N.W.2d 138 (Michigan Court of Appeals, 1997)
Simko v. Blake
532 N.W.2d 842 (Michigan Supreme Court, 1995)
Madugula v. Taub
853 N.W.2d 75 (Michigan Supreme Court, 2014)
Doe v. Henry Ford Health System
308 Mich. App. 592 (Michigan Court of Appeals, 2014)
New Products Corporation v. Harbor Shores Bhbt Land Development
866 N.W.2d 850 (Michigan Court of Appeals, 2014)
Bowden v. Gannaway
871 N.W.2d 893 (Michigan Court of Appeals, 2015)
Bank of America Na v. First American Title Insurance Company
878 N.W.2d 816 (Michigan Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Farrow Group Inc v. Ethan D Dunn, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrow-group-inc-v-ethan-d-dunn-michctapp-2023.