Maeshall, J.

Three questions are presented for consideration on this appeal: (1) What was the indebtedness of defendant to plaintiff for the work rendered by the latter, mentioned in the complaint? (2) Is an architect entitled to a lien, under sec. 3314, Stats. 1898, for compensation for making plans, specifications, and estimates for a contemplated building upon the land of another, if the construction of the building, pursuant to such plans, be commenced, though the use ■of them be abandoned before anything is done except a part ■of the excavating for the basement ? (3) Was the construction of the building commenced according to the plans and ¡specifications furnished by plaintiff ?

1. Appellant’s counsel contended that, respondent having .agreed in writing to make plans and specifications for the building and to superintend its erection for the stipulated price of $1,000, an express contract was necessary to give him' a legal claim upon the appellant for services rendered [95]*95without objection, not included in such contract, basing such contention on the rule governing the relations of master and servant and that between an officer of a corporation and his principal in regard to personal services. Such rule does not apply to a situation of the kind in question. It is well settled that where a builder is ordered to make changes from the original contract plans, which are really extras, or to do work in some way connected with the original contract but substantially independent of it, and the circumstances are such that the proprietor must know that the execution of •such orders will cause extra labor and expense to the builder not contemplated by either party in the original contract, he is liable to compensate the builder therefor in the absence ■of some express provision in such original contract to the contrary. The rule is stated in 1 Hudson, Building Cont. (2d ed.), 358, citing Gibbons v. United States, 15 Ct. Cl. 174, thus: “ Where a change in the contract is ordered amid circumstances which imply or warrant-the belief that no extra cost will result from the change, it is the duty of the contractor to notify the other party that he cannot make the change without extra price. But where a change is ordered which must necessarily cause increased expense, no such notice is necessary.” Such -work cannot be said to have been in contemplation by the parties at the time of making the contract for the construction of the building. There was no meeting •of minds on that subject. So the doing of such work when ■ordered, without objection, cannot reasonably be said to be voluntary and without expectation of compensation if the ■expense to the builder is thereby necessarily materially increased. In such circumstances an implied promise arises to pay for the extra or independent work, in the absence of anything in the contract to the contrary. Boody v. R. & B. R. Co. 24 Vt. 660, 665; Wait, Engineering & Arch. Jur. 490; Escott v. White, 10 Bush, 169.

How the trial court found, on such evidence that the find[96]*96ing cannot be disturbed, that respondent, pursuant to his; contract with appellant, made complete plans and specifications for a building to be erected on appellant’s premises,, and that they were accepted. That branch of the contract was thereby fully executed. Respondent did not agree to> make all plans and specifications appellant might order in contemplation of the construction of a building, but to make-plans and specifications for the proposed building. The only reasonable, sensible construction of that language is that it called for one set of acceptable plans and specifications. That being satisfied, the acceptance of an order for another set was neither within, nor a mere extra, incidental to, the original contract.

The accepted order for the second set of plans was rightly decided by the trial court to constitute a new contract having no relation to the work under the written contract, and not governed thereby except as to the price for the new work. Nothing having been said about compensation therefor, it was fair to presúmelas the trial court did, that both parties contemplated that it would be paid for at the same-rate as the original work of the same nature, called for by the writing.

It is considered that there were two separate and distinct contracts in this case as plainly as there was in Hand v. Agen, 96 Wis. 493. The first contract, exclusive of the work of superintending the construction of the building, having-been fully executed, the rule announced in Boody v. R. & B. R. Co. 24 Vt. 665, applies: “Where the parties [under a special contract] deviate from the original plan agreed upon, and the terms of the original contract do not appear-to be applicable to the new work, it being beyond what was originally contemplated by the parties, it is undoubtedly to-be regarded and treated as a work wholly extra, out of the-scope of the contract, and may be recovered for as such.”

We do not understand that, conceding the above theory [97]*97to be correct, it is claimed that the amount of the indebtedness of appellant to respondent was placed too high by the trial court. In any event, the finding in that regard is well supported by the evidence.

