Giberson v. Fink

151 P. 398, 28 Cal. App. 25, 1915 Cal. App. LEXIS 329
CourtCalifornia Court of Appeal
DecidedJune 30, 1915
DocketCiv. No. 1326.
StatusPublished
Cited by11 cases

This text of 151 P. 398 (Giberson v. Fink) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Giberson v. Fink, 151 P. 398, 28 Cal. App. 25, 1915 Cal. App. LEXIS 329 (Cal. Ct. App. 1915).

Opinion

HART, J.

The plaintiff brought this action to recover the sum of one thousand dollars paid by her to the defendant on the purchase price of a dwelling house, erected by the defendant on a lot situated in East Sacramento. On the fifth day of February 1913, the plaintiff and the defendant entered into and executed a written contract, whereby the latter agreed to erect upon a lot owned by him a dwelling house or cottage, and to sell and convey the same to the plaintiff for the sum of two thousand two hundred, dollars, of which amount the plaintiff agreed to pay and did pay the defendant, upon the execution of said contract, the sum’ of one thousand dollars, the balance of the purchase price to be paid in monthly installments of seven dollars, payable on the fifteenth day of each month and until the purchase price was fully paid. Subsequently the parties made the following supplementary agreement:

"agreement.
"Sacramento, Calif., May 5th, 1913.
"Agreement made this day between W. B. Fink, party of the first part, and Mrs. Belle Giberson, party of the second part, wherein the party .of the first part does agree to sell lot No. 17 (seventeen) of the W. B. Fink subdivision, and to erect thereon a (5) five room cottage, as per plan made by A. W. Campbell, architect, 3405 J. Street, for the sum of $2,500.00 (two thousand five hundred dollars). This- is to include sidewalks in front and around the house, oiled street or roadway.
"Doors, windows, and all inside furnishings to be of redwood. Flooring and all studding to be of Oregon pine. *28 Hard wall plastering, sand finish, two coats of paint inside and outside.
“Low-down toilet, enamel bath tub and lavatory, sink for kitchen, and wash trays for back porch.
‘‘ Gas to be provided for in kitchen. Electric wiring only. The discharge and sewer to be provided for, either by a cesspool or carriage from premises where proper provision will be made. [Signed] W. B. Fink.
Mrs. Belle Giberson.”

The theory upon which the plaintiff claims the right to a recovery is that the defendant failed to perform the terms of the agreements, in this: 1. That he did not complete the construction of the house within a reasonable time; and, 2. That in the construction of the cottage he deviated in material particulars from the plans and specifications according to which the same was to be erected and completed. The complaint, by appropriate averments, charges the breach of the contract in the particulars thus generally referred to, and alleges furthermore that the plaintiff fully performed the obligations imposed upon her by said agreements.

The answer denied that the defendant violated the agreements in any particular, and alleged that he performed the same strictly in accordance with the terms thereof and that he completed the construction of the building on the twenty-seventh day of August, 1913, denied performance on the part of the plaintiff, and alleged that she breached those terms of the first agreement whereby she agreed to pay certain monthly installments on the balance of the purchase price of the cottage and interest on said amount. The defendant, however, asked for no affirmative relief, and was awarded none.

Upon the issues so framed the cause was tried by the court sitting without a jury. Stating it in a general way, the court found that the defendant completed the building within a reasonable time and in accordance with the plan, specifications, and the terms of the contracts, except that, in the construction of the cottage, he departed in certain particulars from the specifications set out in the supplementary agreement, dated May 5, 1913, in the making of which alterations the plaintiff, acquiesced; that the plaintiff failed to keep her part of the first agreement in the respects above-mentioned; and that previously to the completion of the building on August 27, 1913, she “had abandoned her said contract and had refused to be *29 further bound thereby.” The defendant was accordingly awarded judgment, from which the plaintiff prosecutes this appeal, and supports the same by a transcript of the record, as prescribed by section 953a of the Code of Civil Procedure.

The points urged for a reversal of the judgment are that the findings vital thereto derive no support from the evidence, and that the court erred in its rulings permitting and disallowing answers to certain questions propounded to the witnesses.

It will be observed that neither the original nor the supplementary agreement contains a provision as to the time within which the building should be completed after the execution of those instruments, and in the absence of such a provision in a building contract the rule is that the building shall be completed within a reasonable time; and what a “reasonable time” is in such cases is a proposition whose solution must necessarily depend upon all the conditions and circumstances under which the work of constructing the structure has been prosecuted.

The defendant entered upon the execution of the terms of the agreements on or about the first day of June, 1913. It appears that, near the middle of the month of July of that year, the plaintiff conceived that progress in completing the contract on the part of the defendant was not being prosecuted with proper diligence and haste, and thereupon, through her attorney, Mr. H. S. Derby, addressed a letter to the defendant, dated July 18, 1913, the same having been served on and delivered to the latter by a constable, on the twenty-second day of July, 1913, in which, after declaring that there had been unreasonable delay in the completion of the contract of May 5, 1913, directing attention to the absence therefrom of any special time for completing the same, and stating that the absence of a provision as to the time for completing said contract called for the construction of the cottage according to the adopted plan and specifications within a reasonable time, notified him that:

“Unless it [said contract] is so completed on or before the 20th day of August, 1913, I shall decline to be further bound thereunder, and shall demand that you repay to me the sum of one thousand dollars paid you by me on account thereof, with interest.”

*30 The building not having been completed on the twentieth day of Augjist, 1913, the date to which the defendant was limited by the plaintiff in said letter, the latter, on the twenty-first day of August of said year, caused to be served on the defendant on the twenty-second day of August, 1916, the following notice:

.“Sacramento Cal., August 21, 1913.
‘ ‘ To W. B. Fink, 38th and G streets; Sacramento, Cal.: Default having been made by you in the completion of work required under your contract to sell me lot No. 17 of the W. B. Fink subdivision, and to erect thereon a five-room cottage as per plan made by A. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bonadelle Construction Co. v. Hernandez
337 P.2d 85 (California Court of Appeal, 1959)
Campbell v. Jung
261 P.2d 549 (California Court of Appeal, 1953)
Brooks v. Fidelity Savings & Loan Ass'n
128 P.2d 711 (California Court of Appeal, 1942)
Weaver v. Grunbaum
87 P.2d 406 (California Court of Appeal, 1939)
Sim v. Weeks
45 P.2d 350 (California Court of Appeal, 1935)
REID v. COMMISSIONER
28 B.T.A. 1217 (Board of Tax Appeals, 1933)
Murphy v. Sheftel
9 P.2d 568 (California Court of Appeal, 1932)
Fuller v. Mann
6 P.2d 999 (California Court of Appeal, 1932)
Wray v. Young
210 P. 794 (Washington Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
151 P. 398, 28 Cal. App. 25, 1915 Cal. App. LEXIS 329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/giberson-v-fink-calctapp-1915.