06/30/2026
DA 25-0438 Case Number: DA 25-0438
IN THE SUPREME COURT OF THE STATE OF MONTANA
2026 MT 141N
MARK LORENZ AND WADE LORENZ, individually and d/b/a LORENZ BROTHERS CONSTRUCTION,
Plaintiffs, Counterclaim Defendants, and Appellees,
v.
EDWARD C. WILLIAMS, JR.,
Defendant, Counterclaim Plaintiff, and Appellant.
APPEAL FROM: District Court of the First Judicial District, In and For the County of Lewis and Clark, Cause No. BDV-2016-54 Honorable Michael F. McMahon, Presiding Judge
COUNSEL OF RECORD:
For Appellant:
Robert Farris-Olsen, Morrison Sherwood Wilson & Deola, PLLP, Helena, Montana
For Appellees:
Craig D. Charlton, Smith Law Firm, P.C., Helena, Montana
Submitted on Briefs: May 27, 2026 Decided: June 30, 2026
Filed:
__________________________________________ Clerk Justice Katherine M. Bidegaray delivered the Opinion of the Court.
¶1 Pursuant to Section I, Paragraph 3(c), Montana Supreme Court Internal Operating
Rules, this case is decided by memorandum opinion and shall not be cited and does not
serve as precedent. Its case title, cause number, and disposition shall be included in this
Court’s quarterly list of noncitable cases published in the Pacific Reporter and Montana
Reports.
¶2 In 2008, Edward Williams purchased real property located at 4595 York Road in
Helena, Montana. In August 2012, Williams, a disabled veteran, sought to build an
ADA-compliant home on this property using his VA benefits. The District Court found
that, before this project, Mark Lorenz and Wade Lorenz of Lorenz Brothers Construction
had not served as general contractors for the construction of an entire home. After several
meetings and discussions regarding design and budget, the Lorenz Brothers prepared a
“Proposal and Contract for New Home,” which proposed a contract price of $155,420 and
a completion goal of four to five months, or in May 2013. The parties disputed whether
the proposal included a finished basement; the District Court credited the Lorenz Brothers’
testimony that the proposal accounted for an unfinished basement. Williams did not sign
the proposal.
¶3 On December 17, 2012, the Lorenz Brothers signed a $160,000 promissory note
with PT Management, LLC, a subsidiary of Power Townsend, at a 15% interest rate. The
same day, Williams signed a trust indenture and hypothecation agreement pledging the
York Road property as collateral for the note. Construction began in late December 2012.
2 The District Court found that Williams consented to the Lorenz Brothers’ presence on the
property, though Williams disputed that fact.
¶4 In January of 2013, the foundation, walls, and roof were installed. In mid-February
2013, the parties’ relationship broke down after a dispute over whether the basement would
be finished within the original budget. The Lorenz Brothers testified that they told
Williams the $155,420 bid accounted for an unfinished basement and that they could not
finish the basement for that price. The District Court further found that Williams ordered
the contractors off the property. When construction stopped, the home was approximately
30% to 40% complete, and more than $86,000 had already been drawn from the line of
credit.
¶5 After construction stopped, Williams and Opportunity Bank requested that Hal
Aasen of Montana Building Consultants inspect the home. Aasen identified twenty-six
violations of the 2006 International Residential Code (IRC). Engineer Derek Brown later
inspected the project. The District Court found that Brown testified the code violations
and structural issues could be corrected, that most corrections were simple or relatively
inexpensive, and that no reason existed to tear down the structure and start over. Wade
Lorenz testified that the Lorenz Brothers would correct the violations, including repouring
the patio, without additional charge or change orders.
¶6 Within a few days after Wade Lorenz returned to resume work and began correcting
the patio, Williams again called the sheriff. By early March 2013, the Lorenz Brothers had
been fully removed from the project. The line of credit came due on June 17, 2013, but
3 the Lorenz Brothers did not pay PT Management. On July 2, 2013, PT Management served
Williams with a construction lien for $86,726.44.
