L. A. Pipeline Construction v. Glass Bagging Enterprises

CourtWest Virginia Supreme Court
DecidedOctober 27, 2016
Docket15-0970
StatusPublished

This text of L. A. Pipeline Construction v. Glass Bagging Enterprises (L. A. Pipeline Construction v. Glass Bagging Enterprises) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. A. Pipeline Construction v. Glass Bagging Enterprises, (W. Va. 2016).

Opinion

STATE OF WEST VIRGINIA SUPREME COURT OF APPEALS FILED October 27, 2016 released at 3:00 p.m. RORY L. PERRY, II CLERK L.A. PIPELINE CONSTRUCTION, INC., SUPREME COURT OF APPEALS Plaintiff Below, Petitioner OF WEST VIRGINIA

vs) No. 15-0970 (Marshall County Nos. 11-C-70, 11-C-124, and 12-C-47)

GLASS BAGGING ENTERPRISES, INC., Defendant Below, Respondent

MEMORANDUM DECISION

The petitioner (plaintiff below), L.A. Pipeline Construction, Inc. (“L.A. Pipeline”), by counsel, James S. Huggins and Daniel P. Corcoran, appeals the order of the Circuit Court of Marshall County entered on August 26, 2015, granting summary judgment in favor of the respondent (defendant below), Glass Bagging Enterprises, Inc. (“Glass Bagging”). L.A. Pipeline asks this Court to vacate the circuit court’s order; invalidate Glass Bagging’s mechanic’s lien; and immediately disburse the escrow fund established in this matter to L.A. Pipeline. In response, Glass Bagging, by counsel, Mark E. Gaydos, Buddy Turner, and Hilary M. Bright, asserts that the circuit court correctly ruled in its favor and that the summary judgment order should be affirmed.

Upon our review of the parties’ arguments, the pertinent authorities, and the appendix record, we find a memorandum decision affirming the circuit court’s summary judgment order is appropriate under Rule 21 of the West Virginia Rules of Appellate Procedure.

I. Facts and Procedural History

L.A. Pipeline1 was contracted by Caiman Energy, LLC and Caiman Eastern Midstream, LLC (jointly referred to as “Caiman”) to install a pipeline in Marshall County, West Virginia. In December of 2010, L.A. Pipeline asked Glass Bagging to deliver and

1 L.A. Pipeline states that it is no longer in business; that it is insolvent; and that there are currently millions of dollars in unsatisfied judgments entered against it.

supply sand sacks at the rate of $3,180 per load for L.A. Pipeline’s use in the construction of the pipeline.

From December 17, 2010, through April 8, 2011, Glass Bagging delivered the sand sacks ordered by L.A. Pipeline at a total cost of $155,907.90. L.A. Pipeline then asked Glass Bagging to deliver three additional loads necessary to complete the pipeline. Relying upon L.A. Pipeline’s assurances that payment for the prior loads would be forthcoming and that it would remit payment on the three final loads, cash on delivery, Glass Bagging delivered the three additional loads of materials on April 16, 18, and 20, 2011. All three checks that L.A. Pipeline provided for these three additional loads, each in the amount of $3,180, were returned for insufficient funds.

L.A. Pipeline never disputed that it owes the total amount of $165,447.90 to Glass Bagging for the sand sacks it delivered and which were used by L.A. Pipeline in the construction of the pipeline on behalf of Caiman. Because L.A. Pipeline failed to remit payment, on May 24, 2011, Glass Bagging filed a mechanic’s lien in the Office of the Clerk of the County Commission of Marshall County against Caiman’s property on which the pipeline was constructed for the total sum due of $165,447.90.

On July 28, 2011, L.A. Pipeline filed the instant action (Civil Action No. 11-C­ 124) seeking to collect its account receivable and other damages from Caiman totaling in excess of $3,000,000 by enforcing its own mechanic’s lien that it had filed against Caiman. L.A. Pipeline named other lienholders as defendants in that action, including Pipeline Supply & Services, LLC (“Pipeline Supply”) and Glass Bagging, which filed a counterclaim against L.A. Pipeline for breach of contract and unjust enrichment. In its complaint, L.A. Pipeline asked that its mechanic’s lien be foreclosed; that “all liens be marshalled” and priorities determined; that Caiman’s pipeline rights-of-way and pipeline be sold; and that the proceeds of such sale be used first to pay its mechanic’s lien and that of Pipeline Supply.2

2 On May 2, 2011, Glass Bagging instituted a civil action against L.A. Pipeline (No. 11-C-70) asserting claims for breach of contract and unjust enrichment. Caiman was also named as a defendant in that action. On March 15, 2012, Glass Bagging filed a second civil action (No. 12-C-47) against L.A. Pipeline titled “Complaint to Determine Creditors’ Claim.” Although these two civil actions, as well as L.A. Pipeline’s action, appear on the circuit court’s order granting summary judgment in favor of Glass Bagging, it is unclear whether these actions were ever formally consolidated by the circuit court. See, in part, W.Va.R.Civ.P. 42(a) (“When actions involving a common question of law or fact are pending before the court . . . it may order all the actions consolidated; and it may make such (continued...)

