D. E. Holbrook, J.
On March 12, 1976, the trial court ordered judgments of foreclosure of the mechanics’ liens of Williams & Works, Inc., Westinghouse Electric Corporation, Koning & Bandstra, Inc., Johnson & Friedrich Drywall, Inc., Veneklasen Concrete Construction Company, Inc., Shurlow Tile & Carpet, Inc., and Tucker, Inc. The trial court held that each claimant had complied with
the requirements of the Michigan mechanics’ lien statute, MCLA 570.1,
et seq.;
MSA 26.281,
et seq.
with regard to an apartment project known as Foote Hills, located in Kent County, Michigan. Defendant Kelly Mortgage appeals maintaining that the mechanics’ lien statute is unconstitutional, that the various claimants did not comply with the statute and that the trial
court erred
in failing to add a necessary party. In addition, claimant Tucker cross-appeals seeking a modification of the judgment. Claimants Johnson & Friedrich Drywall, Inc., and Veneklasen Concrete Construction Company, Inc., cross-appeal seeking modification of an award of attorney’s fees. The record herein is indeed substantial, consisting of the transcript and numerous briefs, depositions, exhibits, pleadings, etc. Defendant Kelly Mortgage & Investment Company’s initial brief alone contains two volumes consisting of over 170 pages of text, plus hundreds of additional pages of exhibits, affidavits and various other items. In addition, Kelly has filed two additional briefs with this Court. We will not disclose our initial reaction to this mountainous record. We find that the complexity of this case fortunately does not correspond with the sheer volume of the record.
Initially, defendant Kelly Mortgage Company challenges the mechanics’ lien act as being unconstitutional as a violation of the Due Process Clause, US Const, Am XIV and Const 1963, art 1, § 17. Defendant maintains that the mechanics’ lien statute constitutes a cloud on the title to the detriment of the titleholder without the necessity of proper notice and judicial determination as to the validity of the lien which, when filed, constitutes a cloud or encumbrance upon the title.
In Michigan the mechanics’ lien statute has
existed for nearly 80 years.
It was established by 1891 PA 179. The act withstood early challenges and has been rarely challenged since.
Smalley v Gearing,
121 Mich 190; 79 NW 1114 (1899),
Smalley v Northwestern Terra-Cotta Co,
113 Mich 141; 71 NW 466 (1897). A similar mechanics’ lien statute was upheld as against a due process challenge by the United States Supreme Court,
Great Southern Fire Proof Hotel Co v Jones,
193 US 532; 24 S Ct 576; 48 L Ed 778 (1904). In an early decision our Supreme Court stated the following principle: "The statute was intended to protect subcontractors, material men, and laborers, and its benefits should not be frittered away by construction, unless clearly unconstitutional.”
Smalley v Gearing, supra,
121 Mich at 198.
We do recognize the longstanding validity of this statute.
In recent years, however, mechanics’ lien
statutes have been subject to challenge. Numerous decisions have upheld the validity of such statutes. Spielman-Fond,
Inc v Hanson’s Inc,
379 F Supp 997 (D Ariz, 1973),
aff'd
memorandum 417 US 901; 94 S Ct 2596; 41 L Ed 2d 208 (1974),
Cook v Carlson,
364 F Supp 24 (D SD, 1973),
Ruocco v Brinker,
380 F Supp 432 (SD Fla, 1974). Apparently relying on recent Supreme Court decisions in
Sniadach v Family Finance Corp,
395 US 337; 89 S Ct 1820; 23 L Ed 2d 349 (1969), and
Fuentes v Shevin,
407 US 67; 92 S Ct 1983; 32 L Ed 2d 556 (1972),
reh den
409 US 902; 93 S Ct 177; 34 L Ed 2d 165 (1972), several courts have found mechanics’ lien statutes invalid.
Barry Properties, Inc v The Fick Brothers Roofing Co,
277 Md 15; 353 A2d 222 (1976),
Roundhouse Construction Corp v Telesco Masons Supplies Co, Inc,
168 Conn 371; 362 A2d 778 (1975),
cert granted
423 US 809; 96 S Ct 20; 46 L Ed 2d 29 (1975). The determination as to the constitutionality of this statute is an involved and complex question. Fortunately we need not decide this question. We find that defendant lacks standing to challenge the constitutionality of this statute.
