Cameron & Barkley Co. v. American Insurance

434 S.E.2d 632, 112 N.C. App. 36, 1993 N.C. App. LEXIS 1014
CourtCourt of Appeals of North Carolina
DecidedSeptember 21, 1993
Docket9210SC302
StatusPublished
Cited by8 cases

This text of 434 S.E.2d 632 (Cameron & Barkley Co. v. American Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cameron & Barkley Co. v. American Insurance, 434 S.E.2d 632, 112 N.C. App. 36, 1993 N.C. App. LEXIS 1014 (N.C. Ct. App. 1993).

Opinion

JOHN, Judge.

Plaintiff appeals an order granting summary judgment to defendants Blaine Hays Construction Company (Blaine Hays) and Marriott Corporation (Marriott) and denying its own motion for summary judgment. Plaintiff contends the trial court erred by ruling the “Claim of Lien and Notice of Claim of Lien” filed and served by plaintiff failed to comply with the notice requirements established in Article 2 of Chapter 44A of the North Carolina General Statutes, specifically those designated in N.C.G.S. § 44A-19 (1989). We disagree.

In particular, plaintiff, a second tier subcontractor, questions the court’s reading of the applicable sections of the statutory scheme. It asserts the notice requirements for the type of lien involved herein are controlled by N.C.G.S. § 44A-12 (1989), and that its “Claim of Lien and Notice of Claim of Lien” substantially complied therewith. Plaintiff therefore alleges its lien was perfected and its suit for enforcement timely filed, making it error for the court *38 to have granted defendants’ motion for summary judgment. Moreover, plaintiff contends defendants’ affidavit opposing plaintiff’s motion for summary judgment did not address or refute with sufficient specificity each point addressed in plaintiff’s affidavit supporting its motion. As a result, plaintiff requests we not only reverse the order of summary judgment in favor of defendants, but also grant plaintiff’s motion for partial summary judgment regarding particular factual allegations in its affidavit. We hold the trial court correctly construed the relevant statutes in determining plaintiff failed to provide proper notice of its claim of lien, and therefore affirm.

Pertinent facts include the following: in June 1987, Blaine Hays entered into a contract with Marriott for the construction of a Courtyard motel on a tract of real property owned by Marriott and located in Cary, North Carolina. In its capacity as general contractor for the project, Blaine Hays contracted out certain electrical work to a first tier subcontractor, Roper Electric Contractors, Inc. (Roper). Roper ordered from plaintiff electrical supplies and materials to be incorporated into the Courtyard project.

Plaintiff allegedly delivered, pursuant to its agreement with Roper, $63,919.78 worth of supplies and materials to the Courtyard construction site between 28 September 1987 and 5 January 1988. Roper subsequently abandoned work on the project, failed to compensate plaintiff, and filed for bankruptcy on 24 February 1988.

On 26 February 1988 plaintiff filed with the Wake County Clerk of Superior Court a document entitled “Claim of Lien and Notice of Claim of Lien” against the real property owned by Marriott, and served copies on Marriott, Blaine Hays, and Roper. Plaintiff thereafter sought to enforce its purported lien by filing a complaint on 17 May 1988, setting forth claims based on a lien on any funds owed by Blaine Hays to Roper, pursuant to N.C.G.S. § 44A-18(2) (1989), and on a lien upon the improved real estate by way of subrogation to any lien rights of Blaine Hays against Marriott, pursuant to N.C.G.S. § 44A-23 (1989 & Cum. Supp. 1992).

Defendants denied liability in their jointly-filed answer. On 1 November 1989, Blaine Hays filed a surety bond in the amount of $79,899.73, conditioning payment upon a finding the purported lien was properly noticed and perfected. Plaintiff and defendants filed cross-motions for summary judgment, and a hearing was held on 12 November 1991. The court issued a memorandum of decision, *39 memorialized by order dated 3 February 1992, which denied plaintiff’s motion and granted that of defendants.

The court’s order reasoned the document filed by plaintiff did not comply with the notice requirements of G.S. § 44A-23. Additionally, the court held plaintiff’s lien on funds also failed because no money was owing from Blaine Hays to Roper at the time plaintiff’s “Notice” was filed. Plaintiff appeals only that portion of the order granting defendants summary judgment on plaintiff’s claim to a lien by way of subrogation, foregoing its claim to a lien on funds.

I.

Plaintiff first maintains the trial court committed reversible error by granting defendants’ motion for summary judgment pursuant to Rule 56 of the North Carolina Rules of Civil Procedure. Summary judgment is designed to “ferret out those cases in which there is no genuine issue as to any material fact and in which, upon such undisputed facts, a party is entitled to judgment as a matter of law.” Haithcock v. Chimney Rock Co., 10 N.C. App. 696, 698-99, 179 S.E.2d 865, 867 (1971). The movant bears the burden of establishing that no genuine issue of material fact exists, and may carry that burden by “proving that an essential element of the opposing party’s claim is non-existent.” Executive Leasing Assocs., Inc. v. Rowland, 30 N.C. App. 590, 592, 227 S.E.2d 642, 644 (1976) (citation omitted).

In support of its motion below, defendants argued plaintiff’s lien was improperly noticed, was thus not perfected, and therefore plaintiff could not bring an action against defendants seeking enforcement of the alleged lien. The court agreed with defendants, stating in its order:

The claim of lien and notice of claim of lien filed and served by plaintiff fail to comply with the provisions of Chapter 44A . . . regarding liens by subrogation. Plaintiff failed to give proper notice of its claim of lien, in accordance with Article 2 of Chapter 44A, as required by . . . 44A-23. That being the case, plaintiff’s lien perfection action must fail as a matter of law.

A claim of lien must be properly noticed and properly filed, in order for the underlying lien to be perfected. If a lien is not per *40 fected, it cannot be enforced. Strickland v. General Bldg. & Masonry Contractors, Inc., 22 N.C. App. 729, 731, 207 S.E.2d 399, 400 (1974).

We note G.S. § 44A-23 was amended in 1991; however, the newer version of the statute is applicable only to actions filed on or after 22 July 1992. As plaintiff filed suit on 17 May 1991, the language of G.S. § 44A-23 in effect at that time controls, and provides as follows:

A . . . second . . . tier subcontractor, who gives notice as provided in this Article, may, to the extent of his claim, enforce the lien of the contractor created by Part 1 of Article 2 of this Chapter. The manner of such enforcement shall be as provided by G.S. 44A-7 through 44A-16. The lien is perfected as of the time set forth in G.S. 44A-10 upon filing of claim of lien pursuant to G.S. 44A-12. Upon the filing of the notice and claim of lien and the commencement of the action, no action of the contractor shall be effective to prejudice the rights of the subcontractor without his written consent.

G.S. § 44A-23 (1989) (emphasis added).

Plaintiff insists the notice requirements set out in G.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
434 S.E.2d 632, 112 N.C. App. 36, 1993 N.C. App. LEXIS 1014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cameron-barkley-co-v-american-insurance-ncctapp-1993.