Hamtramck Lumber & Supply Co. v. United Home Builders

192 N.W. 575, 222 Mich. 265, 1923 Mich. LEXIS 672
CourtMichigan Supreme Court
DecidedMarch 22, 1923
DocketDocket No. 71
StatusPublished
Cited by2 cases

This text of 192 N.W. 575 (Hamtramck Lumber & Supply Co. v. United Home Builders) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamtramck Lumber & Supply Co. v. United Home Builders, 192 N.W. 575, 222 Mich. 265, 1923 Mich. LEXIS 672 (Mich. 1923).

Opinion

Wiest, C. J.

The original bill herein was filed by plaintiff to enforce a lien for material furnished in the construction of three houses. Other lienors, subsequent purchasers of the property, the principal contractor and the surety on a bond to release the liens, were made defendants.

May 10, 1919, Andrew J. Tarsney was the owner of three lots on Emerson avenue in the city of Detroit, [267]*267and on that day made a verbal agreement with the United Home Builders, Inc., for the erection of three residences thereon at $5,300 each, and paid $1,000. July 1, 1919, the agreement was. reduced to writing and signed by the parties, and required the contractor to provide the labor and material for three new residence buildings to be erected on the lots according to certain specifications, on or before September 1, 1919. The agreement contained the provision:

“It is hereby mutually agreed between the parties hereto that the sum to be paid by the owner to the contractor for the erection of said building according to specifications shall be $5,300, payable as follows:
“1st. $1,000 as first payment on materials to be furnished. Remainder to be paid through loan company.
“2nd. $1,000 when house is ‘under roof/
“3rd. $-when rough plumbing and heating is done and house is plastered.
“Balance loan. $-when house is finished according to specifications.”

The work was not completed September 1, 1919, and the contractor was urged, by the owner, after that date, to continue with the work, and lien claimant Ferrari commenced special mason work on September 20, 1919, and completed the same October 1, 1919. The contractor abandoned the work on or about the 30th of October, 1919, and the owner boarded up the buildings and they remained that way until May, 1920, when defendants Dickson and McDermand purchased the premises from Mrs. R. May Tarsney.

Mr. Tarsney was not well at the time the contractor, abandoned the work and he died March 28, 1920. February 26, 1920, Mr. Tarsney deeded the premises to a third party, who immediately deeded the same to Mr. and Mrs. Tarsney, constituting them tenants by entireties.

Defendants Dickson and McDermand started, on or [268]*268about May 15, 1920, to complete the buildings and finished them about September 10, 1920.

The original bill herein was filed on July 23, 1920, and defendants Dickson and McDermand, as subsequent purchasers, claimed recoupment for loss of rents occasioned by the failure of the contractor to complete the buildings by September 1, 1919.

It seems there was a hearing previous to the one in this record, and it evidently became apparent to the defendants Dickson and McDermand that their claim of recoupment would fail because of want of assignment of such claim from Mr. Tarsney’s estate. Thereupon, on June 24, 1921, Mrs. Tarsney filed a petition in the probate court for the county of Wayne for administration of the estate of Andrew J. Tarsney, deceased. In the petition she alleged that Mr. Tarsney left a will: “which may be offered for probate,” and that his estate consisted of “an unliquidated action for breach of building contract,” and that R. May Tarsney, widow, and Jack Tarsney, a son 14 years of age, were the heirs at law of the deceased. The same day Mrs. Tarsney was appointed special administratrix of the estate, and immediately petitioned the probate court for an order directing her to sell, assign and transfer to defendants Dickson and McDermand the building contract entered into by Andrew j. Tarsney and all right of action for damages for breach thereof. The reason assigned by her for such order was that she had sold the premises to defendants Dickson and McDermand, and

“At the time of said sale, it was agreed that your petitioner should assign to said purchasers all right of action resulting from the breach of a certain building contract executed by the said deceased with the United Home Builders, a Michigan corporation, for the •construction of certain buildings on said premises, which said contract had not been fulfilled by said contractor.”

[269]*269The same day, and upon such petition, the probate court, upon a finding that “it will be for the best interest of said estate to release said contract obligation,” authorized the special administratrix to sell, assign and transfer to defendants Dickson and McDermand the interest of the estate in the building contract and all right of action for damages for breach thereof.

Mr. Tarsney never assigned to Mrs. Tarsney any right of action under the contract. The record discloses no further proceedings in the estate of Andrew J. Tarsney.

The trial judge found that the delay occasioned by boarding up the buildings in the fall of 1919, and leaving them until May, 1920, by reason of the sharp advance in price of building materials made the cost of finishing the buildings 40 per cent, higher than such cost would have been had the construction followed the abandonment by the contractor. The evidence amply supports this finding. The cost of completing the buildings must be determined as of the time their completion fell upon the owner, or within a reasonable period thereafter. Had the work of completion followed within a reasonable period after the contractor left, the cost thereof would have been, at least 40 per cent, less than it was seven months later. The so-called peak of high prices of building material and labor was reached in February, 1920, and by waiting from October 30, 1919, to May, 1920, to even start to complete the buildings, bars the extra cost of construction from being set up against the liens.

The owner paid the contractor $1,000 fifty days before the contract was signed, and it is claimed by the lienors that the court improperly held the owner, and those claiming under him, protected by such payment. The burden of showing that such payment was distributed according to the statute among those [270]*270who might claim liens rested upon the owner or subsequent purchasers. If $1,000 could be paid in advance and protect the owner, the whole contract price could be paid and materialmen and laborers would have no remedy. We have searched the record for evidence tending to show what was done by the contractor with this $1,000, and cannot find that it was .distributed among those who might claim liens.

vCounsel for the present owners contends:

“This payment was specifically required to be made 'by the contract, but was made before any labor or :materials were furnished upon the premises, and for that reason is a protected payment, although no sworn statement was received at the time. This is obviously true because nothing could then be due or owing to any laborers or materialmen under the contract.” Citing Stevens v. Garland, 198 Mich. 24; J. W. McCausey & Co. v. Gittleman, 201 Mich. 8.

The cases cited do not support the broad rule contended for. They are based upon the provision of the lien law protecting incumbrances existing and of record at the time material is furnished or labor services rendered, and present the element of constructive notice, sufficient to put the subcontractors on inquiry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Japes Co. v. Pagel.
225 N.W. 521 (Michigan Supreme Court, 1929)
Corlett-Stone Lumber Co. v. Parker
203 N.W. 122 (Michigan Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
192 N.W. 575, 222 Mich. 265, 1923 Mich. LEXIS 672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamtramck-lumber-supply-co-v-united-home-builders-mich-1923.