Taylor v. Dall Lead & Zinc Co.

111 N.W. 490, 131 Wis. 348, 1907 Wisc. LEXIS 214
CourtWisconsin Supreme Court
DecidedApril 9, 1907
StatusPublished
Cited by10 cases

This text of 111 N.W. 490 (Taylor v. Dall Lead & Zinc Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor v. Dall Lead & Zinc Co., 111 N.W. 490, 131 Wis. 348, 1907 Wisc. LEXIS 214 (Wis. 1907).

Opinion

Dodge, J.

The trial court, as indicated by an opinion filed, found three reasons why the plaintiffs could not maintain a lien against the defendant’s property, although the lumber had been furnished by them as-subcontractors of a principal contractor and in exact accordance with the principal contract. Of these reasons in their order:

1. The trial court, in substance, held that, because the principal contractor did not complete its contract by the construction of buildings and appliances satisfying its guaranty of efficiency, it could itself have maintained no lien; certainly not for any amount in excess of that which had been paid it, which was all that was payable by the terms of the contract until the efficacy of the plant could be tested; and that, since no lien could be maintained by the principal contractor at the time plaintiffs commenced their action, they could have none. Our statute on the subject of subcontractors’ liens, sec. 3315, Stats. (1898), provides substantially as follows: Every person who, as subcontractor of a principal contractor, furnishes any materials to such principal contractor for or in or about the erection, construction, etc., of any building or appurtenances thereto, may have the lien and remedy given by this chapter. Now, it is undisputed that the plaintiffs did exactly those things. They did, as subcontractors, furnish material to the principal contractor for the erection of a building and appurtenances, and such niaterials were wrought into a building and appurtenances now standing on the defendant’s land.

The query at once becomes pertinent why any court can ignore the behest of the statute that the plaintiffs have a lien. Prior to 1889- the statute itself gave one reason whenever the enforcement of a lien would compel the owner to pay more than his original contract required; but that obstacle is now removed. The trial court advances as a reason the fact that [352]*352tbe principal contractor could not itself have maintained a lien; but tbe statute makes no snob exception. That sncb fact is not universally an obstacle to tbe subcontractor’s right is,, of course, clear, for tbe principal contractor could maintain no action for a lien if it bad been paid all tbat it was entitled to, whether such payment were tbe full contract price or were-some less sum to which tbe principal contractor’s right might be reduced because of some right of deduction, setoff, or counterclaim existing in tbe owner’s favor. Tbe trial court seems to have found authority for an exception to tbe generality of tbe language of the statute in Goodman v. Baerlocher, 88 Wis. 287, 60 N. W. 415, where it was apparently-held that no lien against tbe land could exist for materials furnished: for the erection of a building, unless that building; was in fact so completed as .to come into physical existence. Whether even this doctrine could be extended, as in the present case, to deny the lien where the building came into exact and complete existence according to its specifications, but merely failed to satisfy an ancillary guaranty of complete effectiveness for a given purpose, may well be questioned, for the latter situation would go only to the liability of the owner to pay anything, or anything more than he had paid, which would seem to he deprived of any efficacy to defeat subcontractors’ liens by the amendment to our lien statutes already mentioned, brought in by ch. 333, Laws of 1889. The principle rested on in the Baerlocher Case, which may be called the-Pennsylvania doctrine, even if applicable to the present situation, was simply that, no building coming into physical existence, there never had been any physical substance upon, which the mechanic’s lien could fasten. This doctrine was, however, carefully considered by this court in Halsey v. Waukesha Springs S. Co. 125 Wis. 311, 104 N. W. 94, and entirely repudiated as inconsistent with both the language and the policy of our own statutes, which give a lien on the land upon the furnishing of the materials, provided the work of [353]*353erection of tbe structure is in fact commenced; sucli view Laving tbe support of Rees v. Ludington, 13 Wis. 276; Jessup v. Stone, 13 Wis. 466; and Fitzgerald v. Walsh, 107 Wis. 92, 82 N. W. 717. We are informed by counsel that tbe Waukesha Case was not called to tbe attention of tbe trial court. Had it been, we cannot think be would bave based any conclusion upon tbe doctrine that tbe mere failure of the principal contractor to complete tbe contracted building in exact compliance with tbe terms of tbe contract was an insuperable obstacle to tbe existence of a subcontractor’s lien.

Another ground of escape from the direct words of tbe statute conferring tbe lien, as stated by tbe trial court and urged by tbe respondent, is a rule declared or suggested in several cases, that 'the right of tbe subcontractor is referable to tbe original contract, and that what would not be “lienable” in favor of tbe principal contractor under bis contract is not lienable in favor of a subcontractor. This rule is in apparent derogation of tbe express words of the statute and therefore is to be very cautiously applied. In Goodman v. Baerlocher, supra, it was said, arguendo:

“If tbe case is such that tbe principal contractor is not entitled to a lien for any other reason than that be has been paid in full, as in case of abandonment of bis contract or of destruction of tbe building before completion, tbe subcontractors under him, and their materialmen and laborers, would not seem to be entitled to any lien.”

This language has already been criticised, if not repudiated, in Seeman v. Biemann, 108 Wis. 365, 84 N. W. 490, and properly so, for tbe statute does not limit the right of tbe subcontractor to cases where tbe principal contractor could bave a lien, and did not do so even when it contained tbe express limitation protecting tbe owner against payment of more iban tbe contract price.

Tbe two most important cases in which has been declared the dependency of the subcontractor’s lien upon the original [354]*354contract are Siebrecht v. Hogan, 99 Wis. 437, 75 N. W. 71, and Seeman v. Biemann, 108 Wis. 365, 84 N. W. 490, and they well illustrate the scope of that rule. In the first of these a lien was denied to a subcontractor for damages and additional expense caused by wrongful acts of the principal contractor and not called for by the contract. There the court, construing the words of the statute, said:

“Manifestly, such right of lien is confined to work, labor, and material required by the principal contract. To that extent, by force of the statute, the owner malees the principal contractor his agent to bind his property, but no further. . . . The whole theory of it is that the owner consents to what is required to carry out the principal contract, ánd makes his property liable therefor in accordance with the statute, which is made a part of the contract.”

The logic of this case is that labor or materials expended by a subcontractor by reason of the wrongful acts of the principal contractor, not within his original contract, are not performed by the plaintiff “as a subcontractor,” for he cannot be a subcontractor where there is no principal contract contemplating such service; hence he would not fall within the words of the statute conferring a lien merely for work done “as a subcontractor.”’

In Seaman v. Biemann

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cline-Hanson, Inc. v. Esselman
319 N.W.2d 829 (Wisconsin Supreme Court, 1982)
H. & M. HEATING CO. v. Andrae
150 N.W.2d 379 (Wisconsin Supreme Court, 1967)
McCormick v. Kuhnly
131 N.W.2d 840 (Wisconsin Supreme Court, 1965)
Usiak v. Kubiak
225 N.W. 168 (Wisconsin Supreme Court, 1929)
Fischer v. Meiroff
213 N.W. 283 (Wisconsin Supreme Court, 1927)
Rogers-Templeton Lumber Co. v. Welch
208 P. 600 (Montana Supreme Court, 1922)
W. H. Pipkorn Co. v. Tratnik
152 N.W. 141 (Wisconsin Supreme Court, 1915)
Kelleher v. Reedal
143 N.W. 193 (Wisconsin Supreme Court, 1913)
Francis & Nygren Foundry Co. v. King Knob Coal Co.
126 N.W. 39 (Wisconsin Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
111 N.W. 490, 131 Wis. 348, 1907 Wisc. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-v-dall-lead-zinc-co-wis-1907.