¶7 In January 2016, Power Townsend and PT Management sued the Lorenz Brothers
for failing to pay off the line of credit. On June 22, 2016, the Lorenz Brothers filed a
third-party complaint against Williams, alleging breach of construction contract, breach of
trust indenture contract, negligence, and unjust enrichment. The District Court dismissed
the counts for breach of trust indenture and negligence. Williams then answered and filed
counterclaims for intentional trespass, negligence, violation of the Montana Consumer
Protection Act (MCPA), and violation of the Truth in Lending Act. After an unsuccessful
settlement stay, the District Court lifted the stay on September 20, 2023, and set a new
scheduling order. On July 12, 2024, the District Court granted summary judgment to
Williams on the Lorenz Brothers’ remaining claims for breach of contract and unjust
enrichment. Williams voluntarily dismissed his Truth in Lending Act claim at trial, leaving
his trespass, MCPA, and negligence claims for decision after a bench trial that was held on
January 13, 2025.
¶8 On March 31, 2025, the District Court entered Findings of Fact, Conclusions of
Law, and Order. The court dismissed Williams’s trespass and MCPA claims, awarded him
$35,000 on his negligence claim for the patio-related repairs, and dismissed the remaining
negligence theories.
¶9 On appeal from a bench trial, this Court reviews the district court’s findings of fact
for clear error. Roland v. Davis, 2013 MT 148, ¶ 21, 370 Mont. 327, 302 P.3d 91. Clear
error exists when substantial evidence does not support the finding of fact, the district court
4 misapprehended the evidence, or this court has a definite and firm conviction that the
district court made a mistake. Roland, ¶ 21. We review conclusions of law for correctness.
Roland, ¶ 21. In a bench trial, the district court acts as the “exclusive judge” of witness
credibility. Section 26-1-302, MCA; State v. Sanchez, 2017 MT 192, ¶¶ 18-19, 388 Mont.
262, 399 P.3d 886. Mitigation findings are factual and reviewed for clear error.
McCormick v. Brevig, 2007 MT 195, ¶ 41, 338 Mont. 370, 170 P.3d 599.
Montana Consumer Protection Act
¶10 The MCPA provides a private cause of action and treble damages upon proof that
the consumer suffered “ascertainable loss of money or property” caused by the “use or
employment” of “unfair or deceptive acts or practices in the conduct of any trade or
commerce.” Sections 30-14-103, -133(1), MCA. This Court has held “as a matter of law
that an unfair act or practice is one which offends established public policy and
which is either immoral, unethical, oppressive, unscrupulous or substantially injurious to
consumers.” WLW Realty Partners, LLC v. Cont’l Partners VIII, LLC, 2015 MT 312, ¶ 31,
381 Mont. 333, 360 P.3d 1112; Rohrer v. Knudson, 2009 MT 35, ¶ 31, 349 Mont. 197,
203 P.3d 759.
¶11 Williams raises compelling MCPA arguments. He contends the $155,420 proposal
price was unrealistically low; the allowances were vague, “misleadingly low,” and
Free access — add to your briefcase to read the full text and ask questions with AI
06/30/2026
DA 25-0438 Case Number: DA 25-0438
IN THE SUPREME COURT OF THE STATE OF MONTANA
2026 MT 141N
MARK LORENZ AND WADE LORENZ, individually and d/b/a LORENZ BROTHERS CONSTRUCTION,
Plaintiffs, Counterclaim Defendants, and Appellees,
v.
EDWARD C. WILLIAMS, JR.,
Defendant, Counterclaim Plaintiff, and Appellant.
APPEAL FROM: District Court of the First Judicial District, In and For the County of Lewis and Clark, Cause No. BDV-2016-54 Honorable Michael F. McMahon, Presiding Judge
COUNSEL OF RECORD:
For Appellant:
Robert Farris-Olsen, Morrison Sherwood Wilson & Deola, PLLP, Helena, Montana
For Appellees:
Craig D. Charlton, Smith Law Firm, P.C., Helena, Montana
Submitted on Briefs: May 27, 2026 Decided: June 30, 2026
Filed:
__________________________________________ Clerk Justice Katherine M. Bidegaray delivered the Opinion of the Court.
¶1 Pursuant to Section I, Paragraph 3(c), Montana Supreme Court Internal Operating
Rules, this case is decided by memorandum opinion and shall not be cited and does not
serve as precedent. Its case title, cause number, and disposition shall be included in this
Court’s quarterly list of noncitable cases published in the Pacific Reporter and Montana
Reports.
