Queensboro Steel Corp. v. East Coast MacHine & Iron Works, Inc.

346 S.E.2d 248, 82 N.C. App. 182, 1986 N.C. App. LEXIS 2421
CourtCourt of Appeals of North Carolina
DecidedAugust 5, 1986
Docket855SC886
StatusPublished
Cited by7 cases

This text of 346 S.E.2d 248 (Queensboro Steel Corp. v. East Coast MacHine & Iron Works, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Queensboro Steel Corp. v. East Coast MacHine & Iron Works, Inc., 346 S.E.2d 248, 82 N.C. App. 182, 1986 N.C. App. LEXIS 2421 (N.C. Ct. App. 1986).

Opinion

BECTON, Judge.

In this action, Queensboro Steel Corporation (Queensboro) asserted a materialman’s lien on funds owing from Cives Steel Company (Cives) to East Coast Machine & Iron Works, Inc. (East Coast) for steel supplied originally by Queensboro. Branch Banking and Trust Company (Branch Banking) sought to enforce a security interest in the accounts receivable of East Coast, which included the funds sought by Queensboro. The disputed funds were placed in escrow pending trial. The trial court denied a motion by Branch Banking for summary judgment and granted summary judgment in favor of Queensboro. Branch Banking appeals. We affirm.

I

The material facts are not in dispute. On 30 June 1981, East Coast executed a financing arrangement with Branch Banking. East Coast borrowed $1,050,000 from Branch Banking and secured the loan by assigning to Branch Banking a security interest in, among other things, all accounts receivable of East Coast. Branch Banking duly perfected its security interest.

Morrison-Knudson Company was a general contractor building a tobacco facility for R.J. Reynolds Tobacco Company in To-baccoville, North Carolina, near Winston-Salem. The general contractor hired Cives to provide reinforced steel for the project. Cives hired East Coast to provide the steel. East Coast purchased all or nearly all the steel from Queensboro. Queensboro fabricated the steel and delivered steel plate and other steel products to East Coast at its Bridgeton, North Carolina facility in late 1983 and early 1984. East Coast modified, reinforced, sandblasted and primed the steel and then delivered it to the building site in To- *184 baccoville. Cives owed East Coast $154,698.35 for the modified steel, and East Coast owed $153,277.55 to Queensboro.

East Coast is now bankrupt. Branch Banking sought to partially satisfy East Coast’s debt to the bank by enforcing its security interest in East Coast’s account receivable from Cives. Queensboro sought priority over the funds owing from Cives to East Coast by giving proper notice and bringing this action asserting a materialman’s lien on the funds as proceeds from the steel originally supplied by Queensboro for the Tobaccoville project. After several defendants were dismissed by stipulation, Branch Banking filed an answer and counterclaim. Both Queens-boro and Branch Banking moved for summary judgment. After a hearing, the trial court entered summary judgment in favor of Queensboro and denied Branch Banking’s motion for summary judgment. The trial court ordered that $152,337.19 be paid to Queensboro from the escrow fund. 1

On appeal, Branch Banking contends that the trial court erred in denying its motion for summary judgment and in granting summary judgment in favor of Queensboro. We find no error and affirm the judgment below.

II

Branch Banking argues first that summary judgment was inappropriate because there was a genuine issue of material fact whether any of Queensboro’s steel was ever delivered to the building site. See Rule 56(c), North Carolina Rules of Civil Procedure; Bone International, Inc. v. Brooks, 304 N.C. 371, 283 S.E. 2d 518 (1981). This argument is without merit. In March 1984, Branch Banking stipulated that Queensboro’s steel products were delivered to and used in the Tobaccoville facility. Moreover, nothing presented to the trial court contradicts the evidence that Queensboro’s steel was delivered to East Coast by Queensboro, delivered to the building site by East Coast, and actually used in the improvement.

