Builder's Lumber Co. v. Stuart

94 N.W.2d 630, 6 Wis. 2d 356
CourtWisconsin Supreme Court
DecidedFebruary 3, 1959
StatusPublished
Cited by17 cases

This text of 94 N.W.2d 630 (Builder's Lumber Co. v. Stuart) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Builder's Lumber Co. v. Stuart, 94 N.W.2d 630, 6 Wis. 2d 356 (Wis. 1959).

Opinion

Broadfoot, J.

The first question to be determined is whether the trial court committed error in permitting judgment in favor of the mechanic’s lien claimants Stilter, Unger, Ihle, Hengel, Quisel, and Zahn.

The complaint made the following allegation:

“That the public records of La Crosse county, in the custody of the officials of La Crosse county, state of Wisconsin, entitled thereto, show the following alleged liens, judgments, and mortgages: . . .”

Thereafter it recited that each of said lien claimants had filed a claim for mechanic’s lien, giving the date of filing, together with the first and last days on which labor or materials were furnished, as well as the amount thereof. The complaint further alleged that the plaintiff had insufficient knowledge to form a belief as to the validity of the alleged liens and therefore denied the same and put each of said defendants to his proof.

The answer of Gateway Lumber Company alleged it had insufficient information to form a belief as to the validity and priority of the liens set forth in the complaint and therefore it denied the same and put the plaintiff and the other claimants to their proof.

The third appellant, Popple & Le Due Lumber Supply Company, Inc., did not put in an answer.

Upon the trial said lien claimants testified as to their agreements with the Stuarts, what labor and materials they furnished for the construction upon said lot 8, the reasonable value thereof, and the amount due. They further testified *361 that they had filed claims for lien or had caused the same to be done.

It is now contended that six of said lien claimants failed to prove their claims because they did not introduce the original claims for lien or certified copies thereof in evidence upon the trial. No issue was raised as to the filing of the claims for lien by the plaintiffs complaint or the answer of Gateway. The validity and priority thereof were challenged. The effect of the pleadings was to admit that claims of lien were filed on the dates specified in the complaint. No question was raised during the trial as to the form or contents of the claims for lien. In Wisconsin the lien laws are remedial in character and are to be liberally construed. Findorff v. Fuller & Johnson Mfg. Co. 212 Wis. 365, 248 N. W. 766; City Lumber & Supply Co. v. Fisher, 256 Wis. 402, 41 N. W. (2d) 285. In view of this rule the record supports a finding by the trial court that each of said claims was properly filed. Gateway does not challenge the proper filing of a claim for mechanic’s lien by the plaintiff, but contends that plaintiff failed to prove a contract with the owner of lot 8 to furnish materials for the improvement of lot 8. It appears from the record that plaintiff had no direct contract with the owner, Nelda Stuart. Its negotiations were all with her husband, Earl Stuart. Gateway contends that plaintiff did not present proper proof that Earl Stuart was the agent of his wife, and therefore plaintiff had no claim against her.

The complaint alleged that in contracting with plaintiff, Earl Stuart was the agent of Nelda Stuart. That allegation was not denied in Gateway’s answer. The record clearly shows an express contract between plaintiff and Earl Stuart for the furnishing of building materials to be used on lot 8. In addition thereto the record discloses that the Stuarts lived only two doors from lot 8 during the construction period; that Mrs. Stuart was present during the construction period; that other agreements for the improvement of lot 8 were *362 made with both of the Stuarts and that this was the fourth construction project in which both of the Stuarts engaged.

Since the allegation of agency in the complaint was not denied it was not an issue in the case and Gateway is bound by the pleadings. In DeByle v. Roberts, 273 Wis. 648, 653, 79 N. W. (2d) 115, the following from Restatement, 1 Agency, p. 65, sec. 22, comment b, was quoted with approval :

“ ‘Neither husband nor wife by virtue of the relationship has power to act as agent for the other. The relationship is of such a nature, however, that circumstances which in the case of strangers would not indicate the creation of authority or apparent authority may indicate it in the case of husband or wife. Thus, a husband habitually permitted by his wife to attend to some of her business matters may be found to have authority to transact all her business affairs.’ ”

With that rule in mind, the record supports a finding that Stuart was the agent for his wife and had authority to enter into the contract with plaintiff.

