Leeds v. Little, 44 N.W. 309, 42 Minn. 414, 1890 Minn. LEXIS 50 (Mich. 1890).

Opinion

Mitchell, J.

Defendant Little, being the owner of the land described in the complaint, in August, 1887, entered into a contract with defendant Stalbird for the erection of a dwelling-house on the premises. Stalbird then entered into a contract in writing (Exhibit B) with plaintiffs, by which the latter agreed “to furnish and lay the tile on the house according to the plans and specifications by L. S. Buffington, using shingle tile for the sides, and Spanish tile for roof; also finials and crestings for ridges; for the sum of $2,100. Terms, spot cash on completion of job.” The plaintiffs, claiming to have performed their contract, and not having received their pay from Stalbird, in September, 1888, filed their affidavit and statement for a lien, to which was annexed a copy of the written contract between them and Stalbird. To an action to enforce this lien Little interposed two defences:' First, that plaintiffs had not filed a properly itemized account of the labor and material, as required by Gen. St. 1878, c. 90, § 6; and, second, that they had. not fulfilled their contract.

[416]*416The objection to the statement for a lien is that it does not give the items of the labor and material, or their value, but is a mere statement in gross, the same as in the contract with Stalbird. This point is virtually disposed of by King v. Smith, supra, p. 286. Plaintiffs’ contract being for a gross sum for the whole job, no more detailed statement was necessary or practicable. Had the claim for a lien been by a contract, or against the owner, no other form of statement would have been either proper or possible, and yet the requirements of section 7 as to statements for a lien under section 1 are the same as those of section 6 for a lien under section 2, c. 90. This statute, in giving a material-man, laborer, or subcontractor a lien for the value or contract price of his material or labor, proceeds upon the idea that the owner, by making a contract with another for the erection, etc., of a building on his land, in view of the provisions of the existing lien law, makes him his quasi agent, with authority to charge the land for labor or material for all legitimate purposes of its performance; and this authority extends to the prices, as well as the quantity or quality, of the labor or material; and the amount of the claim secured by the lien will be commensurate with the contract price, if one is agreed on, between the contractor and subcontractor, if the contract be an honest and fair one. It is not, of course, conclusive upon the owner, who may show that it is so exorbitant and unreasonable as to indicate fraud, mistake, or the like; but prima facie, at least, it is the measure of the amount of the lien.

2. A careful inspection of the answer satisfies us that the second defence tenders no issue as to the quality of plaintiffs’ work, but merely charges a failure on their part to complete the roof within the time agreed, (alleged to have been November 1, 1887,) by reason of which certain damages resulted to defendant. The eourt finds that no time was agreed on when the .work should be completed, in which case, of course, the law implies a reasonable time. The court further finds that the plaintiffs entered upon the performance of their contract October 15, 1887, and prosequted work thereunder and thereon until June 16, 1888, at which time they had fully corfipleted it. In the absence of the evidence on the question, and of any find[417]*417ing that this was an unreasonable time, we must construe the finding of the court as adverse to the defendant on the issue as to the time of performance.

This would be decisive of the case in favor of the plaintiffs; but if it be assumed that the parties, voluntarily and outside of the pleadings, tried issues as to the quality of the work, the same result is reached. The only provision in the specifications referred to in Exhibit B, as to the manner of laying the tile, is that they shall be “all laid in proper manner.” The only objection made to the manner of laying the tile' on the roof is that they were not laid in cement. The, finding of the court is to the effect that, at the time this contract waffmade and this work done, cement had never been used in this locality in laying tile, but they had been uniformly laid on felt, without-cement, although tile laid in cement make a better roof than when-laid without it. While this, like many of the findings, is rather a. summary of the evidence than a finding on an issuable fact, yet, as-contracts are presumed to be made with reference to the general customs and usages of trade and business, it must be construed as equivalent to a finding that the roof tile was laid in a proper manner. To the suggestion that the specifications provide that the work was to be done to the satisfaction of the architect and the owner, and that the defendant objected to the tile being laid without cement, it is enough to say that, even conceding that, this would give the own’erthe right to exact’ a method of doing the work different from that expressed or implied by the contract, no such thing is pleaded, or even suggested, in the answer. Lautenschlager v. Hunter, 22 Minn. 267. This disposes of the objection to the roof.

