C D Barnes Associates Inc. v. Star Heaven, LLC

834 N.W.2d 878, 300 Mich. App. 389
CourtMichigan Court of Appeals
DecidedApril 11, 2013
DocketDocket No. 300263
StatusPublished
Cited by56 cases

This text of 834 N.W.2d 878 (C D Barnes Associates Inc. v. Star Heaven, LLC) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C D Barnes Associates Inc. v. Star Heaven, LLC, 834 N.W.2d 878, 300 Mich. App. 389 (Mich. Ct. App. 2013).

Opinion

WILDER, P.J.

Defendant Flagstar Bank, FSB, appeals by leave granted an August 27, 2011, judgment that established that the construction lien of C. D. Barnes Associates, Inc., was valid for its full amount and had priority over Flagstar’s mortgage interest. We affirm the construction lien judgment in favor of Barnes, affirm in part and reverse in part the award of attorney fees to Barnes, and remand this case.

I. BASIC FACTS

This action arises out of a failed construction project undertaken by defendant Star Heaven, L.L.C., for which Flagstar provided mortgage financing and Barnes served as the general contractor.

The pertinent facts are largely undisputed. In February 2005, Star Heaven purchased a partially completed apartment project in Grand Haven. At the time of acquisition, the property consisted of 19 buildings, each containing, or planned to contain, 10 apartment units of varying sizes, along with a pool and a clubhouse, all in different stages of completion.

After Star Heaven acquired the site, it began to market the project as a “high-end condominium project” and eventually changed the name to “Grand Haven Club.” In July 2005, Star Heaven hired Barnes to finish construction of the 19 buildings on the site and perform upgrades to some of the existing units and structures consistent with the new vision for the project. Barnes submitted a fixed-price contract to Star Heaven for the work to be performed, but because of uncertainty about the configuration of the units to be constructed as the project progressed, Barnes and Star Heaven instead entered into a time and materials agreement under which Barnes was to submit monthly invoices with supporting documentation to Star Heaven [396]*396for work performed at the site and Star Heaven was to pay each application for payment within 30 days of its receipt.

Barnes performed its first physical improvement to the property for Star Heaven on or about August 10, 2005. On October 4, 2005, Star Heaven filed a notice of commencement as described by MCL 570.1108, which is § 108 of the Construction Lien Act, MCL 570.1101 et seq.

On May 2, 2006, at Star Heaven’s request, Barnes executed a sworn statement that represented that, as of that date, the subject property was “free from claims of construction liens.” On May 16, 2006, Star Heaven recorded the master deed for the new condominium project. Shortly thereafter, Flagstar’s loans to Star Heaven closed. Flagstar recorded its mortgage on May 23, 2006.

In May and October 2007, Star Heaven filed amended master deeds for the project, which changed the name of the condominium to “Grand Haven Club,” amended the total acreage included in the property, redesignated the property into Units 1 to 40 and added Units 41 to 60 to the project.

During the course of the project, Barnes submitted 27 applications for payment to Star Heaven, which totaled approximately $3.11 million. Star Heaven paid the first 20 invoices, leaving 7 invoices totaling $360,909.11 unpaid. Before ceasing work for nonpayment, Barnes completely enclosed all 19 buildings, with two of the buildings achieving “occupancy” status, and another 11 or 12 of the buildings being completed to “white box[]” condition, such that each unit in each building was complete with all mechanical, electrical, and plumbing and was “roughed-in” with drywall. Star Heaven never expressed any concerns with the work [397]*397that was performed at the site; the explanation for late or slow payments was always an inability to pay.

Barnes last provided labor and materials to the site on March 5, 2008. On May 8, 2008, Barnes recorded nine separate claims of lien, in the amount of $360,909.11. Six of these claims of lien referred to particular individual unit numbers within the project. The three remaining claims were filed against the overall project. Each of the three liens filed against the project referred to the last day on which Barnes provided any work to the “overall project,” and each used a metes and bounds description encompassing the entire property set forth in the 2005 notice of commencement; they did not refer to the dates on which labor or materials were provided to any individual condominium unit within the project.