¶2 In 2008, Edward Williams purchased real property located at 4595 York Road in
Helena, Montana. In August 2012, Williams, a disabled veteran, sought to build an
ADA-compliant home on this property using his VA benefits. The District Court found
that, before this project, Mark Lorenz and Wade Lorenz of Lorenz Brothers Construction
had not served as general contractors for the construction of an entire home. After several
meetings and discussions regarding design and budget, the Lorenz Brothers prepared a
“Proposal and Contract for New Home,” which proposed a contract price of $155,420 and
a completion goal of four to five months, or in May 2013. The parties disputed whether
the proposal included a finished basement; the District Court credited the Lorenz Brothers’
testimony that the proposal accounted for an unfinished basement. Williams did not sign
the proposal.
¶3 On December 17, 2012, the Lorenz Brothers signed a $160,000 promissory note
with PT Management, LLC, a subsidiary of Power Townsend, at a 15% interest rate. The
same day, Williams signed a trust indenture and hypothecation agreement pledging the
York Road property as collateral for the note. Construction began in late December 2012.
2 The District Court found that Williams consented to the Lorenz Brothers’ presence on the
property, though Williams disputed that fact.
¶4 In January of 2013, the foundation, walls, and roof were installed. In mid-February
2013, the parties’ relationship broke down after a dispute over whether the basement would
be finished within the original budget. The Lorenz Brothers testified that they told
Williams the $155,420 bid accounted for an unfinished basement and that they could not
finish the basement for that price. The District Court further found that Williams ordered
the contractors off the property. When construction stopped, the home was approximately
30% to 40% complete, and more than $86,000 had already been drawn from the line of
credit.
¶5 After construction stopped, Williams and Opportunity Bank requested that Hal
Aasen of Montana Building Consultants inspect the home. Aasen identified twenty-six
violations of the 2006 International Residential Code (IRC). Engineer Derek Brown later
inspected the project. The District Court found that Brown testified the code violations
and structural issues could be corrected, that most corrections were simple or relatively
inexpensive, and that no reason existed to tear down the structure and start over. Wade
Lorenz testified that the Lorenz Brothers would correct the violations, including repouring
the patio, without additional charge or change orders.
¶6 Within a few days after Wade Lorenz returned to resume work and began correcting
the patio, Williams again called the sheriff. By early March 2013, the Lorenz Brothers had
been fully removed from the project. The line of credit came due on June 17, 2013, but
3 the Lorenz Brothers did not pay PT Management. On July 2, 2013, PT Management served
Williams with a construction lien for $86,726.44.
¶7 In January 2016, Power Townsend and PT Management sued the Lorenz Brothers
for failing to pay off the line of credit. On June 22, 2016, the Lorenz Brothers filed a
third-party complaint against Williams, alleging breach of construction contract, breach of
trust indenture contract, negligence, and unjust enrichment. The District Court dismissed
the counts for breach of trust indenture and negligence. Williams then answered and filed
counterclaims for intentional trespass, negligence, violation of the Montana Consumer
Protection Act (MCPA), and violation of the Truth in Lending Act. After an unsuccessful
settlement stay, the District Court lifted the stay on September 20, 2023, and set a new
scheduling order. On July 12, 2024, the District Court granted summary judgment to
Williams on the Lorenz Brothers’ remaining claims for breach of contract and unjust
enrichment. Williams voluntarily dismissed his Truth in Lending Act claim at trial, leaving
his trespass, MCPA, and negligence claims for decision after a bench trial that was held on
January 13, 2025.
¶8 On March 31, 2025, the District Court entered Findings of Fact, Conclusions of
Law, and Order. The court dismissed Williams’s trespass and MCPA claims, awarded him
$35,000 on his negligence claim for the patio-related repairs, and dismissed the remaining
negligence theories.