As to the tile on the sides of the house, the court finds that they were improperly laid on, without being fastened-properly, so that some of them fell off; but that there was no evidence tending to prove what it would cost to take off and repláce them in a proper manner, or in any way fixing the amount of damage sustained by reason of these tile not having been properly put on. Defendant’s contention is that, plaintiffs’ "contract being an entirety, they to be paid a gross sum on completion of the job, they cannot recover on the contract until it has been fully performed in all respects; that, [418]*418at most, they can only recover for the reasonable value of the labor and material furnished and performed; and that, in the absence of any evidence showing how much it would cost to remedy the defect referred to, there is nothing to show how much, if anything, the plaintiffs are entitled to recover; that the burden of showing how much it would cost to remedy the defect was on them, and not on defendant.

The question what, if anything, a contractor, who has in some respect failed to completely perform his contract according to all its provisions, may recover, and whether upon the contract or on a quantum meruit, is one of some difficulty, and which has given rise to some diversity of judicial decision, especially in the case of building contracts, or others where the party has expended labor and material upon the land of another which cannot be returned to him, but which the owner of the land must necessarily retain and have the benefit of. In some states, such as Massachusetts and New Hampshire, the courts have adopted what is sometimes called the modern equitable rule, that the party who has the possession and enjoyment of the labor and materials of another must make compensation for what, he has received, after full allowance has been made to him for any damage he may have sustained by the non-performance of the contract in its entirety. Hayward v. Leonard, 7 Pick. 181; Smith v. First Cong., etc., 8 Pick. 178; Cullen v. Sears, 112 Mass. 299, 308; Britton v. Turner, 6 N. H. 481.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enviro-Fab, Inc. v. Blandin Paper Co.
349 N.W.2d 842 (Court of Appeals of Minnesota, 1984)
Freeman Contracting Company v. Lefferdink
419 S.W.2d 266 (Missouri Court of Appeals, 1967)
Minnesota Home Rebuilding & Repair Co. v. Kraulik
67 N.W.2d 673 (Supreme Court of Minnesota, 1954)
Sward v. Nash
40 N.W.2d 828 (Supreme Court of Minnesota, 1950)
Mathis v. Holland Furnace Co.
166 P.2d 518 (Utah Supreme Court, 1946)
Knutson v. Lasher
18 N.W.2d 688 (Supreme Court of Minnesota, 1945)
Service & Security, Inc. v. St. Paul Federal Savings & Loan Ass'n
300 N.W. 811 (Supreme Court of Minnesota, 1941)
Fargo Glass & Paint Co. v. Smith
266 N.W. 100 (North Dakota Supreme Court, 1936)
Parker v. Tilghman v. Morgan, Inc.
183 A. 224 (Court of Appeals of Maryland, 1936)
Scott v. Crawford
9 Ohio Law. Abs. 146 (Ohio Court of Appeals, 1930)
Harrild v. Spokane School District
192 P. 1 (Washington Supreme Court, 1920)
Sampson v. Brince
177 N.W. 933 (Supreme Court of Minnesota, 1920)
Middelstadt v. Kostendick
175 N.W. 553 (Supreme Court of Minnesota, 1919)
McClure v. Village of Browns Valley
173 N.W. 672 (Supreme Court of Minnesota, 1919)
Snider v. Peters Home Building Co.
167 N.W. 108 (Supreme Court of Minnesota, 1918)
Morris v. Hokosona
26 Colo. App. 251 (Colorado Court of Appeals, 1914)
Orr v. Sutton
148 N.W. 1066 (Supreme Court of Minnesota, 1914)
Northwestern Lumber & Wrecking Co. v. Parker
145 N.W. 964 (Supreme Court of Minnesota, 1914)
Blakely v. J. Neils Lumber Co.
141 N.W. 179 (Supreme Court of Minnesota, 1913)
Lindquist v. Young
138 N.W. 28 (Supreme Court of Minnesota, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
44 N.W. 309, 42 Minn. 414, 1890 Minn. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leeds-v-little-minn-1890.