During the course of the litigation, Caiman entered into a confidential settlement agreement with L.A. Pipeline and Pipeline Supply which resulted in the release of their respective mechanics’ liens. The parties represent that under the terms of this settlement, L.A. Pipeline and Caiman jointly filed a motion pursuant to West Virginia Code § 38-2-36 (2011) seeking to establish an escrow fund or bond in exchange for the release of Glass Bagging’s mechanic’s lien. Through its order entered on March 5, 2012, circuit court directed the establishment of the escrow fund in the amount of $165,447.90,3 which was the amount claimed in Glass Bagging’s mechanic’s lien, and ordered the execution and recording of a release of Glass Bagging’s mechanic’s lien to be replaced with a lien against the escrow fund.4

Following the establishment of the escrow fund, Caiman was dismissed from the litigation. Thereafter, L.A. Pipeline and Glass Bagging filed competing motions for summary judgment, each claiming entitlement to the escrow fund. On August 26, 2015, the circuit court entered an order granting Glass Bagging’s dispositive motion, finding there was no genuine issue of material fact that L.A. Pipeline breached its contract with Glass Bagging and would be unjustly enriched if it were not ordered to pay for the materials delivered by Glass Bagging. Regarding Glass Bagging’s mechanic’s lien, the circuit court found that in order to perfect a materialman’s mechanic’s lien under West Virginia Code § 38-2-11 (2011), notice of the lien must be provided to the property owner or the owner’s authorized agent. The circuit court found that although the principal contractor is a necessary party to a civil action to enforce a materialman’s mechanic’s lien against the owner’s property, only those entitled to notice of the lien may challenge its validity. Because L.A. Pipeline was not entitled to notice of Glass Bagging’s mechanic’s lien under West Virginia Code § 38-2-11, the circuit court found that L.A. Pipeline did not have standing to challenge the validity of that lien. The circuit court further ruled that even if L.A. Pipeline had standing, the property description in Glass Bagging’s mechanic’s lien, which L.A. Pipeline challenged, was

2 (...continued) orders concerning proceedings therein as may tend to avoid unnecessary costs or delay.”). 3 Upon the circuit court accepting payment by way of a check from United Bank made payable to the Clerk of the Circuit Court of Marshall County, the escrow fund in the amount of $165,477.90 was established. 4 This order was subsequently amended by an order entered nunc pro tunc on September 17, 2012, to order the recording of a release of Glass Bagging’s Notice of Mechanic’s Lien, which was also of record in the office of the Clerk of the County Commission of Marshall County.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Findley v. State Farm Mutual Automobile Insurance
576 S.E.2d 807 (West Virginia Supreme Court, 2003)
Carolina Lumber Company v. Cunningham
192 S.E.2d 722 (West Virginia Supreme Court, 1972)
Duquesne Light Co. v. State Tax Dept.
327 S.E.2d 683 (West Virginia Supreme Court, 1984)
Earp v. Vanderpool
232 S.E.2d 513 (West Virginia Supreme Court, 1976)
Painter v. Peavy
451 S.E.2d 755 (West Virginia Supreme Court, 1994)
Fisher v. Reamer
118 S.E.2d 76 (West Virginia Supreme Court, 1961)
Kendall v. Martin
67 S.E.2d 42 (West Virginia Supreme Court, 1951)
Treasure Valley Plumbing & Heating, Inc. v. Earth Resources Co.
684 P.2d 322 (Idaho Court of Appeals, 1984)
Williams & Works, Inc. v. Springfield Corp.
257 N.W.2d 160 (Michigan Court of Appeals, 1977)
Bailey Lumber Co. v. General Construction Co.
133 S.E. 135 (West Virginia Supreme Court, 1926)
Duncan Box & Lumber Co. v. Stewart
30 S.E.2d 391 (West Virginia Supreme Court, 1944)
Houston Lumber Co. v. Wetzel & Tyler Railway Co.
72 S.E. 786 (West Virginia Supreme Court, 1911)
Harper v. Smith
753 S.E.2d 612 (West Virginia Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
L. A. Pipeline Construction v. Glass Bagging Enterprises, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-a-pipeline-construction-v-glass-bagging-enterprises-wva-2016.