The main issue before us is whether N.C. Gen. Stat. Sec. 44A-18 (1984), which grants a lien to subcontractors “who fur *185 nished labor or materials at the site of the improvement,” requires that the subcontractor claiming the lien personally deliver the materials to the building site. We hold that it does not.

A

Morrison-Knudson Company was the general contractor, contracting with the owner to improve real property in Tobaccoville. Cives, East Coast and Queensboro were first, second and third tier subcontractors, respectively, contracting to improve the same real property. See N.C. Gen. Stat. Sec. 44A-17 (1984). Queensboro does not base its claim on subrogation. Rather, it claims a lien against funds owed to East Coast, the party with whom it dealt. General Statute Section 44A-18 provides in part:

(3) A third tier subcontractor who furnished labor or materials at the site of the improvement shall be entitled to a lien upon funds which are owed to the second tier subcontractor with whom the third tier subcontractor dealt and which arise out of the improvement on which the third tier subcontractor worked or furnished materials.
(5) The liens granted under this section shall secure amounts earned by the lien claimant as a result of his having furnished labor or materials at the site of the improvement under the contract to improve real property, whether or not such amounts are due and whether or not performance or delivery is complete.

Branch Banking argues that these subsections unambiguously require that the lien claimant personally deliver the materials at the site. We disagree.

Generally, words in a statute that have not acquired a technical meaning must be given their “natural, approved, and recognized meaning.” Black v. Littlejohn, 312 N.C. 626, 638, 325 S.E. 2d 469, 478 (1985) (citation omitted); see Parnell-Martin Supply Company v. High Point Motor Lodge, Inc., 277 N.C. 312, 319, 177 S.E. 2d 392, 396 (1970). In determining whether statutory language is ambiguous, and therefore subject to judicial determination of legislative intent, courts may consult a dictionary. Black. In a legal context, “furnish” means “[t]o supply, provide, or equip, for *186 accomplishment of a particular purpose.” Black’s Law Dictionary 608 (5th ed. 1979); see Webster’s Third New International Dictionary, Unabridged 923-24 (1968) (“. . . to provide or supply with what is needed, useful, or desirable. . . .”).

It is not clear that the legislature, by requiring that materials be provided or supplied at the site by the lien claimant, intended to require personal delivery by the lien claimant. Another reasonable interpretation is that, while the lien claimant must provide the materials for the improvement of the real property with the intent that they ultimately arrive at the site, actual delivery of the materials on the premises may be made by anyone. We conclude that this statutory language is ambiguous.

The term “furnish” is used in almost every state’s mechanics’ lien statute. Annot., 32 A.L.R. 4th 1130, 1135 (1984). It is a “key concept,” sometimes treated as equivalent to delivery of the materials to the site, and sometimes “imposing a less stringent requirement.” Id. We must consider whether, in G.S. Sec. 44A-18, “furnished ... at the site” simply requires a delivery of the materials to the building site, or whether it also requires personal delivery by the lien claimant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nhung Ha v. Nationwide Gen. Ins. Co.
829 S.E.2d 919 (Court of Appeals of North Carolina, 2019)
Forsyth Memorial Hospital, Inc. v. Armstrong World Industries, Inc.
470 S.E.2d 826 (Court of Appeals of North Carolina, 1996)
Southeastern Steel Erectors, Inc. v. Inco, Inc.
424 S.E.2d 433 (Court of Appeals of North Carolina, 1993)
Syro Steel Co. v. Hubbell Highway Signs, Inc.
424 S.E.2d 208 (Court of Appeals of North Carolina, 1993)
Contract Steel Sales, Inc. v. Freedom Construction Co.
362 S.E.2d 547 (Supreme Court of North Carolina, 1987)
Contract Steel Sales, Inc. v. Freedom Construction Co.
353 S.E.2d 418 (Court of Appeals of North Carolina, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
346 S.E.2d 248, 82 N.C. App. 182, 1986 N.C. App. LEXIS 2421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/queensboro-steel-corp-v-east-coast-machine-iron-works-inc-ncctapp-1986.