Levin, J.
Lake States Engineering Corporation, an Illinois corporation, brought this action against Lawrence Seaway Corporation to recover damages for alleged breach of a building construction contract between Lake States, as subcontractor, and Lawrence, as general contractor. Lawrence counterclaimed-for Lake States’ alleged breach of the same contract; United States Fidelity
&
Guaranty Company was surety on Lake States’ performance and payment bonds in favor of Lawrence.
The questions presented are:
1) Is Lake States precluded from maintaining this action because of failure to have qualified to do business in.Michigan?
2) '
Even if Lake States cannot recover from Lawrence, may Lake States’ surety, USF & G, recover from Lawrence the amounts USF
&
G pays labor and material claimants?
3) Is Lawrence barred by its failure to have obtained a residential builder’s license from recovering on its counterclaim against Lake States ? ,
The trial judge granted motions for accelerated and summary judgment dismissing the claims of all parties except that judgments totaling $92,217.67 were entered against Lake States and USF & G in favor of labor and material .suppliers who were additional defendants. Lake States and USF & G appealed generally. Lawrence cross-appealed the dismissal of its claims against Lake States and USF
&
G. Neither Lake States nor USE & G have prosecuted their appeals against the labor and material suppliers.
We affirm the judgment dismissing the claims of Lake States and USF
&
G and remand for trial on Lawrence’s counterclaim.
I.
The contract, entered into in June or July, 1962, provided that Lake States would construct the foundation caissons for the Jeffersonian Apartments in Detroit. Lake States commenced performance. Before the dispute arose Lawrence had paid Lake States $252,810 of the $450,000 contract price.
Lake States suspended work in November, 1962, after it failed in its attempts to get Lawrence to agree to pay additional amounts because of certain
subsurface conditions allegedly encountered by Lake States. Lake States claimed that Lawrence was obliged under the contract to pay more on that account. This Lawrence denied. Subsequently Lawrence hired another subcontractor to complete the caisson work.
Lake States claims Lawrence owes it approximately $555,000. The amount of Lawrence’s counterclaim, as stated in the counterclaim appended to Lawrence’s answer, was $300,000.
Section 95 of the Michigan general corporation act (MCLA § 450.95 [Stat Ann 1963 Rev § 21.96]) provides that “no foreign corporation shall be capable of making a valid contract in this state until it shall have fully complied with the requirements of the laws of this state with respect thereto, and at the time holds an unrevoked certificate to that effect.”
In June, 1962, Lawrence’s president mailed the unsigned proposed form of contract from Detroit to Lake States in Chicago, Illinois. Lawrence’s covering letter asked Lake States to sign the contract and added: “When the date of the contract is definitely determined, we will then sign the contracts and supply the dates for these contracts.” Lake States signed in Chicago and later Lawrence signed in Detroit.
Lake States claims the final acceptance of the contract occurred in Chicago, Illinois, when Lake States signed the contract, while Lawrence claims the contract did not become binding until it subsequently signed the contract in Detroit.
The question of when and where the parties became contractually bound depends on their intention as manifested by their verbal statements and conduct in the light of all the circumstances.
The trial
judge did not make specific findings on that question. Furthermore, the question could not he decided without a trial hearing
and, thus, could not he decided on the record so far made. Accordingly, we may not affirm the trial judge on the ground that the contract-was invalid under § 95 of the general corporation act. But that does not end our inquiry.
If, as we must now assume for the purpose of reviewing the judgment entered by the trial judge, the contract was made in Illinois, as Lake States claims, it was a lawful contract even though Lake States was not then qualified to do business in Michigan and the contract contemplated that Lake States would do acts in Michigan requiring qualification.
Whitehead & Kales Co.
v.
Taan
(1926), 233 Mich 597, 600, 601;
Westerlin & Campbell Co.
v.
Detroit Milling Co.
(1925), 233 Mich 384, 386.
Lawrence asserts that Lake States’ actions in Michigan pursuant to the contract were nevertheless unlawful because Lake States was not qualified to do business in Michigan when it acted and, thus, even if the contract was valid, Lake States may not recover on such unlawful acts.
Section 93 of the general corporation act (MCLA § 450.93 [Stat Ann 1963 Rev § 21.94]) provides that it is “unlawful” for an unqualified foreign corporation to carry on its business in this State. Lake
States conceded that it was doing business in Michigan and that it did not have a certificate authorizing it to do so as required by § 93.