Defendant states his challenge on due process grounds as follows:
"Specifically, the Michigan Mechanic’s Lien Statute violates the due process clause of the Fourteenth Amendment by failing to provide for:
"1. Prior notice before perfection of the lien.
"2. Affidavits to establish the validity of the claim or the necessity of invoking the extraordinary remedy.
"3. A bond by the claimant to protect the owner.
"4. Judicial supervision.
"5. A burden on the claimant to establish validity at an early stage of the proceedings.”
Defendant also states that the property interest which is affected is the "restraint on the free alienation of real property”. We need not decide whether this is a sufficient property interest to invoke protection of due process.
It is apparent that this is an interest in the owner, not this subsequent mortgagee. Each of the items cited as interests of the owner do not constitute rights of the mortgagee.
The mortgagee is well aware of the priority interest which exists by virtue of the mechanics’ lien statute and, furthermore, is in a position to avoid being subordinate to the mechanics’ lien rights involved. Defendant maintains that various procedural aspects of the statute serve to invalidate it. However, all these asserted rights are designed to protect the interest of the owner, not other financing parties. Defendant does not challenge the basic foundation or substance of the act itself,
i.e.,
the protection of contractors, subcontractors, material men, etc. One cannot attack this statute on the ground that its application denies constitutional protection to others.
Department of Public Health v Tompkins, on rehearing,
34 Mich
App 114, 119; 190 NW2d 796 (1971),
United States v
Raines, 362 US 17; 80 S Ct 519; 4 L Ed 2d 524 (1960),
American Power & Light Co v Securities & Exchange Commission,
329 US 90; 67 S Ct 133; 91 L Ed 103 (1946). See also,
Shavers v Attorney General,
65 Mich App 355; 237 NW2d 325 (1975).
Defendant herein knew of the mortgagor’s building plans and was aware of the details contained therein. Defendant obviously knew of the mechanics’ lien provisions justifiably granting priority to the claimants.
Free access — add to your briefcase to read the full text and ask questions with AI
D. E. Holbrook, J.
On March 12, 1976, the trial court ordered judgments of foreclosure of the mechanics’ liens of Williams & Works, Inc., Westinghouse Electric Corporation, Koning & Bandstra, Inc., Johnson & Friedrich Drywall, Inc., Veneklasen Concrete Construction Company, Inc., Shurlow Tile & Carpet, Inc., and Tucker, Inc. The trial court held that each claimant had complied with
the requirements of the Michigan mechanics’ lien statute, MCLA 570.1,
et seq.;
MSA 26.281,
et seq.
with regard to an apartment project known as Foote Hills, located in Kent County, Michigan. Defendant Kelly Mortgage appeals maintaining that the mechanics’ lien statute is unconstitutional, that the various claimants did not comply with the statute and that the trial
court erred
in failing to add a necessary party. In addition, claimant Tucker cross-appeals seeking a modification of the judgment. Claimants Johnson & Friedrich Drywall, Inc., and Veneklasen Concrete Construction Company, Inc., cross-appeal seeking modification of an award of attorney’s fees. The record herein is indeed substantial, consisting of the transcript and numerous briefs, depositions, exhibits, pleadings, etc. Defendant Kelly Mortgage & Investment Company’s initial brief alone contains two volumes consisting of over 170 pages of text, plus hundreds of additional pages of exhibits, affidavits and various other items. In addition, Kelly has filed two additional briefs with this Court. We will not disclose our initial reaction to this mountainous record. We find that the complexity of this case fortunately does not correspond with the sheer volume of the record.
Initially, defendant Kelly Mortgage Company challenges the mechanics’ lien act as being unconstitutional as a violation of the Due Process Clause, US Const, Am XIV and Const 1963, art 1, § 17. Defendant maintains that the mechanics’ lien statute constitutes a cloud on the title to the detriment of the titleholder without the necessity of proper notice and judicial determination as to the validity of the lien which, when filed, constitutes a cloud or encumbrance upon the title.
In Michigan the mechanics’ lien statute has
existed for nearly 80 years.
It was established by 1891 PA 179. The act withstood early challenges and has been rarely challenged since.
