Regalbuto v. Grant

473 S.W.2d 833, 1971 Ky. LEXIS 170
CourtCourt of Appeals of Kentucky
DecidedDecember 3, 1971
StatusPublished
Cited by2 cases

This text of 473 S.W.2d 833 (Regalbuto v. Grant) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regalbuto v. Grant, 473 S.W.2d 833, 1971 Ky. LEXIS 170 (Ky. Ct. App. 1971).

Opinion

DAVIS, Commissioner.

The appellee, Floyd H. Grant, Jr., sued the appellants, Constantino J. Regalbuto and Gina B. Regalbuto, his wife, asserting that they owed him a balance of $2,189.85 on a contract under which he had built a residence for them. For convenience we shall refer to appellee Grant as the builder and the Regalbutos as the owners.

The owners asserted a counterclaim against the builder, based on their claims of numerous defects in the building. The prayer of their counterclaim was for return to them of $25,794.06 already paid by them to the builder, plus an adjudication that the building contract was void by reason of nonperformance by the builder or, alternatively, recovery of $32,092.27 for breach of contract and $10,000 by way of punitive damages. There was a trial before a jury, resulting in a verdict for the builder of $1600. This verdict represents [836]*836a deduction of the builder’s claim from $2,-189.85, reflecting that the jury had considered the owners entitled to recovery of only $589.85 on their counterclaim. The owners have appealed and in voluminous briefs have asserted thirteen assignments of error. No useful purpose will be served by cataloging them at this point.

Basically, the evidence showed that the builder and owners entered into a written contract dated August 31, 1967, by the terms of which the builder agreed to build and the owners agreed to buy from him a residence which the parties had already agreed upon, for a total consideration of $30,508. In the caption of the agreement the owners were designated by their respective names, and the builder was described as “Floyd Grant Construction, a company duly organized and existing under and by virtue of the laws of the State of Kentucky, hereinafter called contractor.” The evidence showed that there is no such corporation as Floyd Grant Construction. Grant testified that he did business under that name but not as a corporate entity. A review of the record discloses that the parties never envisioned that Floyd Grant Construction was a corporation. It follows that the court did not err in permitting the litigation to proceed in behalf of Floyd H. Grant, Jr., as an individual. There is no merit in the eleventh assignment of error which raises this question.

After the contract was signed on August 31, 1967, work was commenced on the project sometime in September of 1967, and a few weeks later Constantino J. Regalbuto moved into the admittedly unfinished residence, using a cot and doing interior painting. It was not until January of 1968 that both Mr. and Mrs. Regalbuto moved into the premises. At that time the air-conditioning unit had not been installed. There then remained due to the builder, according to his computations, the sum of $5,-058, a portion of which represented the amount to be paid for the yet uninstalled air-conditioning unit. Mrs. Regalbuto told the builder that she was in no hurry for the air conditioner since there would be no need for it at that time of the year, and expressed the view that she might decide not to have the unit installed and claim a credit for it. The builder testified that he was at all times ready and willing to cause the installation of the air conditioner but that it could not be installed until the owners had completed a patio upon which the condenser was to rest. In any event, the air-conditioning unit was ultimately installed after the patio had been completed. The owners paid for it and were given credit by the builder for the amount paid.

Shortly after the owners moved into the residence, the builder sought to collect from them the balance due on the contract. The owners contended that there were numerous defects which must be remedied before they would pay. In February 1968, the builder had a conference with the owners and there was prepared by them a check list, or punch list, containing nineteen items which the owners then deemed requiring attention by the builder. The builder attended to these claims, most of which were relatively insignificant. Nevertheless, the owners continued to refuse to remit any balance to the builder. In April 1968, the builder, in company with a representative of Scholz Homes, the company which furnished the prefabricated components for the residence, again consulted with the owners, at which time another punch list of twenty-one items was submitted. The evidence for the builder was to the effect that he had adequately provided for each and every defect on each of those lists which required any attention on his part. On neither of the two punch lists was there any reference to any claimed defect in the plumbing or septic-tank disposal system.

When the efforts at settlement broke down, the builder filed this suit on August 6, 1969.

The first claim of the owners is that the court erred in refusing to direct a verdict for them, since the evidence [837]*837showed conclusively that the builder had not substantially complied with his contract to build the house for them. In support of this contention the owners contend that the evidence is uncontradicted that:

“(a) The sanitary facilities, consisting of a septic tank and field bed, do not function and cannot be made to function in their location as placed by the contractor;
(b) The septic tank and field bed facilities are not even on the lot of the def endants-appellants;
(c) That there was not even tender of completion of the contract upon the date alleged in the original complaint which was 'during the month of February, 1968’;
(d) Appellee Grant to a substantial extent refused to supervise construction;
(e) In addition, there was substantial evidence of many other defects and deficiencies in the construction of the house which the contractor refused to remedy, many of which defects counsel for ap-pellee conceded in his closing argument.”

A review of the evidence discloses that there was substantial evidence in behalf of the builder that the sanitary facilities did perform without incident until at least August 1969, and that any imperfection in the performance was readily correctable and probably was not due to improper installation so much as to improper use and maintenance after installation. There was no definitive showing that the septic tank and field-bed facilities were not situated on the lot of the owners, but the builder stipulated in his evidence that he would arrange for an easement to be granted to the owners which would enable them to extend their field-bed facilities onto the adjoining lot if that became necessary. After the judgment in this case, and on motion of the owners, an amended judgment was entered implementing that agreement, so that any complaint of the alleged mislocation of the facilities appears moot. The other matters concerning the completion of the contract, failure to supervise construction, and “many other defects and deficiencies in the construction” were fully developed in the evidence and completely considered by the jury. Jury issues were generated and the court properly denied the owners’ motion for a directed verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McFall v. Peace, Inc.
15 S.W.3d 724 (Kentucky Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
473 S.W.2d 833, 1971 Ky. LEXIS 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/regalbuto-v-grant-kyctapp-1971.