R. Fredrick Redi-Mix, Inc. v. Thomson

292 N.W.2d 648, 96 Wis. 2d 715, 1980 Wisc. LEXIS 2602
CourtWisconsin Supreme Court
DecidedJune 3, 1980
DocketNo. 77-885
StatusPublished
Cited by7 cases

This text of 292 N.W.2d 648 (R. Fredrick Redi-Mix, Inc. v. Thomson) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. Fredrick Redi-Mix, Inc. v. Thomson, 292 N.W.2d 648, 96 Wis. 2d 715, 1980 Wisc. LEXIS 2602 (Wis. 1980).

Opinion

COFFEY, J.

This is a review of an action to foreclose a construction lien that R. Fredrick Redi-Mix, Inc. (Redi-Mix), claimed on a two building apartment complex in New Berlin owned by Thomas and Loretta Thomson, the defendants. The trial court entered judgment granting foreclosure of Redi-Mix’s construction lien on the premises. The court of appeals reversed the trial court’s judgment.

The record establishes that Redi-Mix, a Wisconsin Corporation, is engaged in the business of manufacturing, selling and distributing ready mix concrete, and furnished the concrete, wire mesh and reinforcing rods used in the construction of the apartment complex. The complex consisted of two buildings referred to as the “east” and “west” buildings. Each of the buildings was located on an adjacent parcel of land with separate legal descriptions and addresses.1

Initially, Redi-Mix furnished materials to K & H Construction, Inc. (K & H), the first masonry and concrete subcontractor, from March 31st until November 26, 1971 for use in the construction of the apartment complex. During this period, K & H experienced financial difficulties and defaulted in their payments to Redi-Mix for the materials provided. Thereafter, the Thomsons dis[718]*718charged K & H from the construction project and hired the Don Teffer Construction Corporation (Teffer) to complete the masonry and concrete construction work. Redi-Mix, at the request of Teffer, continued to supply the concrete and materials to complete the construction of the two buildings on the project site. Redi-Mix commenced delivery of materials to Teffer in November of 1971, with the last delivery being made on August 4, 1972 and during this period Teffer made timely payments for all the materials supplied.

Because of K & H’s default in payments, Redi-Mix was compelled to institute legal action and served a notice of intent to file a lien claim on April 21, 1972 on the Thomsons, owners of the property. Redi-Mix in compliance with sec. 289.06(1), Stats., on May 25, 1972 filed a lien claim against the “west” building rather than the “east” building for the labor and materials furnished to K & H for the building project. Shortly thereafter, Redi-Mix became aware of a mistake in their failing to identify the proper building in the lien claim and realized that the labor and materials, the subject of the lien claim, were used in the construction of the “east” building rather than the “west” building. To rectify this mistake, on August 30, 1972, Redi-Mix served an amended (second) notice of intent to file a lien and on November 2, 1972 filed an amended lien claim for labor and materials furnished between June 25, 1971 and August 4, 1972 on both the “east” and the “west” buildings.

Almost two years later, on May 7, 1974, Redi-Mix commenced a lawsuit to foreclose its lien against the Thomsons’ property and requested a judgment in the amount of $12,223.84 plus interest and costs. The defendants answered the complaint with the filing of a general denial.

In June of 1974 the mortgagees of the properties, the subject of the lien foreclosure action, Mutual Savings and Loan Association and Great Midwest Savings and [719]*719Loan, pursuant to sec. 289.08(1) Stats.,2 deposited the sum of $15,279.80 with the Waukesha county court as security to insure payment of Redi-Mix's construction lien. The court, after a hearing on June 10,1974, ordered the lien claim on the real estate satisfied of record and also discharged the lis pendens on file against the property. The construction lien claim, pursuant to sec. 289.08 (4), Stats.,3 thus became attached to the security (money) on deposit with the clerk of courts.