Smalley v Gearing,
121 Mich 190; 79 NW 1114 (1899),
Smalley v Northwestern Terra-Cotta Co,
113 Mich 141; 71 NW 466 (1897). A similar mechanics’ lien statute was upheld as against a due process challenge by the United States Supreme Court,
Great Southern Fire Proof Hotel Co v Jones,
193 US 532; 24 S Ct 576; 48 L Ed 778 (1904). In an early decision our Supreme Court stated the following principle: "The statute was intended to protect subcontractors, material men, and laborers, and its benefits should not be frittered away by construction, unless clearly unconstitutional.”
Smalley v Gearing, supra,
121 Mich at 198.
We do recognize the longstanding validity of this statute.
In recent years, however, mechanics’ lien
statutes have been subject to challenge. Numerous decisions have upheld the validity of such statutes. Spielman-Fond,
Inc v Hanson’s Inc,
379 F Supp 997 (D Ariz, 1973),
aff'd
memorandum 417 US 901; 94 S Ct 2596; 41 L Ed 2d 208 (1974),
Cook v Carlson,
364 F Supp 24 (D SD, 1973),
Ruocco v Brinker,
380 F Supp 432 (SD Fla, 1974). Apparently relying on recent Supreme Court decisions in
Sniadach v Family Finance Corp,
395 US 337; 89 S Ct 1820; 23 L Ed 2d 349 (1969), and
Fuentes v Shevin,
407 US 67; 92 S Ct 1983; 32 L Ed 2d 556 (1972),
reh den
409 US 902; 93 S Ct 177; 34 L Ed 2d 165 (1972), several courts have found mechanics’ lien statutes invalid.
Barry Properties, Inc v The Fick Brothers Roofing Co,
277 Md 15; 353 A2d 222 (1976),
Roundhouse Construction Corp v Telesco Masons Supplies Co, Inc,
168 Conn 371; 362 A2d 778 (1975),
cert granted
423 US 809; 96 S Ct 20; 46 L Ed 2d 29 (1975). The determination as to the constitutionality of this statute is an involved and complex question. Fortunately we need not decide this question. We find that defendant lacks standing to challenge the constitutionality of this statute.
Defendant states his challenge on due process grounds as follows:
"Specifically, the Michigan Mechanic’s Lien Statute violates the due process clause of the Fourteenth Amendment by failing to provide for:
"1. Prior notice before perfection of the lien.
"2. Affidavits to establish the validity of the claim or the necessity of invoking the extraordinary remedy.
"3. A bond by the claimant to protect the owner.
"4. Judicial supervision.
"5. A burden on the claimant to establish validity at an early stage of the proceedings.”
Defendant also states that the property interest which is affected is the "restraint on the free alienation of real property”. We need not decide whether this is a sufficient property interest to invoke protection of due process.
It is apparent that this is an interest in the owner, not this subsequent mortgagee. Each of the items cited as interests of the owner do not constitute rights of the mortgagee.
The mortgagee is well aware of the priority interest which exists by virtue of the mechanics’ lien statute and, furthermore, is in a position to avoid being subordinate to the mechanics’ lien rights involved. Defendant maintains that various procedural aspects of the statute serve to invalidate it. However, all these asserted rights are designed to protect the interest of the owner, not other financing parties. Defendant does not challenge the basic foundation or substance of the act itself,
i.e.,
the protection of contractors, subcontractors, material men, etc. One cannot attack this statute on the ground that its application denies constitutional protection to others.
Department of Public Health v Tompkins, on rehearing,
34 Mich
App 114, 119; 190 NW2d 796 (1971),
United States v
Raines, 362 US 17; 80 S Ct 519; 4 L Ed 2d 524 (1960),
American Power & Light Co v Securities & Exchange Commission,
329 US 90; 67 S Ct 133; 91 L Ed 103 (1946). See also,
Shavers v Attorney General,
65 Mich App 355; 237 NW2d 325 (1975).
Defendant herein knew of the mortgagor’s building plans and was aware of the details contained therein. Defendant obviously knew of the mechanics’ lien provisions justifiably granting priority to the claimants. Defendant then proceeded to provide the money for the project. Defendant cannot now assert these procedural constitutional challenges to this statute which admittedly would serve to protect only the owner. Neither the past nor the present owners of the property have joined in this procedural challenge to the mechanics’ lien statute. Defendant has no standing to complain of procedural deficiencies of which only the owner of the property can complain. We express no opinion as to the merits of defendant’s constitutional arguments.
The next question with which we are faced is whether claimants have in fact properly asserted their rights under the mechanics’ lien statute. The trial court concluded that they had and we agree.
