Smalley v. Gearing

79 N.W. 1114, 121 Mich. 190, 1899 Mich. LEXIS 549
CourtMichigan Supreme Court
DecidedSeptember 12, 1899
StatusPublished
Cited by43 cases

This text of 79 N.W. 1114 (Smalley v. Gearing) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smalley v. Gearing, 79 N.W. 1114, 121 Mich. 190, 1899 Mich. LEXIS 549 (Mich. 1899).

Opinions

Long, J.

Traugott Schmidt, now deceased, in April, 1895, was the owner of a certain lot in the city of Detroit. On April 9 th of that year, he entered into a written contract with Joseph L. Gearing for the construction of a building thereon, for the sum of $52,812.08. Afterwards, Schmidt, with the consent of Gearing, let the contract for the plastering for $6,850; thus leaving the contract to stand at $45,962.08. Gearing went on with the work under the contract, paying most of the labor bills, and in great part for the materials, when, on October 12, 1895, he failed, leaving the building uncompleted. The contract for completion was then let to J. L. Hudson for $22,040.40. He completed it, and was paid for the same. This bill is filed by complainants to enforce a mechanic’s lien, under [193]*193Act No. 179,. Pub. Acts 1891, as amended by Act No. 199, Pub. Acts 1893. The defendants are the owners of the property (the heirs of Traugott Schmidt, deceased), the contractor, and certain lien claimants. The court below found and decreed that there were due to the complainants and defendant lienors the following sums: To complainants, $3,992.89; to the Hall & Wolf Company, $2,608.47; to Stanstead Granite Company, $1,046.46; to Wetmore & Brady, $644.14; to Ashland Brown Stone Company, $2,479.77; to Northwestern Terra-Cotta Company, $1,-238.21; to Strelinger & Hart, $658.30. The court also found by the decree that the amount paid by Schmidt to Gearing under the contract, in excess of the amount distributed among the laborers and material men, was $4,937.48, and that the amount of the contract price remaining unpaid after the payment to Hudson for the completion of the building was $271.68. The'court computed interest on these amounts at 6 per cent, from January, 1896, to date of decree, making a total, of principal and interest, of $5,836.39, and made this amount a lien on the land, with interest at 6 per cent, from date of decree. After deducting $15 for entry and stenographer’s fees, etc., in favor of complainants, from this sum, the court decreed that the balance should be distributed to the complainants and other lienors ratably and in proportion to the amount due each from Gearing. From this decree all the parties appeal except Gearing.

1. It is contended by the property owners that the act of 1891, as amended by the act of 1893, is unconstitutional, because it is an unwarrantable abridgment of the freedom of contract, and because it undertakes to give special and unreasonable privileges to one class of citizens at the expense of another. The amendatory act of 1893 amends sections 1, 6, and 9 of the act of 1891. Section 1, as amended, provides substantially:

“ Every person who shall, as subcontractor, laborer, or material man, perform any labor or furnish materials- to such original or principal contractor, or any subcontractor, [194]*194in carrying forward or completing any such contract, shall have a lien therefor upon such house * * * to the extent of the right, title, and interest of such owner. * * * Provided, that any person * * * furnishing material or performing labor of any kind entering into the construction of such building * * * shall, within ten days after furnishing the first of such material, or performing the first of such labor to any contractor or subcontractor, serve on the owner * * * a notice, which notice shall be such as will inform the owner * * * of the nature of the materials furnished or to be furnished or labor performed or to be performed, and a description of the premises where furnished. * * * Such notices, however, shall be sufficient if served at any time subsequent to said ten days* but before the original contractor shall make out and give to the owner * * * a statement under oath of the number and names of every subcontractor or laborer in his employ, and of every person * * * furnishing materials, giving the amount, if anything, which is due or to become due to them, or any of them, for work done or materials furnished, as required by section four of this act. The owner * * * shall not be liable to the subcontractor, material men, or laborers for any greater amount than he contracted to pay the original contractor; * * * but the risk of all payments made to the original contractor after he shall have received the notice above mentioned, or before the contractor shall have furnished him with a statement as hereinbefore provided, shall be upon the owner * * * until the expiration of sixty days within which claims for lien may be filed, as hereinafter provided, and no payment made to any contractor before the expiration of said sixty days shall defeat any lien of any subcontractor, material man, or laborer, unless such payment has been distributed among the subcontractors, material men, or laborers, or, if distributed in part only, then to the extent of such distributions.”