Among other cases, Lawrence cites
Imperial Curtain Co.
v.
Jacob
(1910), 163 Mich 72. In that case the foreign corporation was not allowed to recover for services rendered in Michigan pursuant to a contract apparently made in Pennsylvania (p 77):
“Even though it should be held that the contract was accepted in Philadelphia, we cannot see how this fact would make any difference in the disposition of the case.
The statutes with reference to foreign corporations were not made merely for the purpose of preventing foreign corporations from coming into Michigan and making contracts here, but were passed principally for the purpose of preventing foreign corporations from carrying on their business in this State without subjecting themselves to certain liabilities and obligations.
It was the prevention of work within the State that was aimed at, and it was for work and service in this State that this suit was brought, as appears by the record.” (Emphasis supplied.)
Also denying recovery, not because the contract was made in Michigan but because its performance by the unqualified foreign corporation constituted doing business in Michigan, are
Nernst Lamp Co.
v.
Conrad
(1911), 165 Mich 604;
General Highways System
v.
Dennis
(1930), 251 Mich 152;
Decorators Supply Co.
v.
Chaussee
(1920), 211 Mich 302;
Smilansky
v.
Mandel Bros.
(1931), 254 Mich 575;
Free access — add to your briefcase to read the full text and ask questions with AI
Levin, J.
Lake States Engineering Corporation, an Illinois corporation, brought this action against Lawrence Seaway Corporation to recover damages for alleged breach of a building construction contract between Lake States, as subcontractor, and Lawrence, as general contractor. Lawrence counterclaimed-for Lake States’ alleged breach of the same contract; United States Fidelity
&
Guaranty Company was surety on Lake States’ performance and payment bonds in favor of Lawrence.
The questions presented are:
1) Is Lake States precluded from maintaining this action because of failure to have qualified to do business in.Michigan?
2) '
Even if Lake States cannot recover from Lawrence, may Lake States’ surety, USF & G, recover from Lawrence the amounts USF
&
G pays labor and material claimants?
3) Is Lawrence barred by its failure to have obtained a residential builder’s license from recovering on its counterclaim against Lake States ? ,
The trial judge granted motions for accelerated and summary judgment dismissing the claims of all parties except that judgments totaling $92,217.67 were entered against Lake States and USF & G in favor of labor and material .suppliers who were additional defendants. Lake States and USF & G appealed generally. Lawrence cross-appealed the dismissal of its claims against Lake States and USF
&
G. Neither Lake States nor USE & G have prosecuted their appeals against the labor and material suppliers.
We affirm the judgment dismissing the claims of Lake States and USF
&
G and remand for trial on Lawrence’s counterclaim.
I.
The contract, entered into in June or July, 1962, provided that Lake States would construct the foundation caissons for the Jeffersonian Apartments in Detroit. Lake States commenced performance. Before the dispute arose Lawrence had paid Lake States $252,810 of the $450,000 contract price.
Lake States suspended work in November, 1962, after it failed in its attempts to get Lawrence to agree to pay additional amounts because of certain
subsurface conditions allegedly encountered by Lake States. Lake States claimed that Lawrence was obliged under the contract to pay more on that account. This Lawrence denied. Subsequently Lawrence hired another subcontractor to complete the caisson work.
Lake States claims Lawrence owes it approximately $555,000. The amount of Lawrence’s counterclaim, as stated in the counterclaim appended to Lawrence’s answer, was $300,000.
Section 95 of the Michigan general corporation act (MCLA § 450.95 [Stat Ann 1963 Rev § 21.96]) provides that “no foreign corporation shall be capable of making a valid contract in this state until it shall have fully complied with the requirements of the laws of this state with respect thereto, and at the time holds an unrevoked certificate to that effect.”
In June, 1962, Lawrence’s president mailed the unsigned proposed form of contract from Detroit to Lake States in Chicago, Illinois. Lawrence’s covering letter asked Lake States to sign the contract and added: “When the date of the contract is definitely determined, we will then sign the contracts and supply the dates for these contracts.” Lake States signed in Chicago and later Lawrence signed in Detroit.
Lake States claims the final acceptance of the contract occurred in Chicago, Illinois, when Lake States signed the contract, while Lawrence claims the contract did not become binding until it subsequently signed the contract in Detroit.
The question of when and where the parties became contractually bound depends on their intention as manifested by their verbal statements and conduct in the light of all the circumstances.
