Nance v. Patterson Building Co.

131 S.W. 484, 140 Ky. 564, 1910 Ky. LEXIS 322
Court of Appeals of Kentucky·Decided November 11, 1910·Published·Cited by 12 cases

Opinion

Opinion of the Court by

Judge O’Rear

Reversing.

Appellee contracted with appellant to build her a house on a lot in Dayton, Ky., owned by the former, and to sell the property to her completed for $2,800, $100 of which she paid in advance and the balance was to be paid in installments. The house was to be a duplicate of a certain house in Newport, ICy., named in the contract. The house was to be completed and possession delivered by the first of December, 1907. It was not completed until some time in January, 1908, and then some parts were not completed, especially certain concrete walks. Appellee tendered appellant the- property about January 8, 1908, but she declined to receive it, and demanded that her money be refunded. Appellee refused to refund the money, and sold the property for $2,850. Appellant then brought this suit against appellee to recover the money she had paid, and the difference between the contract price and the fair market value of the'property if the place had been built as provided in the contract. The suit was for the breach of contract, and for the damages named.

The result of the trial was a verdict for appellee.'

The evidence shows, without dispute, that the house was not completed by the date named in the contract; that the foundation of the house was different from the one taken as a pattern; that the arrangement of the openings, the doors and windows, was different also; that the cement construction in the cellar was deficient, faulty, and inferior to that of the pattern house; that the new house was not provided with suitable sewer or drainage pipes so -as to carry off the waste water, etc., from the bath room and sinks; that the new place had a vault built in the back yard near the house as a cess-pool which overflowed. The foul water found its way into the cellar and through the cellar, running a more or less constant stream through the cellar; that some of the concrete work in the cellar and a passage or tunnel to the street was cracked because of faulty material and workmanship; that a stair[566] way in tlie front hall was 5 1-2 inches narrower than in the Newport house. There were other particulars in which it was alleged by the plaintiff that the house was materially different, but upon these there was a conflict in the proof; also there was proof that the plaintiff had consented to those changes. But upon the uncontradicted evidence there is no doubt that the house was materially different from the one in Newport.' The circuit court should therefore have instructed'the jury to find for the plaintiff the sum of^'lOO and such sum in addition as represented the difference between the contract price and the market value of the property if the house had been completed as reouired by the contract, not less than $50 however. Appellee had sold the property for $50 more than the contract price. It will not be heard to say that it was not worth at least that much more than the contract price. When the property was not finished and tendered to the plaintiff as the contract provided, she was not hound to accept it. But, for the defendant’s breach of the contract, she was entitled to recover her money paid, and the value of her contract as indicated.

The court instructed the jury that if the house was built substantially 'as provided in the contract, that was a sufficient performance. Which is true. But the case did not authorize that instruction. It is shown by the evidence, as stated, without contradiction that it was not built substantially as provided in the contract. There, .were material and radical differences between the two houses. Although the pleadings make an issue, unless the evidence also tends to support each side of the issue, the instruction should be regulated by the evidence, as where the evidence is all on one side, there should be a peremptory instruction upon that issue in accordance with the evidence. It is true that appellee undertook to explain the defective conditions shown to exist by saying that the concrete was put down in frostv weather, and was thereby caused to crumble and crack. But that is not material. Appellant did not undertake to bear the consequences of misadventure in the work. Appellee undertook to build the house a duplicate of the other. If one mishap or another made it materially different, the loss, is appellee’s, not appellant’s. .As a matter of law, it is a substantial failure if the foundation óf a house cracks so as to leak, and crumble, immediately after its completion, whereas if it had been properly constructed it would have done neither. ,

[567] As defining the phrase “substantial compliance” the court told the jury:

“Substantial compliance and performance as used in instructions one and two permit only such omissions or deviations from the contract as are inadvertent or unintentional, are not due to bad faith, do not impair the structure as a whole, are remedial without doing material damages to other parts of the building in tearing down and reconstructing, and may without injustice be compensated for by deduction from the contract price.”

Free access — add to your briefcase to read the full text and ask questions with AI

Nance v. Patterson Building Co., 131 S.W. 484, 140 Ky. 564, 1910 Ky. LEXIS 322 (Ky. Ct. App. 1910).

131 S.W. 484 (Nance v. Patterson Building Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Raimer v. Stout
14 V.I. 568 (Supreme Court of The Virgin Islands, 1978)
Regalbuto v. Grant
473 S.W.2d 833 (Court of Appeals of Kentucky, 1971)
Alvey v. Kern
354 S.W.2d 516 (Court of Appeals of Kentucky, 1962)
Mitchell v. Carlson
313 P.2d 717 (Montana Supreme Court, 1957)
Newcomb v. Schaeffler
279 P.2d 409 (Supreme Court of Colorado, 1955)
Helm v. Speith
182 S.W.2d 635 (Court of Appeals of Kentucky (pre-1976), 1944)
United States Pipe & Foundry Co. v. City of Waco
100 S.W.2d 1099 (Court of Appeals of Texas, 1936)
White v. Mitchell
213 P. 10 (Washington Supreme Court, 1923)
Vincennes Bridge Co. v. Walker
205 S.W. 778 (Court of Appeals of Kentucky, 1918)
Giberson v. Fink
151 P. 398 (California Court of Appeal, 1915)
Union L. H. & P. Co. v. Young
142 S.W. 692 (Court of Appeals of Kentucky, 1912)