Vincennes Bridge Co. v. Walker

205 S.W. 778, 181 Ky. 651, 1918 Ky. LEXIS 597
CourtCourt of Appeals of Kentucky
DecidedOctober 18, 1918
StatusPublished
Cited by4 cases

This text of 205 S.W. 778 (Vincennes Bridge Co. v. Walker) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vincennes Bridge Co. v. Walker, 205 S.W. 778, 181 Ky. 651, 1918 Ky. LEXIS 597 (Ky. Ct. App. 1918).

Opinion

Opinion of the Court by

Judge Hurt

Affirming.

[652]*652The appellant, Vincennes Bridge Company, and the appellee, C. L. Walker, entered into a contract, which, was reduced to writing and signed by the parties, on the 7th day of October, 1909, whereby the appellant agreed to furnish all the materials and build, for the appellee, a steel footbridge, over a ravine, which separated Fulton street, in the city of Hickman from the property of Mrs. Jack Rogers, resting at the latter end on a small piece of, land owned by appellee. The bridge was to be two hun-i dred and eighty-five feet in length, and to be completed on or before the first day of December, 1909. As the consideration for the furnishing of the materials and construction of the bridge, the appellee agreed to pay the appellant, the sum of $1,575.00, in money, upon the completion and acceptance of the bridge. One undertaking in the contract was as follows: ‘ ‘ Said work shall be done in accordance with the plans and specifications hereunto attached, which are hereby made a part of this contract. ” The plans and specifications were made by an agent of the Bridge Company, who, also, made the contract with the appellee. This agent, before preparing the plans and specifications and entering into the contract, visited tho place, where the bridge was to be erected, and made such measurements, as he deemed necessary to the preparation of the plans and specifications, and the contract. The appellant did all toward the construction of the bridge, which it has ever done, on or before the, day designated in the contract for the completion of the bridge. While the construction of the bridge was going on, the appellee began to protest, that the bridge was not being constructed, in accordance with the contract, and declared his purpose not to accept or pay for the bridge, as it was being built, but, the agents of appellant, in charge of the work would assure him, that when it was completed,' it would be all right, and in accordance with the contract. When appellant had completed its work, the appellee refused to accept the bridge, as not having been erected according to the contract, and refused to pay for it.

On the third day of January, 1916, the appellant instituted this action against appellee for the contract prico of the bridge, with interest at 6% per annum, from the completion of the bridge, and alleged, that, it had furnished the materials and erected the bridge, under and id [653]*653accordance with the terms of the contract, which had been entered into between it and appellee, and that it had been accepted by appellee,-as having been bnilt in accordance with the contract. The appellee answered and denied, that the bridge had been constructed, in accordance with the requirements of the contract, or that he had ever accepted it, as having been so done. He, also, alleged, by way of counterclaim, that the structure was erected at the only place, where a bridge could be built over the ravine, so as to enable him to go from his property into the city of Hickman; that before making the . contract with appellant, he maintained a wooden bridge, at that point, and that appellant, in order to erect the bridge, in controversy, had torn down the wooden bridge, and that when he refused to accept the bridge erected by1 appellant or to pay for it, appellant agreed, that it had not constructed the bridge in accordance, with the contract, but promised to thereafter make same, in its construction and materials, conform to the contract, but had failed to do so; that the bridge, as erected, was unsafe and dangerous and worthless;'that he relied upon appellant’s promise to rebuild the bridge, so as to make it conform to the terms of the contract, and was thereby prevented from building another bridge, and that since that time, there has been an advance in materials, until such a bridge, as he had contracted for, would now cost him the sum of $2,500.00 and that he had been damaged on such accounts, in the sum of the difference, in the contract price and the present cost of such a bridge, which he pleaded as a counterclaim. The answer of appellee set out, specifically, the' instances wherein the bridge, as erected, was different from the bridge which the contract required the. appellant to erect for him. The allegations, upon which the counterclaim was based, were contraverted, by agreement upon the record.

At the conclusion of the evidence; each party, moved the court, for a directed verdict in its favor, but, these motions were overruled. The appellant then offered several instructions and moved the court to give them to the jury, but all were overruled, and the court then gave five instructions to the jury, all of which were objected to by both appellant and appellee.

The first instruction, in substance, advised the jury, that the appellant had contracted to furnish all the ma[654]*654terials and construct a steel footbridge for appellee, over a ravine between Pulton street and the property of Mrs. Rogers, 285 feet in length, and to complete same on or before December 1, 1909, “in accordance with the plans and specifications introduced as evidence in this case,” and for which the appellee was to pay appellant the sum of $1,575.00 upon its completion and acceptance, and if the jury believed from the evidence, that appellant did build and complete the bridge on or before - the date specified, “in accordance with said plans and specifications,” “or substantially, in accordance with said plans and specifications,” to find for appellant, the sum of $1,575.00, with interest at 6% per annum from December 1st, 1909.

The second instruction directed, that although the jury did not believe that the bridge was constructed as! set out in instruction No. 1,'yet, if it believed from the evidence that appellee accepted the bridge, to find for appellant the contract price for the bridge, as set out in instruction No. 1.

The third instruction directed, that if the jury, did not believe, from the evidence, that the appellant had constructed the bridge as set out in instruction No. 1, or that appellee accepted it as set out in instruction No. 2,' to find for the appellee.

The fourth instruction advised the jury, under what' circumstances it should find for appellee upon his counterclaim, and the fifth instruction was the converse of the fourth, but, as the verdict of the jury denied to appellee any recovery upon his counterclaim, it is unnecessary to any further consider the fourth and fifth instructions.'

The jury found for appellee, specifically stating in its verdict, that it did so, in accordance with the third instruction. The appellant’s motion for a new trial was overruled, and it has appealed, and its complaint of the instructions will be first considered.

The objection urged to the first instruction, and, if the instruction was applicable to the facts of the case, it is the only objection, which could be urged, is, that the court did not construe the contract and tell the jury, what the contract was, fully, but, inasmuch as it advised the jury, that the contract required the bridge to be built, “in accordance with the plans and specifications in evidence,” and if it was built substantially “in accordance' [655]*655with the plans and specifications,” to find for appellant, left the jury to judge of both the law and the facts. It is true, that there is nothing better settled, than that the construction of a contract, which is in writing, and the terms of which are not ambiguous nor inconsistent, is the province of the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Totten v. Stewart
286 S.W.2d 539 (Court of Appeals of Kentucky, 1955)
Cassinelli v. Stacy
38 S.W.2d 980 (Court of Appeals of Kentucky (pre-1976), 1931)
O'Bryan v. Mengel Company
6 S.W.2d 249 (Court of Appeals of Kentucky (pre-1976), 1928)
Clinton v. Hibbs'
259 S.W. 356 (Court of Appeals of Kentucky, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
205 S.W. 778, 181 Ky. 651, 1918 Ky. LEXIS 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vincennes-bridge-co-v-walker-kyctapp-1918.