Section 4 of the act of 1891, which was not amended by the act of 1893, provides:

“The owner * * * may at any time retain from any moneys due or to become due to the original contractor an amount sufficient to pay all demands owing ox-unpaid to any subcontractor, material man, or laborer who has filed and served the notice in manner and form [195]*195as provided in section one of this act. The original contractor shall, whenever any payment of money shall become due from the owner, * *' * or whenever he desires to draw any money from the owner, * * * make out and give to the owner * * * a statement under oath of the number and names of every subcontractor or laborer in his employ, and of every person furnishing materials, giving the amount, if anything, which is due or to become due to them, or any of them, for work done or materials furnished; and the^ owner * * * may retain out of any money then due or to become due to the contractor an amount sufficient to pay all demands that are due dr to become due to such subcontractors, laborers, and material men, as shown by the contractor’s statement, and pay the same to them, according to their respective rights; and all payments so made shall, as between such owner * * * and such contractor, be considered the same as if paid to such original contractor. Until the statement provided for in this section is made, in manner and form as herein provided, the contractor shall have no right of action or lien against the owner * * * on account of such contract; and any payments made by the owner * * * before such statement is made, or without fetaining sufficient money, if that amount be due or is to become due, to pay the subcontractors, laborers, or material men as shown by the statement, shall be considered illegal, and made in violation of the rights of the persons intended to be benefited by this act, and the rights of such subcontractors, laborers, and material men to a lien shall not be affected thereby.”

The argument against the constitutionality of the act is that, by the amendment of 1893, the owner is prohibited from paying according to the terms of his contract, and the contractor is prevented from obtaining his pay, whenever it appears from the sworn statement that there are. bills outstanding in favor of subcontractors, laborers, or material men; and this, although no person to whom a bill is owing has notified the owner that he proposes to claim a hen. It is insisted that this provision of the law, if enforced, will utterly destroy the system, of credit as applied to the building business; that every contractor must pay cash or go out of business; that, no matter how [196]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ronnisch Construction Group, Inc v. Lofts on the Nine, LLC
886 N.W.2d 113 (Michigan Supreme Court, 2016)
Vugterveen Systems, Inc. v. Olde Millpond Corp.
560 N.W.2d 43 (Michigan Supreme Court, 1997)
Vugterveen Systems, Inc. v. Olde Millpond Corp.
533 N.W.2d 320 (Michigan Court of Appeals, 1995)
Queensboro Steel Corp. v. East Coast MacHine & Iron Works, Inc.
346 S.E.2d 248 (Court of Appeals of North Carolina, 1986)
Price Bros. v. Charles J. Rogers Construction Co.
304 N.W.2d 584 (Michigan Court of Appeals, 1981)
Williams & Works, Inc. v. Springfield Corp.
257 N.W.2d 160 (Michigan Court of Appeals, 1977)
Rowen & Blair Electric Co. v. Flushing Operating Corp.
239 N.W.2d 633 (Michigan Court of Appeals, 1976)
Georgia-Pacific Corp. v. Central Park North Co.
228 N.W.2d 380 (Michigan Supreme Court, 1975)
J Altman Companies, Inc. v. Saginaw Plumbing and Heating Supply Co.
202 N.W.2d 707 (Michigan Court of Appeals, 1972)
Sacchetti v. Recreation Co.
7 N.W.2d 265 (Michigan Supreme Court, 1943)
Chapel State Theatre Co. v. Hooper
175 N.E. 450 (Ohio Supreme Court, 1931)
Queal Lumber Co. v. Anderson
229 N.W. 707 (Supreme Court of Iowa, 1930)
Lazenby v. Wright
229 N.W. 437 (Michigan Supreme Court, 1930)
Niland v. Gill
99 Pa. Super. 107 (Superior Court of Pennsylvania, 1930)
Boulia-Gorrell Lumber Co. v. East Coast Realty Co.
148 A. 28 (Supreme Court of New Hampshire, 1929)
Hamtramck Lumber & Supply Co. v. United Home Builders
192 N.W. 575 (Michigan Supreme Court, 1923)
Kokomo, Frankfort & Western Traction Co. v. Kokomo Trust Co.
137 N.E. 763 (Indiana Supreme Court, 1923)
Ypsilanti Lumber & Coal Co. v. Leslie
188 N.W. 395 (Michigan Supreme Court, 1922)
Sandusky Grain Co. v. Borden's Condensed Milk Co.
183 N.W. 218 (Michigan Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
79 N.W. 1114, 121 Mich. 190, 1899 Mich. LEXIS 549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smalley-v-gearing-mich-1899.