The trial
judge did not make specific findings on that question. Furthermore, the question could not he decided without a trial hearing
and, thus, could not he decided on the record so far made. Accordingly, we may not affirm the trial judge on the ground that the contract-was invalid under § 95 of the general corporation act. But that does not end our inquiry.
If, as we must now assume for the purpose of reviewing the judgment entered by the trial judge, the contract was made in Illinois, as Lake States claims, it was a lawful contract even though Lake States was not then qualified to do business in Michigan and the contract contemplated that Lake States would do acts in Michigan requiring qualification.
Whitehead & Kales Co.
v.
Taan
(1926), 233 Mich 597, 600, 601;
Westerlin & Campbell Co.
v.
Detroit Milling Co.
(1925), 233 Mich 384, 386.
Lawrence asserts that Lake States’ actions in Michigan pursuant to the contract were nevertheless unlawful because Lake States was not qualified to do business in Michigan when it acted and, thus, even if the contract was valid, Lake States may not recover on such unlawful acts.
Section 93 of the general corporation act (MCLA § 450.93 [Stat Ann 1963 Rev § 21.94]) provides that it is “unlawful” for an unqualified foreign corporation to carry on its business in this State. Lake
States conceded that it was doing business in Michigan and that it did not have a certificate authorizing it to do so as required by § 93.
Among other cases, Lawrence cites
Imperial Curtain Co.
v.
Jacob
(1910), 163 Mich 72. In that case the foreign corporation was not allowed to recover for services rendered in Michigan pursuant to a contract apparently made in Pennsylvania (p 77):
“Even though it should be held that the contract was accepted in Philadelphia, we cannot see how this fact would make any difference in the disposition of the case.
The statutes with reference to foreign corporations were not made merely for the purpose of preventing foreign corporations from coming into Michigan and making contracts here, but were passed principally for the purpose of preventing foreign corporations from carrying on their business in this State without subjecting themselves to certain liabilities and obligations.
It was the prevention of work within the State that was aimed at, and it was for work and service in this State that this suit was brought, as appears by the record.” (Emphasis supplied.)
Also denying recovery, not because the contract was made in Michigan but because its performance by the unqualified foreign corporation constituted doing business in Michigan, are
Nernst Lamp Co.
v.
Conrad
(1911), 165 Mich 604;
General Highways System
v.
Dennis
(1930), 251 Mich 152;
Decorators Supply Co.
v.
Chaussee
(1920), 211 Mich 302;
Smilansky
v.
Mandel Bros.
(1931), 254 Mich 575;
Columbus Services, Inc.
v.
Preferred Building Maintenance, Inc.
(WD Mich, 1967), 270 F Supp 875, 879, 880;
A. H. Andrews Co.
v.
Colonial Theatre Co.
(ED Mich, 1922), 283 F 471. See, also,
Watts Construction Company
v.
Joint Clutch & Gear Service,
Inc.
(1949), 325 Mich 548;
Mathews Conveyer Co. v. Palmer-Bee Co.
(CA 6, 1943), 135 F2d 73.
EJA § 2021 (MCLA § 600.2021 [Stat Ann 1962 Eev § 27A.2021]) provides:
“When, by the laws of this state, any act is forbidden to be done by any corporation, or by any association of individuals, without express authority by law, and such act was done by a foreign corporation, the foreign corporation shall not maintain any action founded upon such act, or upon any liability or obligation, express or implied, arising out of, or made or entered into in consideration of such act.”
In doing business in Michigan without having qualified to do so, Lake States, a foreign corporation, in the words of EJA § 2021, thereby did an “act * * * forbidden to be done * * * without express authority by law.” Accordingly, it may ‘‘not maintain any action founded upon such act,” the act of doing business in Michigan, or “upon any liability or obligation, express or implied, arising out of, or made or entered into in consideration of such act.”
Smilansky
v.
Mandel Bros., supra; Mathews Conveyer Co.
v.
Palmer-Bee Co., supra; Seamans
v.
Temple Co.
(1895), 105 Mich 400.
Lake States’ count against Lawrence for damages for breach of contract and its alternative count in
quantum meruit
are both “founded upon” Lake States’ unlawful act of doing business in Michigan without having qualified to do so. Additionally, both the express and implied-in-law liability and obligation sought to be enforced against Lawrence is clamed by Lake States to arise out of such unlawful act and whatever liability or obligation Lawrence may owe Lake States was made or entered into in consideration of Lake States’ unlawful act of doing business in Michigan. Thus, the clear and blunt
language of RJA § 2021 bars Lake States from maintaining this action.