The mechanics’ lien statute has been described as: "designed to create confusion and frustrate anyone who attempts to meet all of its requirements”.
Spartan Asphalt Paving Co v Grand Ledge Mobile Home Park,
71 Mich App 177, 181; 247 NW2d 589 (1976),
rev’d,
400 Mich 184; 253 NW2d 646 (1977). The statute itself clearly announces its remedial purpose and indicates that it is to be liberally construed to achieve that purpose. MCLA 570.27; MSA 26.307,
Spartan Asphalt Paving Co v Grand Ledge Mobile Home Park, supra.
Recent
decisions have indicated that substantial compliance with the requirements of the mechanics’ lien statute shall be sufficient to establish claims.
Spartan Asphalt v Grand Ledge Mobile Home Park, supra, Georgia-Pacific Corp v Central Park North Co,
394 Mich 59; 228 NW2d 380 (1975). Furthermore, herein much of the problem was due to the reorganization of Foote,
effectively precluding proper notification. Such change in organization should not preclude the claimants from asserting their statutory remedies.
William Moors, Inc v Pine Lake Shopping Center, Inc, #1,
74 Mich App 12; 253 NW2d 658 (1977). Furthermore, the owner never requested statements of the amount of work and materials and, therefore, this should not upset the valid lien. MCLA 570.8; MSA 26.288. Notice was, in effect, given to the owners and substantial compliance with MCLA 570.1,
et seq.;
MSA 26.281,
et seq.,
was achieved.
Defendant also maintains that the trial court erred in finding that several of the plaintiffs did not give waivers of their liens, which would have precluded claimants from asserting any rights or foreclosure of the liens. In the absence of clear and unequivocal proof on the part of the defendant to the contrary we are unwilling to disturb the trial court’s finding.
G O Lewis Co v Erving,
4 Mich App 589; 145 NW2d 368 (1966),
Saginaw Lumber
Co v Wilkinson,
266 Mich 661, 665; 254 NW 240 (1934). See also,
Saginaw Lumber Co v Stirling,
305 Mich 473; 9 NW2d 680 (1943).
The delivery of materials or other commencement of work prior to the recording of the mortgage on the subject property gives the liens priority, even without the filing of notice of lis pendens. MCLA 570.1; MSA 26.281, MCLA 570.9; MSA 26.289,
Wallich Lumber Co v Golds,
375 Mich 323; 134 NW2d 722 (1965). Claimants were entitled to priority.
Strom Construction Co v Raymond,
356 Mich 79; 95 NW2d 879 (1959).
Defendant claims that Schwaemle Construction Company was a necessary party to this action. GCR 1963, 205.1. The record shows that Schwaemle Construction Company contracted to finish construction of this project after the other contractors had walked off the job because of nonpayment. Schwaemle filed its statement of account and mechanics’ lien on April 14, 1975. We find that it was possible to render complete relief on the complaint and the several cross-complaints and counter-complaints. The fact that Schwaemle was not a party did not interfere with the court’s determination of whether the parties herein had money coming to them or if their respective mechanics’ liens were valid and enforceable. No relief was sought from Schwaemle. It may have been convenient to have Schwaemle enter this action, however, it was not necessary. Schwaemle actively opposed joinder and we find the trial court properly acted by denying the motion to add Schwaemle.
Tucker, Inc., disputes the figure established by the trial court as the proper amount of its mechanics’ lien. The record reveals conflicting testimony as to the work actually completed by
Tucker. The trial judge’s determination that Tucker had not sufficiently proven that the invoice submitted represented completed work should therefore be affirmed.
Mazur v Blendea,
74 Mich App 467; 253 NW2d 801 (1977),
G O Lewis Co v Erving, supra, Saginaw Lumber Co v Wilkinson, supra.
Veneklasen Concrete Construction Company, Inc., and Johnson & Friedrich Drywall, Inc., challenge the sum of the award of attorney’s fees maintaining that the awards are inadequate. The statute does authorize an award of attorney’s fees. MCLA 570.12; MSA 26.292. This Statute vests discretion in the trial court and the amounts awarded are affirmed.
River Rouge Savings Bank v S & M Building Co,
359 Mich 189; 101 NW2d 260 (1960). See Anno:
Amount of Attorneys’ Compensation in Matters Involving Real Estate,
58 ALR3d 201, 226, § 8.
Affirmed.