[720]*720The trial court found that the plaintiff, Redi-Mix, had supplied “materials and labor,” including the ready mix concrete used in the construction of the apartment buildings on the defendants’ property. The court further found that there remains due and payable to the plaintiff [Redi-Mix] from K & H Construction, Inc., the principal amount of $12,223.84, plus interest and costs of $3,766.38, for materials and labor furnished in the construction of the “east” building. The court ruled that the amended lien claim, filed November 2, 1972, secured payment of the principal amount found due and owing. The court further found the amount of the claim was reasonable. The court entered judgment in favor of the plaintiff, Redi-Mix, and ordered payment of the principal sum, including interest and costs, from the security fund in satisfaction of the judgment.

The defendants, Thomsons, appealed from the adverse judgment awarding Redi-Mix the sum of $15,990.22 and the court of appeals reversed. The court of appeals held that Redi-Mix’s lien was unenforceable as not having been perfected in accordance with the statute, sec. 289.06, Stats. Specifically, the court of appeals concluded that:

1. The original notice of intent to file a lien claim and the lien claim itself were unenforceable on their face because the legal descriptions of the building and property in the documents were inaccurate. The materials that were the subject of this lien foreclosure action had been used exclusively in the construction of the “east” building rather than the “west” building. Therefore, the original lien notice and lien claim were in error and thus unperfected and unenforceable.

2. The court of appeals further ruled that the amended notice and claim for lien, containing a description of both the “east” and “west” building properties, were also unenforceable because the plaintiff failed to file the lien claim within the statutorily mandated time [721]*721limit of six months from the date of delivery of the last labor or materials (on or before May 26, 1972), pursuant to sec. 289.06(1), Stats. The court of appeals concluded that since Redi-Mix’s lien arose as a result of the unpaid labor and materials furnished to K & H for the construction project, as opposed to the materials furnished to Teffer, Redi-Mix was required to file its lien claim within six months from the date it last delivered labor or materials to K & H, the original masonry contractor, rather than Teffer, the succeeding masonry contractor:

“. . . the last supplies were delivered to K & H on November 26, 1971. The amended lien claim was filed November 2, 1972, almost a year later. Redi-Mix argues that materials were delivered to the east building in August 1972 and, therefore, the lien claim was timely. We cannot accept that argument. The materials supplied in August 1972 were delivered, not to K & H, but to its successor subcontractor, Don Teffer Construction Corporation. Since Redi-Mix admits that all materials furnished to Don Teffer were paid for and that the lien does not relate to them, the deliveries made to Don Teffer cannot be used to extend the time in which to file the lien claim based on materials furnished to K & H. We read sec. 289.06(1), Stats., to mean the lien claim must be filed within six months of the date the last materials for which the lien is claimed were furnished.”

3. The court of appeals also held that the amended notice and lien claim failed to rectify the mistake in the legal description on the grounds that it did not effectively relate back to the original notice and claim for lien and therefore it was not timely filed, stating as follows:

. .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunzinger Construction Co. v. Scs of Wisconsin, Inc.
2005 WI App 47 (Court of Appeals of Wisconsin, 2005)
Hoida, Inc. v. M&I MIDSTATE BANK
2004 WI App 191 (Court of Appeals of Wisconsin, 2004)
Daughtry v. MPC Systems, Inc.
2004 WI App 70 (Court of Appeals of Wisconsin, 2004)
Riverwood Park, Inc. v. Central Ready-Mixed Concrete, Inc.
536 N.W.2d 722 (Court of Appeals of Wisconsin, 1995)
Torke/Wirth/Pujara, Ltd. v. Lakeshore Towers of Racine
531 N.W.2d 419 (Court of Appeals of Wisconsin, 1995)
Wes Podany Const. Co., Inc. v. Nowicki
354 N.W.2d 755 (Court of Appeals of Wisconsin, 1984)
State Central Credit Union v. Bigus
304 N.W.2d 148 (Court of Appeals of Wisconsin, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
292 N.W.2d 648, 96 Wis. 2d 715, 1980 Wisc. LEXIS 2602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-fredrick-redi-mix-inc-v-thomson-wis-1980.