¶9 On appeal from a bench trial, this Court reviews the district court’s findings of fact
for clear error. Roland v. Davis, 2013 MT 148, ¶ 21, 370 Mont. 327, 302 P.3d 91. Clear
error exists when substantial evidence does not support the finding of fact, the district court
4 misapprehended the evidence, or this court has a definite and firm conviction that the
district court made a mistake. Roland, ¶ 21. We review conclusions of law for correctness.
Roland, ¶ 21. In a bench trial, the district court acts as the “exclusive judge” of witness
credibility. Section 26-1-302, MCA; State v. Sanchez, 2017 MT 192, ¶¶ 18-19, 388 Mont.
262, 399 P.3d 886. Mitigation findings are factual and reviewed for clear error.
McCormick v. Brevig, 2007 MT 195, ¶ 41, 338 Mont. 370, 170 P.3d 599.
Montana Consumer Protection Act
¶10 The MCPA provides a private cause of action and treble damages upon proof that
the consumer suffered “ascertainable loss of money or property” caused by the “use or
employment” of “unfair or deceptive acts or practices in the conduct of any trade or
commerce.” Sections 30-14-103, -133(1), MCA. This Court has held “as a matter of law
that an unfair act or practice is one which offends established public policy and
which is either immoral, unethical, oppressive, unscrupulous or substantially injurious to
consumers.” WLW Realty Partners, LLC v. Cont’l Partners VIII, LLC, 2015 MT 312, ¶ 31,
381 Mont. 333, 360 P.3d 1112; Rohrer v. Knudson, 2009 MT 35, ¶ 31, 349 Mont. 197,
203 P.3d 759.
¶11 Williams raises compelling MCPA arguments. He contends the $155,420 proposal
price was unrealistically low; the allowances were vague, “misleadingly low,” and
insufficient to allow a consumer to understand what the proposal included; a four-to-five-
month completion timeline was unrealistic; and the project caused an objectively
measurable pecuniary loss. He relies on evidence that the home was only 30% to 40%
5 complete when the Lorenz Brothers left, that more than $86,000 had been drawn on the
line of credit, and that the project contained twenty-six IRC violations.
¶12 The District Court did not disregard the MCPA theory. It identified the challenged
proposal price, allowances, timeline, and description-of-material issues, but credited
contrary testimony from Mike Wall of Power Townsend and the Lorenz Brothers. Wall
testified that Power Townsend reviewed the bid, was comfortable with financing the
project based on the bid and the purchase of materials through Power Townsend and could
supply midrange and first-quality materials within the budget. The Lorenz Brothers
testified that no change orders or price increases had been given to Williams when
construction stopped and that the home could have been completed as contracted. The
court also found Mark Lorenz and Wade Lorenz credible and Williams not credible at
times.
¶13 A materially understated or misleading residential construction proposal may
support an MCPA claim on an appropriate record. We do not hold that vague allowances,
unrealistic pricing, or an unrealistic completion timeline can never constitute an unfair or
deceptive act or practice. We hold only that, on this record and under the applicable
standard of review, Williams has not shown that the District Court clearly erred in its
factual findings or incorrectly concluded that he failed to prove an unfair or deceptive act
or practice causing financial detriment. We therefore affirm the District Court’s dismissal
of the MCPA claim.
6 Negligence and Mitigation
¶14 Contractors owe a common law duty to construct a house in a good and
workmanlike manner. Mitchell v. Carlson, 132 Mont. 1, 20, 313 P.2d 717, 721-22 (1957);
Carroccia v. Todd, 189 Mont. 172, 176, 615 P.2d 225, 227 (1980). The party asserting
failure to mitigate bears the burden of proof. A. T. Klemens & Sons v. Reber Plumbing &
Heating Co., 139 Mont. 115, 125, 360 P.2d 1005, 1010 (1961). The duty to mitigate
requires an injured party to do what an ordinarily prudent person would do under the
circumstances, but it does not require unreasonable or impracticable action. McPherson v.
Kerr, 195 Mont. 454, 459-60, 636 P.2d 852, 855-56 (1981).
