Wes Podany Const. Co., Inc. v. Nowicki

354 N.W.2d 755, 120 Wis. 2d 319, 1984 Wisc. App. LEXIS 4038
CourtCourt of Appeals of Wisconsin
DecidedJuly 24, 1984
Docket83-1657, 83-2083
StatusPublished
Cited by8 cases

This text of 354 N.W.2d 755 (Wes Podany Const. Co., Inc. v. Nowicki) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wes Podany Const. Co., Inc. v. Nowicki, 354 N.W.2d 755, 120 Wis. 2d 319, 1984 Wisc. App. LEXIS 4038 (Wis. Ct. App. 1984).

Opinion

MOSER, J.

This is an appeal from separate summary judgments dismissing Wes Podany Construction Co., Inc.’s (Podany) lien foreclosure actions against two condominium properties in the Parnell Woods Condominiums, one owned by Thomas and Barbara Bauman (Bau-mans) and the other by Raymond W. Quandt and Ruth Quandt (Quandts). Podany appeals.

On January 1, 1979, Podany entered into a contract with Walter A. Nowicki (Nowicki) to provide masonry work and materials for the condominium project. During the time Podany supplied his materials and accomplished his masonry work, Nowicki sold Unit 1 in Building 16 to the Baumans. The Baumans’ deed was recorded in the register of deeds office on October 15, 1979. No-wicki sold Unit 1 in Bulding 11 to the Quandts and the deed was recorded on December 10, 1979. Podany completed the work on or about December 14, 1979. On February 20, 1980, he gave Nowicki a notice of intent to file a lien claim against the condominium properties in Buildings 11 and 16 as required under sec. 779.06(2), Stats. On May 12, 1980, Podany filed his lien pursuant to sec. 779.06(1) and (3), Stats., 1 for the separate amounts of *322 $2,151 and $2,577.44 against the Quandts’ and the Bau-mans’ units respectively.

On September 26, 1983, and on November 16, 1983, Podany filed his summonses and complaints for foreclosure against the Baumans’ and the Quandts’ condominium units. 2 The record does not disclose whether the Baumans answered the complaint, but the Quandts did answer. Both the Baumans and the Quandts moved for summary judgment on the basis that they, as owners, received no notice of intent to file a lien claim under sec. 779.06(2), Stats. Both trial courts granted summary judgment.

*323 There is no question that at the time Podany contracted for and commenced the mason work on Units 11 and 16 Nowicki was the owner of the premises. It is less clear from the record when Podany did the last work on these premises, but there is no question as to whether Podany’s last work was completed within five months prior to the notice of intent to file lien sent to Nowicki. It is undisputed that the lien was filed within thirty days after the notice of intent was served upon Nowicki or within six months after the last work was completed on the units as required by law. Likewise, it is undisputed that separate foreclosure complaints against the unit owners were filed within two years after the last work on the subject property.

The sole issue on this appeal is whether the notice of intent to file a lien under sec. 779.06(2), Stats., served on Nowicki was effective to allow a lien foreclosure against the Baumans’ and the Quandts’ condominium units.

Both trial courts held that because no notice of intent to file a lien was provided to the Baumans and the Quandts as required under sec. 779.06(2), Stats., and because they were the owners on the day the notice of intent to file a lien was served on Nowicki, no lien foreclosure could be brought against the Baumans and Quandts. Therefore, they dismissed the complaints via summary judgment.

Podany argues that the notice of intent to file a lien under sec. 779.06(2), Stats., must be served on the owner of the premises who was owner at the time the prime contractor first furnished work or materials on the premises. This party remains the owner, he argues, regardless of any transfer of ownership between the date of the first furnishing of work or materials and the date of the service of the notice of intent to file a claim for lien, unless the material and labor contractor had actual or constructive notice of any conveyance within that pe *324 riod. He cites as authority the supreme court decision in Duitman v. Liebelt. 3 The Baumans and Quandts argue that Duüman is not authority for the instant case because the statute on which that decision was based is no longer the Wisconsin law. 4

Construction liens for work and materials are purely statutory and cannot be maintained beyond the extent of the legislative grant conferred. 5 One pursuing rights under the Wisconsin construction lien law must follow the statute or lien rights fail. 6 Nevertheless, our lien laws are remedial in character and are to be liberally construed to give effect to the legislative intent of protecting the claims of tradesmen, laborers and material-men for work and materials supplied. 7

The 1957 statutes separated lien rights of contractors and subcontractors. 8 In 1967 the state legislature removed this difference in situations where labor and material suppliers work directly for the owner; the legislature established those suppliers as prime contractors. 9 In 1979 the whole subject of liens was transferred to ch. 779 of the statutes. 10 In the 1967 revision there were some changes, including the creation of the notice of intent to file for lien under sec. 289.06(2), Stats. (1967), *325 which remained the same under sec. 779.06(2), Stats. (1979). The notice required under sec. 289.02(2), Stats. (1965), was merged into sec. 289.06, Stats. (1967), and sec. 779.06, Stats. (1979). 11 Generally stated, after the 1967 changes, a prime contractor for an owner was required to meet the notice of intent to file a lien and lien filing requirements to preserve his lien, provided that he hired no subcontractors to fulfill the work and materials requirements of his contract. 12 To protect his prime contractor’s lien after 1968, and to this date, the contractor for an owner is required to follow the mandates of what is presently sec. 779.06, Stats. 13

The term “prime contractor” was introduced to the lien statutes in sec. 289.01(2), Stats. (1967), partially to avoid the anomalous treatment of construction contractors. The term encompasses only those persons who deal directly with the owner. It further recognizes the distinction between prime contractors who contract to improve the land of someone else and the owner who does the general contracting for improvements of his own land. Both, in fact, are prime contractors. Under prior law, and in a factual situation like that in Duitman, a subcontractor might suddenly find himself a contractor if he dealt with an owner who happened to be his general contractor. 14

*326

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc.
2022 WI 44 (Wisconsin Supreme Court, 2022)
Bayland Buildings, Inc. v. Spirit Master Funding VIII, LLC
2017 WI App 42 (Court of Appeals of Wisconsin, 2017)
Watertown Regional Medical Center, Inc. v. General Casualty Insurance
2014 WI App 62 (Court of Appeals of Wisconsin, 2014)
American Wood Dryers, Inc. v. Bombardier Capital, Inc.
305 F. Supp. 2d 966 (W.D. Wisconsin, 2002)
Golden Valley Supply Co. v. American Insurance
537 N.W.2d 58 (Court of Appeals of Wisconsin, 1995)
Torke/Wirth/Pujara, Ltd. v. Lakeshore Towers of Racine
531 N.W.2d 419 (Court of Appeals of Wisconsin, 1995)
Plumber's Local 458 Holiday Vacation Fund v. Howard Immel, Inc.
445 N.W.2d 43 (Court of Appeals of Wisconsin, 1989)
Estate of Riese Ex Rel. Commercial & Savings Bank of Monroe v. Weber
389 N.W.2d 640 (Court of Appeals of Wisconsin, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
354 N.W.2d 755, 120 Wis. 2d 319, 1984 Wisc. App. LEXIS 4038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wes-podany-const-co-inc-v-nowicki-wisctapp-1984.