Escott v. White

73 Ky. 169, 10 Bush 169, 1873 Ky. LEXIS 72
CourtCourt of Appeals of Kentucky
DecidedMarch 27, 1873
StatusPublished
Cited by14 cases

This text of 73 Ky. 169 (Escott v. White) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Escott v. White, 73 Ky. 169, 10 Bush 169, 1873 Ky. LEXIS 72 (Ky. Ct. App. 1873).

Opinion

JUDGE PRYOR

delivered the opinion op the court.

The appellees, White & Son, entered into an agreement in writing with the appellants, Escott & Son, by which they undertook to remodel a building in the city of Louisville, owned by the latter, according to the plan and specifications made by the architect, Andrewartha. The price to be paid was four thousand eight hundred and fifty dollars, all of the money to be paid as the work progressed except twenty-five per cent of the amount, and this was to be retained by the appellants for one month after the inspection and acceptance of the work by the architect, with the right of the appellants to apply the same to the payment of any damages that the employers might sustain by reason of the failure of the appellees to comply with their contract. It was further stipulated “that in no event will any work be considered extra under this contract unless the same shall be ordered in writing by the proprietor, [171]*171indorsed by the architect, and the amount added to this contract in writing.”

If the work was delayed, the architect, who was to superintend the work, had the right to employ others to complete it, and deduct the costs from the contract price.

Other clauses are contained in the agreement not necessary to be recited in determining the rights of the parties.

White & Son instituted this action on the agreement in the common pleas court, alleging the performance of the contract on their part, the acceptance of the work by the appellants, and their failure to pay the contract price, having paid them only the sum of $4,092.50. They further allege that at the instance and request of the defendants (appellants) they performed extra work of the value of $-, leaving due the plaintiffs on the original contract and for the extra work the sum of fifteen hundred dollars, for which they ask á judgment.

The appellants file an answer and counter-claim to the petition, denying the completion of the work by the appellees, its acceptance by them, and claiming-damages of the latter by reason of the delay in the work, the defective materials used, as well as the inferior manner of its execution; also damages by reason of having to employ others to complete the building. They deny the extra work, or that any writing was given authorizing it to be done.

The allegations of this counter-claim are denied by the reply.

The case was transferred by consent to the Louisvilie Chancery Court, and a judgment rendered in favor of the appellees, of which Escott & Son now complain.

The evidence in the case shows a failure on the part of the appellees to comply with their contract in not completing the building; or if, as insisted by the appellees, the building was completed, their own testimony shows that the work was [172]*172not executed in the manner required by the terms of the contract.

The chancellor, in his opinion rendered, allows the damages sustained by the failure of the appellees to comply by applying them as a set-off to the claim for extra work. Whether or not this is an equitable adjustment of the claims of these parties is not proper for this court to determine, as the case must go back for further preparation or a dismissal of appellees’ action.

It is conceded by counsel on each side, in argument, that the action is based upon the contract between the parties; and although it has found its way into a court of equity, it is only a common-law action, containing no allegation of fraud or mistake or prayer for rescission that would enable the chancellor to grant any other relief than as a common-law judge.

It is a well-recognized principle, and too well understood to be discussed, that where a party by the terms of the contract must perform a condition precedent before he is entitled to his money or the consideration for its performance, he can maintain no action on the contract without alleging in his petition, and establishing by proof, if denied, a full performance on his part. “The omission of the averment of performance of a condition precedent, or of an excuse for non-performance, is fatal on demurrer, or in case of judgment by default.” (1 Chitty’s Pleading, 327.)

By section 149 of the Civil Code it is provided that “ in pleading the performance of a condition precedent in a contract it shall not be necessary to state the facts showing such performance; but it may be stated generally that the party duly performed all the conditions on his part,” etc. The petition in this regard presents a good cause of action, but the evidence shows that this allegation of performance is untrue. The balance of the money due on the contract — that is, the twenty-five [173]*173per cent for which this action was instituted — was not to be paid until one month after the completion of the work or its acceptance by the architect, and it is immaterial whether the building was left by the appellees in an unfinished condition or was completed, but not in the manner required, as in either case no recovery can be had by the appellees in an action on the contract. The fact that the appellants took possession of the building can not be considered as an acceptance of the work. The building was owned by them and upon their premises, and they could not be required to abandon it altogether so as to enable them to maintain an action for damages. They had no alternative but to take possession as they did, protesting all the while that appellees had failed to comply with their agreement.

If the work has been done, but is defectively executed, the party performing it may recover on a quantum meruit, as has been often decided, and by this court in the cases of Morford v. Ambrose (3 J. J. Marsh.) and Morford v. Mastin (6 Mon.) Such a recovery is permitted by reason of the hardship resulting to the employee or laborer in withholding from him any compensation whatever for his work and labor when by reason of his failure to perform the stipulations of his contract he can maintain no action upon it; and while a recovery on a quantum meruit is permitted, the amount claimed may be lessened by reason of the damages the employer has sustained by the breach of the covenant. It is true the condition precedent has not been complied with by the appellees, and that ordinarily a quantum meruit will not lie in such a case, still we are well satisfied under the facts here presented it may be maintained. If the work was yet incomplete, the appellees could have no remedy until they complied with their agreement; but by the express stipulations of the contract the appellants had the right through the architect to elnploy others to complete- the work in the event of a failure to do so. by the appellees. Other [174]*174parties were employed to finish the building, and did complete it, for which the appellants are now claiming damages on their counter-claim, as well as for the defective execution of the work by the appellees.

The latter can not now comply with the contract, as it has been performed or the work finished by some one else; and it would be a harsh as well as unjust rule that would deny the appellees any compensation whatever for their work and material when it is impossible for them to comply with the condition precedent in completing the work for the reason thát it has already been done by some one else. So the parties occupy the same position as if they had completed the building, but not in a workmanlike manner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wehr Constructors, Inc. v. Steel Fabricators, Inc.
769 S.W.2d 51 (Court of Appeals of Kentucky, 1988)
Cassinelli v. Stacy
38 S.W.2d 980 (Court of Appeals of Kentucky (pre-1976), 1931)
O'Bryan v. Mengel Company
6 S.W.2d 249 (Court of Appeals of Kentucky (pre-1976), 1928)
Anglin v. Simpson's Administrator
295 S.W. 868 (Court of Appeals of Kentucky (pre-1976), 1927)
Kentucky-Elkhorn Coal Corp. v. France
278 S.W. 578 (Court of Appeals of Kentucky (pre-1976), 1925)
Jackson Lumber Supply Company v. Deaton
272 S.W. 717 (Court of Appeals of Kentucky (pre-1976), 1925)
Vincennes Bridge Co. v. Walker
205 S.W. 778 (Court of Appeals of Kentucky, 1918)
Madison-Jackson-Estill Lumber & Development Co. v. Coyle
178 S.W. 1170 (Court of Appeals of Kentucky, 1915)
Pippy v. Winslow
125 P. 298 (Oregon Supreme Court, 1912)
Ludlow Lumber Co. v. Kuhling
83 S.W. 634 (Court of Appeals of Kentucky, 1904)
Hill v. Ragland
70 S.W. 634 (Court of Appeals of Kentucky, 1902)
Illinois Central R. R. v. Manion
67 S.W. 40 (Court of Appeals of Kentucky, 1902)
Fitzgerald v. Walsh
82 N.W. 717 (Wisconsin Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
73 Ky. 169, 10 Bush 169, 1873 Ky. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/escott-v-white-kyctapp-1873.