Northern Concrete Pipe, Inc v. Sinacola Companies—midwest, Inc

603 N.W.2d 257, 461 Mich. 316, 1999 Mich. LEXIS 2835
CourtMichigan Supreme Court
DecidedDecember 22, 1999
DocketDocket 114004
StatusPublished
Cited by35 cases

This text of 603 N.W.2d 257 (Northern Concrete Pipe, Inc v. Sinacola Companies—midwest, Inc) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Concrete Pipe, Inc v. Sinacola Companies—midwest, Inc, 603 N.W.2d 257, 461 Mich. 316, 1999 Mich. LEXIS 2835 (Mich. 1999).

Opinion

Per Curiam.

The plaintiff sought to enforce a construction lien, but the circuit court granted summary disposition to the defendants on the ground that the lien was untimely filed. The Court of Appeals reversed, finding substantial compliance with statutory requirements. We reverse in part the judgment of the Court of Appeals and reinstate the judgment of the circuit court.

i

This case concerns a construction lien 1 that was filed with regard to property owned by The R.L. Corporation. 2 The lien was filed by plaintiff Northern Concrete Pipe, Inc., a subcontractor who had pro *318 vided labor and materials to a contractor named Sinacola Midwest, Inc. 3

Such a lien must be filed within ninety days after the last date when materials or services are supplied. MCL 570.1111(1); MSA 26.316(111)(1). 4 In the present case, it is admitted that materials were last supplied on November 10, 1993. Northern Concrete Pipe mailed its lien to the Oakland County Register of Deeds less than ninety days later, 5 but it was twice returned. The lien was eventually accepted for filing after Northern Concrete Pipe supplied the complete legal description of the affected property, but the acceptance occurred on March 14, 1994, more than ninety days after November 10, 1993.

Sinacola failed to pay its subcontractor, Northern Concrete Pipe, 6 and later filed for bankruptcy.

*319 Northern Concrete Pipe filed suit against Sinacola 7 and The R.L. Corporation, asserting several theories of liability. In count I of its complaint, Northern Concrete Pipe sought to foreclose on the construction lien.

The R.L. Corporation filed a motion for summary disposition, which the circuit court granted on the ground that the lien had not been timely filed. 8

A divided panel of the Court of Appeals reversed the judgment of the circuit court. 9 The majority found that the plaintiff’s substantial compliance with the ninety-day filing deadline is sufficient in light of MCL 570.1302(1); MSA 26.316(302)(1), 10 which provides:

This act is declared to be a remedial statute, and shall be liberally construed to secure the beneficial results, intents, and purposes of this act. Substantial compliance with the provisions of this act shall be sufficient for the validity of the construction liens provided for in this act, and to give jurisdiction to the court to enforce them.

*320 Writing in dissent, Judge O’Connell urged adherence to the strict-compliance rule stated in Blackwell v Bornstein, 100 Mich App 550, 553-555; 299 NW2d 397 (1980). 11

The R.L. Corporation has applied to this Court for leave to appeal. 12 We have also received motions from the Real Property Law Section of the State Bar of Michigan and the Michigan Land Title Association to appear as amici curiae. Each urges that we reverse the judgment of the Court of Appeals because of the difficulties that will be faced by those who must determine valid title, if the ninety-day deadline for filing a construction lien is not strictly enforced. 13

n

Judge O’Connell is correct. 14 It is a cardinal rule of statutory construction that a clear and unambiguous statute warrants no further interpretation and requires full compliance with its provisions, as written. Tryc v Michigan Veterans’ Facility, 451 Mich 129, 135; 545 NW2d 642 (1996). Within the Construction Lien Act, however, the Legislature provided an *321 exception to that rule, in the form of the “substantial compliance” provision. As an exception, this provision should not be interpreted to nullify altogether the general rule that statutes should be interpreted consistent with their plain and unambiguous meaning. Richardson v Warren Consolidated School Dist, 197 Mich App 697, 702; 496 NW2d 380 (1992). In fact, this Court has already determined that the “substantial compliance” provision is limited in its application. See Brown Plumbing & Heating, Inc v Homeowner Construction Lien Recovery Fund, 442 Mich 179, 185; 500 NW2d 733 (1993) (precluding application with respect to recovery from the construction lien fund). We must therefore determine whether the “substantial compliance” provision here is applicable to the ninety-day filing requirement. 15