RJA § 2021 explicitly covers implied liabilities or obligations as well as express liabilities or obligations. There is no room to construe it so as to make an exception for a liability or obligation the law implies, like the quasi-eontractual recovery Lake States alternatively seeks.
Furthermore, to engraft an exception for implied liabilities or obligations would be to emasculate the legislative policy reflected in RJA § 2021. It would be a rare case where recovery of amounts approximating, sometimes greater than, those denied recovery under the express contract could not be obtained quasi-eontractually if we allow unqualified foreign corporations to ignore the contract and to recover on restitutionary theories whenever they are forbidden from recovering on the express contract.
The prohibition against suit we now consider functions as a penalty. In that respect it differs from the statute of frauds which is designed to provide protection from imposition in certain kinds of transactions. ¥e recognize that not infrequently in cases where a statute of frauds defense has been interposed courts have concluded that enforcement of the claim will not cause imposition and have allowed recovery by finding part performance taking the case out of the statute or invoking a restitutionary remedy;
Vanderhoef
v.
Parlcer Brothers
Company,
Limited
(1934), 267 Mich 672, 681. The principles developed in those cases have no application where the prohibition, as the one here, is meant to apply without regard to whether the defendant has a meritorious defense, indeed even if he does not. See
Cashin
v.
Pliter
(1912), 168 Mich 386, 391, 392.
The legislature has deliberately decided to declare a forfeiture in the belief that the
in terrorem
effect
of such a forfeiture will tend to compel compliance with the statutory provisions requiring foreign corporations to register and pay taxes comparable to those imposed on domestic corporations. That being the legislative decision our duty is to enforce it even though in a given ease the amount of the forfeiture may appear quantitatively or relatively large.
Cf. Dawn Construction Co.
v.
Paris Home Builders, Inc.
(1960), 360 Mich 281, 285;
Bilt-More Homes, Inc.
v.
French
(1964), 373 Mich 693.
Nor does Lake States’ compliance with Michigan’s requirements after it committed all the acts upon which it declares in its complaint enable Lake States to maintain this action.
EJA § 2021 provides that an action may not be maintained based upon the commission of unlawful acts of the kind described in that section. Lake States’ acts were of that kind. Lake States’ subsequent qualification did not make those unlawful acts lawful.
Lake States asserts that its contract with Lawrence was “executed” rather than “excutory” within the sense of
Carolin Manufacturing Corporation
v.
George S. May, Inc.
(1945), 312 Mich 487, and
Gill
v.
S. H. B. Corporation
(1948), 322 Mich 700. In those cases the party contracting with the foreign corporation failed in an attempt to declare the contract with the foreign corporation void after it had been fully performed by both parties. Lake States contends that Lawrence’s termination of Lake States’ employment under the contract after Lake States ceased work converted the contract from an executory to an executed one and thus, Lake States may recover under the cited eases.
We need not decide the somewhat metaphysical question whether the contract then became executed
as to performance required of Lake States thereunder. The cited cases only preclude the assertion of the contract’s infirmity by the other contracting party after such other contracting party has himself performed,
i.e.,
when the contract is executed on both sides.
In this case Lake States is complaining that Lawrence has
not
executed the performance (payment of money) Lake States claims Lawrence contracted to render. Lawrence chose to avail itself of the unlawfulness of Lake States’ actions before the performance required of Lawrence was rendered. Since Lawrence has not rendered the performance for which Lake States brought this action, the policy which precludes rescission by one who has fully performed, who fails prior to performance to assert the unlawful nature of the foreign corporation’s act, does not here apply.
Lake States claims that when § 93a (making it a misdemeanor to violate § 93) was added in 1961 to the Michigan general corporation act,
BJA § 2021 ceased to apply to violators of § 93. The argument is that the criminal law penalties provided for in the 1961 enactment were intended to replace preexisting remedies.
Apart from the fact that repeals by implication are not favored, we note that BJA § 2021, reenacting earlier legislation,
was passed subsequent to the law which added § 93a to the corporation act. We also note that it has not been Michigan’s tradition to rely on criminal penalties in preference to civil
remedies to obtain compliance with corporate filing-requirements. "We read the 1961 legislature’s intention to be the addition of still another sanction, not as eliminating by indirection the harsh but exceedingly effective RJA § 2021.
