Mitchell v. Carlson

313 P.2d 717, 132 Mont. 1, 1957 Mont. LEXIS 8
CourtMontana Supreme Court
DecidedJuly 9, 1957
Docket9430
StatusPublished
Cited by12 cases

This text of 313 P.2d 717 (Mitchell v. Carlson) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell v. Carlson, 313 P.2d 717, 132 Mont. 1, 1957 Mont. LEXIS 8 (Mo. 1957).

Opinion

MR. CHIEF JUSTICE HARRISON:

The plaintiffs in the lower court purchased a residence in July 1952 from A. F. Carlson, the defendant, for $11,000, entering into an oral agreement that they would pay $6,500 down, *3 balance to be paid when the house ivas completed and plaintiffs moved in. The plaintiffs however paid the balance before completion and moved into the house. The house was completed shortly thereafter with the exception of constructing the front steps and sidewalk, which work it was agreed would be done in the spring.

After plaintiffs had moved into the dwelling, complaint was made to defendant that a crack had developed in the bedroom and that nail heads and stripping over the seams in the sheet-rock in the living and dining room were visible; that the ceiling in this room had sagged in one place; that the plastic tile in the bathroom and kitchen commenced to curl and peel off the base, and some of the doors would not close properly; that the cupboard doors fit improperly and would not close; and that there were numerous other defects in the house.

Defendant contends that he offered to correct these defects immediately or in the spring, whichever was agreeable to plaintiffs, and he and Mr. Mitchell agreed that the work would be done in the spring. This, however, Mr. Mitchell could not recall at the time of the trial. Mrs. Mitchell denied any such agreement.

At the time the tile peeled in the bathroom, defendant went to Missoula and returned with sufficient tile to re-do the bathroom floor, but Mrs. Mitchell would not accept the tile because she contended that the agreement called for roll-type inlaid linoleum.

Although plaintiffs and defendant consulted in regard to correcting the defects, no agreement could be arrived at because the manner in which defendant wished to cure them was not suitable or satisfactory to plaintiff.

In March 1953, Louis M. Mitchell demanded $3,000 from defendant to compensate for the defects and poor material used in the home. This, defendant refused to pay and this action was instituted.

Plaintiffs, in their amended complaint, alleged that defendant “promised and agreed to furnish and construct a modern home, *4 complete in every detail, and to use first-class lumber and material throughout the dwelling” for the sum of $11,000, and that “immediately after moving into said dwelling,” they discovered, “from an examination thereof, that the house was constructed of cheap and inferior materials, and that all the carpenter work and finishing was poorly and inadequately done,” and that defendant refused to change, remodel or complete the dwelling in the manner agreed. Plaintiffs set forth a detailed list of the defects and omissions for which they brought this action. Plaintiffs then alleged that in order to make the dwelling conform to the specifications agreed upon, it would cost the plaintiffs at least $3,000, and in addition it would cost at least $250 to construct the front steps and sidewalk. Defendant demurred to this amended complaint both specially and generally, which demurrers were overruled.

Defendant in his answer admitted some of the defects and omissions complained of, and alleged that he had always been ready and willing to correct these defects and omissions, but had been prevented from so doing by the plaintiffs, and particularly by the plaintiff, Margaret C. Mitchell.

Upon the trial, plaintiffs testified to the defects and omissions complained of, admitted that defendant had offered to remedy those defects, but testified the manner in which he wished to remedy them did not conform to the specifications orally agreed upon and refused to allow him to do any further work upon the house. They also admitted that they had agreed ■to allow defendant to build a sidewalk and steps in the spring, but that after discovering the defects and omissions complained of in the complaint no longer felt him qualified to do the work.

To support plaintiffs’ testimony a former contractor, Leo Redding, a carpenter of some sixteen years experience, testified as to the defects and his estimate of the cost of repairing them. 'He enumerated the cost of repairs as to each specific item: allocating $1,200 to $1,500 for repairing the sheetrock; $200 for repairing the floors; $20 to replace two doors plus cost of installation; and $50 for new linoleum in kitchen and bath *5 room. He made no estimate as to the cost of repairing the cupboards, bathroom tub or building the sidewalk and steps. Two other persons testified as to the existence of the defects; one, Mr. Buchanan, an electrician and plumber, experienced in the building trades, testified the only way he knew of to correct the defects in the sheetrock was to tear it down and put it up new.

Defendant in his testimony contradicted plaintiffs’ and their witnesses’ testimony as to the method of repairing the defects and as to the cost of repair.

The jury returned a verdict in favor of the plaintiffs in the sum of $2,000, and judgment was entered thereon from which this appeal was taken.

The defendant alleges four specifications of error: (1) The court erred in giving plaintiffs’ proposed instruction No. 2, given as court’s instruction No. 4; (2) The judgment is contrary to the law and evidence; (3) The evidence was”insufficient to substantiate the verdict; and (4) Misconduct on the part of counsel for plaintiffs and the court. We shall consider them in this order.

The first specification of error is that the trial court erred in giving instruction No. 4, reading:

“You are instructed that if you find from a preponderance of the evidence in this action that plaintiffs are entitled to damages, then in arriving at the measure of damages, it is the amount which will compensate the plaintiffs for all detriment proximately caused thereby, or which, in the ordinary course of things, would be likely to result therefrom, or which has resulted therefrom.”

The defendant excepted to this instruction on the grounds it was too broad and would allow the jury to “compensate for damages not alleged or prayed for in the amended complaint. ’ ’ Defendant cites in support of his contention the following quotation from Montgomery v. Karavas, 45 N.M. 287, 114 Pac. (2d) 776, 781:

“Where the contractor fails to keep his agreement, the measure of the employer’s [owner’s] damages, whether sought in *6 an independent action or by recoupment or counterclaim, is always tbe sum which will put him in as good a position as if the contract had been performed. If the defect is remedial from a practical standpoint, recovery generally will be based on the market price of completing or correcting the performance, and this will generally be shown by the cost of getting work done or completed by another person. * * * 5 Williston on Contracts, Sec. 1362.”

While defendant may be correct in stating the above as the generally accepted measure of damages for breach of a construction contract, it does not necessarily follow that the one given is erroneous.

R.C.M. 1947, section 17-301, provides the following as the measure of damages for breach of contract:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul Companies v. Construction Management Co.
96 F. Supp. 2d 1094 (D. Montana, 2000)
Carroccia v. Todd
615 P.2d 225 (Montana Supreme Court, 1980)
Carter v. Quick
563 S.W.2d 461 (Supreme Court of Arkansas, 1978)
Prudential Federal Savings & Loan v. McDougall
567 P.2d 445 (Montana Supreme Court, 1977)
PRUDENTIAL FEDERAL v. McDOUGALL
Montana Supreme Court, 1977
Kirby v. Kenyon-Noble Lumber Co.
558 P.2d 452 (Montana Supreme Court, 1976)
Haggerty v. Selsco
534 P.2d 874 (Montana Supreme Court, 1975)
Maxted v. Stenberg
Montana Supreme Court, 1975
Vernali v. Centrella
266 A.2d 200 (Connecticut Superior Court, 1970)
Gosselin v. Better Homes, Inc.
256 A.2d 629 (Supreme Judicial Court of Maine, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
313 P.2d 717, 132 Mont. 1, 1957 Mont. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-carlson-mont-1957.