Contract Steel Sales, Inc. v. Freedom Construction Co.

353 S.E.2d 418, 84 N.C. App. 460, 1987 N.C. App. LEXIS 2525
CourtCourt of Appeals of North Carolina
DecidedMarch 3, 1987
Docket8618SC599
StatusPublished
Cited by4 cases

This text of 353 S.E.2d 418 (Contract Steel Sales, Inc. v. Freedom Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contract Steel Sales, Inc. v. Freedom Construction Co., 353 S.E.2d 418, 84 N.C. App. 460, 1987 N.C. App. LEXIS 2525 (N.C. Ct. App. 1987).

Opinion

JOHNSON, Judge.

It is not disputed that plaintiff is a first tier subcontractor within the meaning of G.S. 44A-17(2) or that Du Pont is an owner obligor as defined by G.S. 44A-17(3), by virtue of funds that were owed to Freedom, the general contractor.

The two primary questions argued on appeal are (1) whether plaintiff furnished materials at the site of improvement to Du Pont’s real property as contemplated by G.S. 44A-18G), and (2) whether plaintiffs letter, dated 6 December 1983, substantially complied with the requirement of notice as stated in G.S. 44A-19.

If plaintiff, as a first tier subcontractor, furnished materials at the site of improvement then the lien granted pursuant to G.S. 44A-18(1), was perfected upon plaintiff giving written notice, as required by G.S. 44A-19, to Du Pont. Upon Du Pont’s receipt of the requisite written notice, Du Pont was under a duty, pursuant to G.S. 44A-20, to retain any funds subject to plaintiffs lien. Du Pont, pursuant to G.S. 44A-20(b), would be personally liable to plaintiff for any payments Du Pont made to Freedom after receipt of plaintiffs notice of claim of lien.

*463 I

We first address the question of whether plaintiff, pursuant to a contract with Freedom, a general contractor, furnished materials at the site of improvement to Du Pont’s real property. We hold that plaintiff furnished materials at the site of improvement to Du Pont’s real property as called for by the contract between plaintiff and Freedom. We express no opinion on the main issues preserved for trial by jury, to wit: (1) whether plaintiff is entitled to recover against either defendant Du Pont or defendant Freedom pursuant to the subcontract between plaintiff and defendant Freedom, and (2) whether the steel fabricated pursuant to the subcontract was defective or properly rejected by defendants.

The statute, G.S. 44A-18(1), by which plaintiff seeks to assert its lien, states the following:

(1) A first tier subcontractor who furnished labor or materials at the site of improvement shall be entitled to a lien upon funds which are owed to the contractor with whom the first tier subcontractor dealt and which arise out of the improvement on which the first tier subcontractor worked or furnished materials.

G.S. 44A-18G).

In Raleigh Paint and Wallpaper Co. v. Peacock & Associates, Inc., 38 N.C. App. 144, 247 S.E. 2d 728 (1978), disc. rev. denied, 296 N.C. 415, 251 S.E. 2d 470 (1979), this Court held that G.S. 44A-18 did not require a lien claimant who contracted with an owner to personally deliver materials to the site of improvement. Recently, this Court followed the example set in Raleigh Paint, supra, and made an exhaustive inquiry to determine whether the General Assembly intended that G.S. 44A-18 require a subcontractor to personally deliver materials to the site of improvement. See generally, Queensboro Steel Corp. v. East Coast Machine & Iron Works, Inc., 82 N.C. App. 182, 346 S.E. 2d 248 (1986). In Queensboro Steel Corp., supra, this Court held the following:

We now hold there is no such requirement under G.S. Sec. 44A-18. If a third tier subcontractor delivers to a second tier subcontractor with the intent that the materials ultimately be delivered at the site, and the materials are actually delivered at the site, the third tier subcontractor has a lien *464 on the funds owed to the second tier subcontractor for those materials.

Queensboro Steel Corp., supra, at 191, 346 S.E. 2d at 254 (emphasis supplied). Although the holding in Queensboro Steel Corp., supra, is not dispositive of the case sub judice this Court did review relevant case law, legislative history, and legal commentary from which we may draw guidance.

This Court in Queensboro Steel Corp., supra, noted the following: “[t]he term ‘furnish’ is used in almost every State’s mechanics’ lien statute. Annot., 32 A.L.R. 4th 1130, 1135 (1984). It is a ‘key concept,’ sometimes ‘imposing a less stringent requirement.’ ” Id. Queensboro Steel Corp., supra, at 186, 346 S.E. 2d at 251. The meaning of furnish as construed by this Court is to supply, provide or equip. Id. at 185-86, 346 S.E. 2d at 250. This Court in Queensboro Steel Corp., supra, noted the following pertinent observation:

In contrast to the State rules discussed in Annot., 32 A.L.R. 4th 1130, 1164-68, Secs. 11-13 (1984) and Annot., 39 A.L.R. 2d 394, 435-49, Secs. 11-16 (1955), North Carolina’s current mechanics’ and materialmen’s lien statutes apparently do not require actual incorporation of materials into the improvement, even when the materials are furnished to a subcontractor. See Urban & Miles, supra, at 303-04, 354-55. But see Fulp & Linville v. Kernersville Light and Power Company, 157 N.C. 154, 72 S.E. 869 (1911) (interpreting an older statute that has since been repealed). In some states, proof of actual use is required when the materials are delivered to a contractor or subcontractor rather than directly to the owner. This protects the owner against liens based on materials that are never actually delivered and of which the owner has no notice. This function is served in our State, at least in part, by the requirement that the materials be delivered at the site, whether by the lien claimant or by another party.

Queensboro Steel, supra, at 190, 346 S.E. 2d at 253. We hereby adopt the reasoning in Queensboro Steel, supra, and hold that materials are furnished within the meaning of G.S. 44A-18 if pursuant to a subcontract a subcontractor delivers materials to the site of improvement to real property.

*465 Bearing the foregoing in mind we now turn to the trial court’s pertinent findings of fact to determine if they support a conclusion of law that plaintiff did not furnish materials to the site of improvement. The trial court’s conclusion of law number 2 that “Contract Steel is not entitled to a lien on the funds or on the real property owned by Du Pont” indicates that the court concluded that plaintiff had not furnished materials at the site of improvement.

The trial court, sitting as the trier of fact, in pertinent part, made the following findings of fact:

4. In August and September, 1983, Contract Steel delivered reinforcing Steel to the jobsite. Some of these items, consisting of wire mesh and rebar, were incorporated into the improvement, and Contract Steel was paid $1,600. On September 6 and 15, angle frames, regalvanized angle frames and galvanized field bolts were delivered to the jobsite. On September 22, 1983, one load of galvanized structural steel was delivered to the jobsite. The total amount of the structural and fabricated miscellaneous steel at the jobsite on September 22, as a result of the deliveries on September 6, 15 and 22, was approximately 14 tons.
5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Distinctive Builders, Inc.
549 S.E.2d 496 (Court of Appeals of Georgia, 2001)
Cameron & Barkley Co. v. American Insurance
434 S.E.2d 632 (Court of Appeals of North Carolina, 1993)
State v. Milbradt
756 P.2d 620 (Oregon Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
353 S.E.2d 418, 84 N.C. App. 460, 1987 N.C. App. LEXIS 2525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contract-steel-sales-inc-v-freedom-construction-co-ncctapp-1987.