Cf. Irvine & Meier
v.
Wienner
(1920), 212 Mich 199, 202;
Reuter Hub & Spoke Co.
v.
Hicks
(1914), 181 Mich 250, 253;
Dawn Construction Company
v.
Paris Home Builders, Inc., supra,
p 285.
Lake States cites
Rex Beach Pictures Co.
v.
Garson Productions
(1920), 209 Mich 692, where a nonqualified foreign corporation was permitted to replevy a motion picture film belonging to it. However, as pointed out by the Supreme Court in that case (p 707): “Plaintiff’s [Rex Beach Pictures Co.] right to the possession of the property in question does not depend upon the void contract, but is rather in spite of, or notwithstanding such contract and the doing of business thereunder.”
Here Lake States’ right to recover depends on proof of the unlawful act of doing business in Michigan, not proof of ownership of property owned before it performed such unlawful act.
Under part III of this opinion we remand for trial on Lawrence’s counterclaim against Lake States. So as to avoid misunderstanding, Lake States may defend against Lawrence’s counterclaim by asserting as an offset whatever claims Lake States may have against Lawrence even though Lake States is statutorily precluded from maintaining an action on such
claims or seeking an affirmative recovery based tbereon. Since Lawrence has pnt in issue the entire relationship of the parties, Lake States must be allowed to use defensively whatever claims it has against Lawrence.
.
Cf. Milum
v.
Herz Brothers Water Well Drilling and Supply Company
(1958), 74 Nev 309 (329 P2d 1068).
II.
The claim of the surety, USF
&
Gr, is that even though its principal, Lake States, is barred by the statute from recovering anything in our courts, it, USF & Gr, should be allowed as surety to recover from Lawrence the amounts it pays labor and material claimants.
USF
&
Gr relies principally on rules of law developed in public construction contract cases. Since mechanic’s liens cannot be filed against public property,
contractors for public structures are required to furnish bonds for the protection of labor and material suppliers. See,
e.g.,
MCLA § 570.101 (Stat Ann 1953 Rev § 26.321); MCLA § 129.201 (Stat Ann Cum Supp § 5.2321 [1]).
In
Pearlman
v.
Reliance Insurance Co.
(1962), 371 US 132 (83 S Ct. 232, 9 L Ed 2d 190), the surety prevailed against a bankrupt contractor’s trustee in bankruptcy, a majority of the justices so holding on the ground that the surety was subrogated to the claims of laborers and materialmen against the funds retained by the government while the concurring justices put their concurrence on the ground that the surety stood in the shoes of the governmental authority itself.
However, in
United States
v.
Munsey Trust Co.
(1947), 332 US 234 (67 S Ct 1599, 91 L Ed 2022) the United States was permitted, in preference to the claim of the contractor’s surety who had paid unpaid laborers and materialmen, to set off against the funds which it had retained an amount due it from the defaulting contractor under another contract. In so holding the United States Supreme Court acknowledged that in earlier cases it had (p 240) “recognized the peculiarly equitable claim of those responsible for the physical completion of building contracts to be paid from available moneys ahead of others whose claims come from the advance of money. But in all those cases, the owner was a mere stakeholder and had no rights of its own to assert.”
We have already held that Lake States may. not recover from Lawrence and, thus, Lawrence has no obligation to Lake States which will be recognized
by our courts as supporting an affirmative recovery against Lawrence.
USF & Gr has cited no authority allowing a surety to recover for amounts the contractor could not recover.
In all the cases cited by USF & G-, the one against whom recovery was sought was a stakeholder only and not a party to the controversy.
The Jeffersonian Apartments could have been liened by the labor and material suppliers USF & Gf has paid or may pay. As a general proposition, labor and material suppliers of a subcontractor have no claim against the general contractor or owner.
The principles developed in the public construction contract sector might, nevertheless, properly be invoked in a case where the private property owner or general contractor holds an unpaid amount owing to an uncollectible subcontractor and the question is whether labor and material claimants of the uncollectible subcontractor who have not protected their mechanic’s lien rights, or a surety paying such claimants, should be preferred over general creditors or assignees of the subcontractor.
It is apparent that the rules and principles of law urged upon us by USF & Gr developed as they did in cases where the real question was one of priority to moneys in the hands of the governmental authority or owner as between the surety and his contrac
tor-principal’s receiver, assignee, or creditors who had no claim against the surety.