¶15 Williams argues that the Lorenz Brothers were negligent as a matter of fact and law
because the partially completed home contained twenty-six IRC code violations, including
defects involving the foundation, slab, framing, roofing, deck, patio, waterproofing, and
ADA-related access (failing to provide the level flooring required for ADA compliance
and using inferior materials like MDF trim instead of the specified pine). He further argues
that the District Court effectively excused unworkmanlike construction because the defects
were correctable. Williams also contends he did not fail to mitigate because he could not
afford to hire another contractor and because it was unreasonable to require him to allow
the same contractors to cure the defects they created.
¶16 Correctability does not erase defective work. We therefore do not affirm on the
ground that code violations cease to matter because they can be corrected. Instead,
assuming without deciding that the twenty-six IRC violations established defective work
at the time of inspection, substantial credible evidence supports the District Court’s
7 narrower causation, damages, and mitigation findings. Brown testified that the code
violations and structural issues could be corrected and that no reason existed to tear down
the structure. Wade Lorenz testified that the Lorenz Brothers would correct the violations,
including repouring the patio, without additional charge. The District Court credited that
testimony and found that Williams prevented the Lorenz Brothers from completing the
recommended remedies.
¶17 Williams relies on McPherson, 195 Mont. at 459-60, 636 P.2d at 855-56, to justify
his inaction, specifically the principle that the duty to mitigate “does not run to a person
financially unable to make such expenditures.” He argues that because his sole form of
income was VA disability and he lives on a fixed income that he could not afford a
replacement contractor and therefore did not breach his duty to mitigate.
¶18 However, Williams’s reliance on McPherson does not require reversal. McPherson
protects an injured party from being required to make unreasonable or impracticable
expenditures, including expenditures the party is financially unable to make. McPherson,
195 Mont. at 459-60, 636 P.2d at 855-56. It does not provide a shield for unreasonable
inaction when an available corrective option is offered at no cost. Here, the District Court
found that Williams refused an available no-cost corrective option and then did nothing to
protect the structure or materials from weather and deterioration for more than a decade.
Those findings distinguish McPherson and support the District Court’s mitigation ruling.
¶19 Williams’s distrust of the Lorenz Brothers is understandable given the number and
nature of the alleged defects. A homeowner is not invariably required to allow the same
contractor to return to a project regardless of the circumstances. But the question here is
8 not what this Court would have found in the first instance. The District Court heard the
witnesses, credited Brown and the Lorenz Brothers, found that the defects were correctable,
found that the Lorenz Brothers would correct them without additional charge, and found
that Williams’s refusal and later inaction caused or increased the non-patio damages he
seeks. On this record, those findings are not clearly erroneous.
¶20 Consequently, the District Court did not err by limiting Williams’s negligence
recovery to the $35,000 patio award and dismissing the remaining negligence theories
based on failure of proof, causation, and mitigation.
Cross-Appeal
¶21 Williams argues that, because the Lorenz Brothers did not file a timely cross-appeal,
they may not challenge the District Court’s finding that the partially completed home had
twenty-six IRC violations or seek reduction of the $35,000 patio award.
¶22 Williams is correct in part. Without a cross-appeal, the Lorenz Brothers may not
obtain affirmative relief reducing or eliminating the $35,000 patio judgment. Bucy v.
Edward Jones & Co., 2019 MT 173, ¶ 23, 396 Mont. 408, 445 P.3d 812. They may,
however, defend the judgment on any ground supported by the record. We therefore
consider their arguments only insofar as they support affirmance and do not reduce the
patio award.
¶23 Because the District Court did not clearly err or misapply the MCPA when it
concluded that Williams failed to prove an unfair or deceptive act or practice causing
financial detriment, and because substantial credible evidence supports the District Court’s
causation, damages, and mitigation findings on Williams’s negligence claim, we affirm.
9 ¶24 We have determined to decide this case pursuant to Section I, Paragraph 3(c) of our
Internal Operating Rules, which provides for memorandum opinions. This appeal presents
no constitutional issues, no issues of first impression, and does not establish new precedent
or modify existing precedent.
/S/ KATHERINE M. BIDEGARAY
We Concur:
/S/ CORY J. SWANSON /S/ BETH BAKER /S/ INGRID GUSTAFSON /S/ JIM RICE