Gibbons v. United States

15 Ct. Cl. 174
CourtUnited States Court of Claims
DecidedDecember 15, 1879
StatusPublished
Cited by4 cases

This text of 15 Ct. Cl. 174 (Gibbons v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbons v. United States, 15 Ct. Cl. 174 (cc 1879).

Opinions

Nott, J.,

delivered the opinion of the court:

The first and most important question in this case is as to the construction that should be given to the second clause of the specifications, which is in these words: “ The foundations and the brick walls now standing that were uninjured by the fire will remain and be carried up to the height designated on the plan by new work?.

[190]*190When it becomes the duty of a court to- ascertain the true construction which should be given to a disputed article of a contract, there are three things which ordinarily should be the subject of consideration: 1st, the circumstances, known to both parties, which preceded and attended the making of the contract in the light of which it should be interpreted; 2d, the general purpose of the contract and those specific provisions which directly or indirectly bear upon and affect the provision which is the subject of controversy; 3d, the language and effect of the clause or article to which a construction must be applied. We will consider these in their order.

The circumstances known to both parties which preceded and attended the making of this contract were these:

The old walls were in the possession and under the control of the defendants. It was to their interest that as much as possible of these old walls should be saved, yet that no imperfect portion should be retained. To a contractor it mattered not until he entered into a contract whether much or little should be utilized. If the former, there would be so much the less work for him to do; if the latter, he would be paid for doing so much the more; in either case, he could regulate his bid by the amount of old wall that was to enter into the new building. But it was vital to every contractor to know how much of the old walls woidd remain, and how much new work he must contribute. A superficial inspection would not tell the bidders what was the real condition of the walls. It was necessary that they be dismantled of the injured parts, if the contractors sending in proposals were to make close and accurate estimates ; otherwise every bidder would leave margin enough in his calculations to cover the unknown contingency, and the result might be that the government would- be allowed little or nothing for the old walls. Such being the conditions of the case, the officers of the government, instead of leaving the walls' as the fire left them, and turning them over to the contractor to be razeed by him to such extent as might be found necessary, pulled down what they deemed the imperfect portions, and apparently left only so much of them standing as was fit for the new superstructure. They next prepared the specifications afterward annexed to the contract, and then, handing the contractor a copy of these specifications on the one hand and show[191]*191ing him the razeed walls on the other, invited him to make proposals for erecting a superstructure.

These circumstances, so far as they go, point to an interpretation favorable to the claimant. “ The duty of the court is to ascertain not what the parties may have secretly intended as contradistinguished from what their words express, but what is the meaning of words they have used. It is merely a duty of interpretation, that is, to find out the true sense of the written words as the parties used them; and of construction, that is, when the true sense is ascertained, to subject the instrument in its operation to the established rules of law.” (1 Greenl. § 277, p. 323.) If the defendants had turned the old walls over to the contractor untouched at the time he entered into the contract, that would have been a significant, a controlling fact against him. If it was not their intention to save the uninj ured portion of the walls and reject the injured, why did they touch them ? If the contractor was to assume the risk of the old walls, what object had the defendants in apparently rejecting- and apparently retaining a portion before inviting his bid ? Somebody had to assume the risk of the old walls being fit to build upon. Responsibility for their fitness (in the absence of express words to the contrary) would naturally be assumed by the party who owned them, and controlled them, and put them into the contract, and who apparently had prepared them for the uses and purposes of the contract. It would be contrary to the ordinary dealings of men to infer, from such circumstances, that the party who did not own them or control them, who did not put them into the work as his contribution toward the new building, and who had not examined, tested, or prepared them for a new superstructure, was to assume and be responsible for their fitness.

• The other terms and provisions of the contract which have any bearing upon this point are not very significant, but, so far as they go, are likewise favorable to the claimant. In the first place, the contract, like the advertisement upon which it was founded, was not for rebuilding the edifice, but for “ repairs.” In the second place, the contract expressly throws “the risk and expense of all the materials and work” which the claimant was to “furnish” upon him, but does not in terms, if at all, throw upon him any risk as to the fitness of the walls furnished by the defendants. In the third place, the contract [192]*192also expressly provides uthat all the materials furnished and work performed ” by tbe claimant “should he of the best quality and subject to the inspection, approval, or rejection” of the defendant’s superintendent. The old walls were neither material furnished nor work performed by the claimant, and there was no provision expressly authorizing their rejection by the party who furnished them. In the fourth place, the contract is not like that in Dermott v. Jones (2 Wall., 1), where the contractor agreed to build a house and have it “ fit for use and occupation” by a certain day. Here the contractor simply agreed to repair a partially existing building under the supervision of the other party’s officers and according to the plans and specifications annexed. In other words, his responsibility for the fitness of the old walls does not, if it exist, spring out of the general purpose or express covenants of the contract, but must be attributed entirely to the single clause of the specifications which has been quoted.

That clause of the specifications was prepared by the defendants before the .contract was made, and was shown to the claimant when he was estimating for the work. Upon the faith of it he made his bid. Its language is, “ The foundations and the brick walls now standimg that were uninjured by the fire will remain and be carried up to the height designated on the plan by new work.” It is manifest that this language needs some amplification to make its meaning clear. The defendants contend ip effect that it means [“ So much of] the foundations and the brick walls now standing [as subsequent examination may show] were uninjured by the fire will remain and.be carried up.” The claimant contends that the true construction is, The foundations and the brick walls now standing [being those portions'] that were uninjured by the fire will remain.”

As was held by the Supreme Court in Garrison Case (7 Wall., 688; 7 C. Cls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orino v. United States
77 F. Supp. 938 (Court of Claims, 1948)
Fitzgerald v. Walsh
82 N.W. 717 (Wisconsin Supreme Court, 1900)
Woolverton v. United States
27 Ct. Cl. 292 (Court of Claims, 1892)
Otis v. United States
20 Ct. Cl. 315 (Court of Claims, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
15 Ct. Cl. 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbons-v-united-states-cc-1879.