Lake States Engineering Corp. v. Lawrence Seaway Corp.

167 N.W.2d 320, 15 Mich. App. 637
CourtMichigan Court of Appeals
DecidedFebruary 21, 1969
DocketDocket 849, 850
StatusPublished
Cited by17 cases

This text of 167 N.W.2d 320 (Lake States Engineering Corp. v. Lawrence Seaway Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake States Engineering Corp. v. Lawrence Seaway Corp., 167 N.W.2d 320, 15 Mich. App. 637 (Mich. Ct. App. 1969).

Opinion

Levin, J.

Lake States Engineering Corporation, an Illinois corporation, brought this action against Lawrence Seaway Corporation to recover damages for alleged breach of a building construction contract between Lake States, as subcontractor, and Lawrence, as general contractor. Lawrence counterclaimed-for Lake States’ alleged breach of the same contract; United States Fidelity & Guaranty Company was surety on Lake States’ performance and payment bonds in favor of Lawrence.

*641 The questions presented are:

1) Is Lake States precluded from maintaining this action because of failure to have qualified to do business in.Michigan?

2) ' Even if Lake States cannot recover from Lawrence, may Lake States’ surety, USF & G, recover from Lawrence the amounts USF & G pays labor and material claimants?

3) Is Lawrence barred by its failure to have obtained a residential builder’s license from recovering on its counterclaim against Lake States ? ,

The trial judge granted motions for accelerated and summary judgment dismissing the claims of all parties except that judgments totaling $92,217.67 were entered against Lake States and USF & G in favor of labor and material .suppliers who were additional defendants. Lake States and USF & G appealed generally. Lawrence cross-appealed the dismissal of its claims against Lake States and USF & G. Neither Lake States nor USE & G have prosecuted their appeals against the labor and material suppliers.

We affirm the judgment dismissing the claims of Lake States and USF & G and remand for trial on Lawrence’s counterclaim.

I.

The contract, entered into in June or July, 1962, provided that Lake States would construct the foundation caissons for the Jeffersonian Apartments in Detroit. Lake States commenced performance. Before the dispute arose Lawrence had paid Lake States $252,810 of the $450,000 contract price.

Lake States suspended work in November, 1962, after it failed in its attempts to get Lawrence to agree to pay additional amounts because of certain *642 subsurface conditions allegedly encountered by Lake States. Lake States claimed that Lawrence was obliged under the contract to pay more on that account. This Lawrence denied. Subsequently Lawrence hired another subcontractor to complete the caisson work.

Lake States claims Lawrence owes it approximately $555,000. The amount of Lawrence’s counterclaim, as stated in the counterclaim appended to Lawrence’s answer, was $300,000.

Section 95 of the Michigan general corporation act (MCLA § 450.95 [Stat Ann 1963 Rev § 21.96]) provides that “no foreign corporation shall be capable of making a valid contract in this state until it shall have fully complied with the requirements of the laws of this state with respect thereto, and at the time holds an unrevoked certificate to that effect.”

In June, 1962, Lawrence’s president mailed the unsigned proposed form of contract from Detroit to Lake States in Chicago, Illinois. Lawrence’s covering letter asked Lake States to sign the contract and added: “When the date of the contract is definitely determined, we will then sign the contracts and supply the dates for these contracts.” Lake States signed in Chicago and later Lawrence signed in Detroit.

Lake States claims the final acceptance of the contract occurred in Chicago, Illinois, when Lake States signed the contract, while Lawrence claims the contract did not become binding until it subsequently signed the contract in Detroit.

The question of when and where the parties became contractually bound depends on their intention as manifested by their verbal statements and conduct in the light of all the circumstances. 1 The trial *643 judge did not make specific findings on that question. Furthermore, the question could not he decided without a trial hearing 2 and, thus, could not he decided on the record so far made. Accordingly, we may not affirm the trial judge on the ground that the contract-was invalid under § 95 of the general corporation act. But that does not end our inquiry.