On December 31, 2008, Star Heaven assigned all of its interests in the property to David Findling, for the purpose of liquidating the assets and distributing the proceeds to creditors according to applicable statutes.

On May 8, 2009, Barnes filed the instant complaint, seeking to foreclose on its claims of lien under the Construction Lien Act and alleging claims of breach of contract and unjust enrichment against Star Heaven and Findling. Flagstar contested the priority of Barnes’s construction lien over its mortgage.

On December 24, 2009, a default was entered against Star Heaven. Thereafter, on December 28, 2009, Barnes moved for partial summary disposition on the issue of the priority of its lien over the Flagstar mortgage. Barnes argued that because there was no issue of material fact that Barnes’s first day of actual physical improvement to the property predated the recording of Flagstar’s mortgage, its liens had priority over the Flagstar mortgage. Barnes also asserted in support of [398]*398its motion that, in response to discovery requests, Flagstar disclosed no facts and produced no documents contesting the priority of the construction lien.

Flagstar argued that summary disposition was premature because discovery was not set to close until April 23, 2010, and additional discovery stood a fair chance of uncovering evidence to challenge the priority of Barnes’s lien over the mortgage. Flagstar explained that its loan officer who oversaw the closing of the loan between Flagstar and Star Heaven was no longer with the company and consequently was not available to provide the details of the circumstances surrounding the closing of the loan. Flagstar further stated that the documents supporting the closing of the loan had moved several times over the 3V2 years since the loan’s closing, “which has made securing documentation to support that obligation difficult.” Flagstar assured the trial court that it would continue to work to locate additional information.

On January 18, 2010, the trial court held a hearing on Barnes’s motion for summary disposition, during which the parties reiterated the positions set forth in their briefs. Barnes asserted the priority of its lien on the basis of the facts before the trial court, and it argued that under the circumstances, and considering the length of time it took to get all parties properly served, Flagstar had more than sufficient time to conduct discovery. Flagstar acknowledged that the evidence submitted suggested that Barnes’s construction lien could have priority, but it also asserted that this view was the result of an incomplete picture because “it is reasonable to believe that additional documentation exists that supports Flagstar’s position that a subordination agreement may have been executed at the time of the closing of this loan.” Counsel for Flagstar admit[399]*399ted that he had not been able to “track . . . down” the loan officer who closed the loan or locate what he believed to be the complete documentation relating to the closing of the loan. Counsel explained that there were “two factors that suggest that [a subordination] agreement may exist”:

First of all, it’s an eight-million-dollar construction loan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re D E Jones Minor
Michigan Court of Appeals, 2026
Amy Scotto-Divetta v. Ann Kawaske
Michigan Court of Appeals, 2025
Jamie M Treadway v. Joseph C Treadway Jr
Michigan Court of Appeals, 2025
20250127_C366630_42_366630P.Opn.Pdf
Michigan Court of Appeals, 2025
Melanie Culp v. John Trimberger
Michigan Court of Appeals, 2024
Antonio Lasala v. Blue Water Beagle Club
Michigan Court of Appeals, 2024
Jaunice Kellar v. Roderic Horton
Michigan Court of Appeals, 2024
Patricia Tyler v. Kalamazoo Public Schools
Michigan Court of Appeals, 2024
Strata Oncology Inc v. Department of Treasury
Michigan Court of Appeals, 2023
In Re Dorothy Marie Talanda Trust
Michigan Court of Appeals, 2023
O in Re Baby Boy Doe
Michigan Court of Appeals, 2022
In Re McLin Minors
Michigan Court of Appeals, 2022
Mjcc 8 Mile LLC v. Basrah Custom Design Inc
Michigan Court of Appeals, 2022
Akf Inc v. Restoration Services Holding LLC
Michigan Court of Appeals, 2021

Cite This Page — Counsel Stack

Bluebook (online)
834 N.W.2d 878, 300 Mich. App. 389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-d-barnes-associates-inc-v-star-heaven-llc-michctapp-2013.