2. The right .to a lien under oh. 143, Stats. 1898, for work done in the construction of a building, is not dependent upon whether a building is actually constructed, but upon whether such construction is commenced. If the latter circumstance occur, and lienable work be done in aid thereof, the right of lien thereby becomes perfect and cannot thereafter be defeated by any act of the proprietor. The language of sec. 3314 is that the lien for work done in the construction of a building shall be prior to any other lien which originates subsequent to the commencement of such construction. Sec. 3321 provides for joining in one action all claims on the property affected. Sec. 3324 provides that the judgment shall direct a sale of all the right, title, and interest which the owner had in the property at the time of the commencement of the work. And sec. 3325 provides for the distribution of the proceeds of a sale made pursuant to the judgment, among all the lien clairhants without priority, clearly indicating that, without reference to when the indebtedness of the respective lien claimants on the same property accrued, if there be several and the liens be for work done or material furnished in the construction of a building, they shall all attach at the same time; that is, at the time of the commencement of the construction. That was decided to have been the legislative intention in Vilas v. McDonough Mfg. Co. 91 Wis. 607, where it was held that the right of lien for machinery manufactured and furnished for a sawmill after the commencement of the construction of the mill building, related back and attached to the property at the time of the commencement of such construction, regardless of when work commenced on the machinery at the factory or when it was attached to such building, and took prece-[98]*98clence of a mortgage placed on the property in the meantime.

Statutes similar to ours exist in Indiana, Kansas, Maryland, New Jersey, and other states, and have been construed there as in Vilas v. McDonough Mfg. Co., the courts m some instances remarking that such statutes evidence the intent indicated so plainly as to leave no room for judicial construction. Kansas M. Co. v. Weyerhaeuser, 48 Kan. 335.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FOREST CONST. v. Farrell-Cheek Steel Co.
484 So. 2d 40 (District Court of Appeal of Florida, 1986)
Waddington v. Wick
652 S.W.2d 147 (Missouri Court of Appeals, 1983)
Williams & Works, Inc. v. Springfield Corp.
293 N.W.2d 304 (Michigan Supreme Court, 1980)
Goebel v. National Exchangors, Inc.
277 N.W.2d 755 (Wisconsin Supreme Court, 1979)
Mortgage Associates, Inc. v. Monona Shores, Inc.
177 N.W.2d 340 (Wisconsin Supreme Court, 1970)
Nolte v. Smith
189 Cal. App. 2d 140 (California Court of Appeal, 1961)
Builder's Lumber Co. v. Stuart
94 N.W.2d 630 (Wisconsin Supreme Court, 1959)
Clark v. Smith
290 N.W. 592 (Wisconsin Supreme Court, 1940)
Gaastra v. Bishop's Lodge Co.
299 P. 347 (New Mexico Supreme Court, 1931)
W. H. Pipkorn Co. v. Tratnik
152 N.W. 141 (Wisconsin Supreme Court, 1915)
Lamoreaux v. Andersch
150 N.W. 908 (Supreme Court of Minnesota, 1915)
Sabin v. Cameron
133 N.W. 422 (Nebraska Supreme Court, 1911)
Rieflin v. Grafton
115 P. 851 (Washington Supreme Court, 1911)
Barker & Stewart Lumber Co. v. Marathon Paper Mills Co.
130 N.W. 866 (Wisconsin Supreme Court, 1911)
Tonopah Lumber Co. v. Nevada Amusement Co.
30 Nev. 445 (Nevada Supreme Court, 1908)
Hennessey v. Fleming Bros.
40 Colo. 27 (Supreme Court of Colorado, 1907)
Taylor v. Dall Lead & Zinc Co.
111 N.W. 490 (Wisconsin Supreme Court, 1907)
Halsey v. Waukesha Springs Sanitarium Co.
104 N.W. 94 (Wisconsin Supreme Court, 1905)
Rogers-Ruger Co. v. Murray
59 L.R.A. 737 (Wisconsin Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
82 N.W. 717, 107 Wis. 92, 1900 Wisc. LEXIS 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitzgerald-v-walsh-wis-1900.