This case presents no issue of priority between USP & Gr and other competing creditors of Lake States. Different policies and principles of law are here controlling. USP & Gr has not claimed that Lake States is uncollectible, that it will not be able to enforce its right of indemnification against Lake States as principal for whatever amount it has paid or shall pay under the bond. Irrespective of whether USP & Gr and Lake States are in fact collaborating as Lawrence charges, if, as we must assume absent a claim to the contrary, Lake States, the principal on the bond, is collectible, the effect of allowing its surety, USP
&
Gr, to recover from Lawrence would be to benefit Lake States since Lake States would to that extent be relieved of the payment of labor and material claims.
Whatever equitable considerations might encourage us to recognize a remedy in favor of a surety whose principal is uncollectible against a fund still intact and owing, without regard to whether the principal may himself maintain an action to collect from the fund, do not apply where allowance of such a remedy would in fact subvert the policy of § 93 of the general corporation act and RJA § 2021 by reducing the sanction against a solvent foreign corporation.
III.
Lawrence’s counterclaim for damages for breach of contract is defended by Lake States on the ground that Lawrence’s failure to obtain a residential builder’s license prevents it from maintaining any action on the contract (PA 1965, No 383 [MOLA § 338.1501,
et seq.,
Stat Ann 1968 Cum Supp § 18.-86(101),
et
seq.~\).
Our examination of this statute convinces us that the policy and language of its sanction are different from those imposed by the general corporation act and RJA § 2021.
Allowing anyone who deals with an unqualified foreign corporation to avail itself of the bar to suits by such corporation serves the public as a whole by providing a most effective deterrent to avoidance of State taxation and regulation of foreign corporations. The purpose of the residential builder’s licensing law, on the other hand, is to serve a more limited portion of the public, namely, owners:
“In order to safeguard and protect home owners and persons undertaking to become home owners, it shall be unlawful * * * for any person to engage in the business of or to act in the capacity of a residential builder * * * without having a license therefor.” MOLA § 338.1501 (Stat Ann 1968 Oum Supp § 18.86 [101]).
The policy of protecting the owner is reflected in the language adopted to express the scope of the disqualification on maintenance of suit which results from building without a license.
Section 16 of the statute provides:
“No person engaged in the business or acting in the capacity of a residential builder and/or residential maintenance and alteration contractor may bring or maintain any action in any court of this state for the collection of compensation for the performance of any act or contract for which a license is required by this act without alleging and proving that he was duly licensed under this act at all times during the performance of such act or contract”. MCLA § 338.1516 (Stat Ann 1968 Cum Supp § 18.86 [116]).
Thus, a nonlicensed builder may not maintain an action to recover “compensation for the
performance
of any act or contract for which a license is required.” (Emphasis supplied.) Accordingly, a non-licensed builder may not recover for his own performance.
Lawrence’s counterclaim does not seek recovery for Lawrence’s performance. Lawrence rather seeks recovery against a subcontractor for the subcontractor’s alleged nonperformance. Since Lawrence’s counterclaim seeks recovery for nonperformance, not performance, the statutory limitation on suit by a nonlicensed builder does not bar the counterclaim.
It is true that Lawrence’s unlicensed building operations were unlawful. MOLA § 338.1501 (Stat Ann 1968 Cum Supp § 18.86 [101]). Absent an express statutory provision like § 16 as to the effect of such unlawfulness on its contracts made during the period of noncompliance, we might well declare them voidable at the option of the other contracting party on the common-law principle expressed in
Maurer
v.
Greening Nursery Co.
(1917), 199 Mich 522. But § 16 occupies the field. It states the extent to which one violating this statute is precluded from bringing suit. To invoke the principle expressed in the last cited case would be to give no significance to the legislature’s choice of language and would be in effect to supersede § 16 altogether with the more comprehensive common-law sanction.
As the Michigan Supreme Court observed in
Cashin
v.
Pliter
(1912), 168 Mich 386, before a court declares applicable the common-law sanction invalidating contracts made in violation of Jaw (pp 390, 391) :
“the court should carefully scrutinize the particular statute under advisement, for the purpose of
ascertaining, from the subject-matter and language used, the object for which it was enacted and the intent of its makers, to the end that such intent may be rendered effectual and the indicated purpose accomplished.”
Affirmed as to Lake States’ and USF
&
G-’s appeal. Reversed and remanded for trial on Lawrence’s counterclaim. Costs to Lawrence.
Lesinski, C. J., and J. H. Gillis, J., concurred.