If, as we must now assume for the purpose of reviewing the judgment entered by the trial judge, the contract was made in Illinois, as Lake States claims, it was a lawful contract even though Lake States was not then qualified to do business in Michigan and the contract contemplated that Lake States would do acts in Michigan requiring qualification. Whitehead & Kales Co. v. Taan (1926), 233 Mich 597, 600, 601; Westerlin & Campbell Co. v. Detroit Milling Co. (1925), 233 Mich 384, 386. 3

Lawrence asserts that Lake States’ actions in Michigan pursuant to the contract were nevertheless unlawful because Lake States was not qualified to do business in Michigan when it acted and, thus, even if the contract was valid, Lake States may not recover on such unlawful acts.

Section 93 of the general corporation act (MCLA § 450.93 [Stat Ann 1963 Rev § 21.94]) provides that it is “unlawful” for an unqualified foreign corporation to carry on its business in this State. Lake *644 States conceded that it was doing business in Michigan and that it did not have a certificate authorizing it to do so as required by § 93.

Among other cases, Lawrence cites Imperial Curtain Co. v. Jacob (1910), 163 Mich 72. In that case the foreign corporation was not allowed to recover for services rendered in Michigan pursuant to a contract apparently made in Pennsylvania (p 77):

“Even though it should be held that the contract was accepted in Philadelphia, we cannot see how this fact would make any difference in the disposition of the case. The statutes with reference to foreign corporations were not made merely for the purpose of preventing foreign corporations from coming into Michigan and making contracts here, but were passed principally for the purpose of preventing foreign corporations from carrying on their business in this State without subjecting themselves to certain liabilities and obligations. It was the prevention of work within the State that was aimed at, and it was for work and service in this State that this suit was brought, as appears by the record.” (Emphasis supplied.)

Also denying recovery, not because the contract was made in Michigan but because its performance by the unqualified foreign corporation constituted doing business in Michigan, are Nernst Lamp Co. v. Conrad (1911), 165 Mich 604; General Highways System v. Dennis (1930), 251 Mich 152; Decorators Supply Co. v. Chaussee (1920), 211 Mich 302; Smilansky v. Mandel Bros. (1931), 254 Mich 575;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Remark LLC v. Adell Broadcasting
817 F. Supp. 2d 990 (E.D. Michigan, 2011)
Hawker v. Northern Michigan Hospital, Inc
416 N.W.2d 428 (Michigan Court of Appeals, 1987)
Liberty Mutual Insurance v. Vanderbush Sheet Metal Co.
512 F. Supp. 1159 (E.D. Michigan, 1981)
American Oil Co. v. L a Davidson, Inc.
290 N.W.2d 144 (Michigan Court of Appeals, 1980)
Thomas Industries, Inc. v. Wells
262 N.W.2d 853 (Michigan Court of Appeals, 1977)
Michigan Health Care, Inc. v. Flagg Industries, Inc.
240 N.W.2d 295 (Michigan Court of Appeals, 1976)
Reynolds v. College Park Corp.
234 N.W.2d 507 (Michigan Court of Appeals, 1975)
Lindhout v. Ingersoll
228 N.W.2d 415 (Michigan Court of Appeals, 1975)
Trans Plastic, Inc. v. Conser Construction Co.
220 N.W.2d 762 (Michigan Court of Appeals, 1974)
Behlen Manufacturing Co. v. Andries-Butler Inc.
217 N.W.2d 125 (Michigan Court of Appeals, 1974)
Show Counselors, Ltd. v. American Motors Corp.
211 N.W.2d 111 (Michigan Court of Appeals, 1973)
Tyranski v. Piggins
205 N.W.2d 595 (Michigan Court of Appeals, 1973)
Long Manufacturing Co. v. Wright-Way Farm Service, Inc.
197 N.W.2d 862 (Michigan Court of Appeals, 1972)
Stoneleigh Homes, Inc. v. Jerome Building Co.
188 N.W.2d 152 (Michigan Court of Appeals, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
167 N.W.2d 320, 15 Mich. App. 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-states-engineering-corp-v-lawrence-seaway-corp-michctapp-1969.