The scope of a statutory “substantial compliance” provision requires an analysis, on a case-by-case basis, of the following logically relevant factors among others: the overall purpose of the statute; the *322 potential for prejudice or unfairness when the apparent clarity of a statutory provision is replaced by the uncertainty of a “substantial compliance” clause; the interests of future litigants and the public; the extent to which a court can reasonably determine what constitutes “substantial compliance” within a particular context; and, of course, the specific language of the “substantial compliance” and other provisions of the statute.

With respect to the purpose of the provision in question, a ninety-day period of limitation advances policies of preventing stale claims and protecting defendants from the fear of protracted litigation. Chase v Sabin, 445 Mich 190, 199; 516 NW2d 60 (1994), quoting Bigelow v Walraven, 392 Mich 566, 576; 221 NW2d 328 (1974). This is especially important in light of the public’s substantial interest in the certainty of land titles. Absent strict compliance with the ninety-day filing requirement of MCL 570.1111(1); MSA 26.316(111)(1), every construction project could create a potential cloud on the title to property, creating uncertainty in land titles. Moreover, where property owners and subsequent purchasers rely on the clear and unambiguous requirements of MCL 570.1111(1); MSA 26.316(111)(1), and find no notice of lien filed with the county office of the register of deeds, it would be inequitable to later subject those parties to the risk of foreclosure. Under these circumstances, certainty of title could only be achieved by researching the complete history of improvements with respect to a particular parcel of property and painstakingly obtaining waivers of lien from each contractor, subcontractor, materials supplier, and laborer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Elsie N Sage Revocable Trust
Michigan Court of Appeals, 2025
Quantum Concrete Inc v. Plaza De Kaza LLC
Michigan Court of Appeals, 2023
Desai v. A. R. Design Grp., Inc.
799 S.E.2d 506 (Supreme Court of Virginia, 2017)
C D Barnes Associates Inc. v. Star Heaven, LLC
834 N.W.2d 878 (Michigan Court of Appeals, 2013)
Big L Corp. v. Courtland Construction Co.
750 N.W.2d 628 (Michigan Court of Appeals, 2008)
Gold v. Interstate Financial Corp. (In Re Schmiel)
362 B.R. 802 (E.D. Michigan, 2007)
Paige v. City of Sterling Heights
720 N.W.2d 219 (Michigan Supreme Court, 2006)
E R Zeiler Excavating, Inc v. Valenti Trobec Chandler Inc
717 N.W.2d 370 (Michigan Court of Appeals, 2006)
Advanta National Bank v. McClarty
667 N.W.2d 880 (Michigan Court of Appeals, 2003)
Alan Custom Homes, Inc v. Krol
667 N.W.2d 379 (Michigan Court of Appeals, 2003)
Nippa v. Botsford General Hospital
651 N.W.2d 103 (Michigan Court of Appeals, 2002)
Roberts v. Mecosta County General Hospital
642 N.W.2d 663 (Michigan Supreme Court, 2002)
Central Ceiling & Parttiton, Inc v. Department of Commerce
642 N.W.2d 397 (Michigan Court of Appeals, 2002)
Daenzer v. Wayland Ford, Inc.
193 F. Supp. 2d 1030 (W.D. Michigan, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
603 N.W.2d 257, 461 Mich. 316, 1999 Mich. LEXIS 2835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-concrete-pipe-inc-v-sinacola-companiesmidwest-inc-mich-1999.