Upon the trial the manager of the plaintiff testified that plaintiff delivered building materials of the value of $2,692.38 to lot 8 for the buildings being erected thereon. He further testified that Earl Stuart called at plaintiff’s place of business with a truck and took delivery there of building materials valued at $3,276.68, which he stated were to be used for the improvement of lot 8, and that information was noted on the invoices. The trial court held that plaintiff was entitled to a lien only for the amount of materials it delivered to lot 8. The plaintiff contends that it was entitled to a lien for the full amount of the materials furnished.

Sec. 289.01, Stats. 1953, provided that every contractor who furnishes materials for the improvement of land shall have a lien therefor. There are two major doctrines involving the application of the lien laws. One is the doctrine that a delivery of materials to the building site or a furnishing of *363 such materials for the particular improvement to the owner or his agent is sufficient to maintain a mechanic’s lien. A second and more-restricted doctrine is that the materials must be actually used in the building or other improvement for which they were furnished in order to sustain a lien.

An annotation which discusses these doctrines and particular application thereof appears in 39 A. L. R. (2d) 397. A review of the Wisconsin cases starts on page 438 thereof. The following cases are there reviewed: Esslinger v. Huebner, 22 Wis. *632; Fitzgerald v. Walsh, 107 Wis. 92, 82 N. W. 717; Francis & Nygren Foundry Co. v. King Knob Coal Co. 142 Wis. 619, 126 N. W. 39; Barker & Stewart Lumber Co. v. Marathon Paper Mills Co. 146 Wis. 12, 130 N. W. 866.

The above cases, together with Neumann v. Strandt, 195 Wis. 610, 219 N.W. 348, are cited in the plaintiffs brief. In the Neumann Case the court stated the rule as follows (p. 613) :

“Thus materials and services can be furnished upon the credit of the building to be erected and the land upon which it stands. Otherwise the owner of real estate might, as against materials furnished and services rendered, unjustly enrich himself at the expense of the materialman furnishing materials and those rendering services. In the early case of Esslinger v. Huebner, 22 Wis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Bank N.A. v. Jack W. Collier
2014 WI 62 (Wisconsin Supreme Court, 2014)
Queensboro Steel Corp. v. East Coast MacHine & Iron Works, Inc.
346 S.E.2d 248 (Court of Appeals of North Carolina, 1986)
R. Fredrick Redi-Mix, Inc. v. Thomson
292 N.W.2d 648 (Wisconsin Supreme Court, 1980)
Beneficial Finance Co. v. Wegmiller Bender Lumber Co.
402 N.E.2d 41 (Indiana Court of Appeals, 1980)
Amoco Oil Co. v. Capitol Indemnity Corp.
291 N.W.2d 883 (Court of Appeals of Wisconsin, 1980)
Goebel v. National Exchangors, Inc.
277 N.W.2d 755 (Wisconsin Supreme Court, 1979)
State v. Lunz
273 N.W.2d 767 (Wisconsin Supreme Court, 1979)
Raleigh Paint & Wallpaper Co. v. Peacock & Associates, Inc.
247 S.E.2d 728 (Court of Appeals of North Carolina, 1978)
RALEIGH PAINT & WALLPAPER v. Peacock & Assoc.
247 S.E.2d 728 (Court of Appeals of North Carolina, 1978)
Kilgust Heating Division of Wolff, Kubly & Hirsig, Inc. v. Kemp
235 N.W.2d 292 (Wisconsin Supreme Court, 1975)
Smith v. Osborn
223 N.W.2d 913 (Wisconsin Supreme Court, 1974)
Ohio Casualty Ins. Co. v. Holz & Holz, Inc.
129 N.W.2d 330 (Wisconsin Supreme Court, 1964)
Christensen v. Dorman
320 F.2d 213 (Seventh Circuit, 1963)
Lee v. Junkans
117 N.W.2d 614 (Wisconsin Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.W.2d 630, 6 Wis. 2d 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/builders-lumber-co-v-stuart-wis-1959.