Rogers-Templeton Lumber Co. v. Welch

208 P. 600, 63 Mont. 287, 1922 Mont. LEXIS 117
CourtMontana Supreme Court
DecidedMay 8, 1922
DocketNo. 4,694
StatusPublished
Cited by1 cases

This text of 208 P. 600 (Rogers-Templeton Lumber Co. v. Welch) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rogers-Templeton Lumber Co. v. Welch, 208 P. 600, 63 Mont. 287, 1922 Mont. LEXIS 117 (Mo. 1922).

Opinion

MR. JUSTICE COOPER

delivered the opinion of the court.

Upon a former appeal this cause was remanded to the [1] district court with directions to correct its ruling in striking the lien from the record, and to make findings. (56 Mont. 321, 184 Pac. 838.) No new statement of the case is necessary. Upon the record as it stood upon the filing of the remittitur in the court below, the cause was submitted for decision. In response thereto it made findings of substantially the following facts: That on August 10, 1914, defendant Welch handed to plaintiff’s agent a list or estimate of lumber and other materials deemed necessary for the construction of a building to be used as a general store; that $1,600 was agreed upon as the price to be paid therefor, and cash, or payment within thirty days from the delivery of the last item thereof, as the terms, and, further, that extra materials ordered and delivered for the work should be “at the same rate, and subject to like discount o.r proportionate reduction”; that the materials comprehended in the estimate constitute “a separate and independent contract” the last item of which was delivered November 3, 1914, and went into the building; that on November 6 an account was stated between them; that “while said materials were being delivered” monthly statements of account were handed to Welch, and that all the materials furnished after November 6 were delivered under separate and distinct implied contracts, none of which was [289]*289paid for; that the lien was filed March 22, more than ninety days after the last item in the open account went into the building. The court also found that, pursuant to stipulation of the parties, Welch was indebted to plaintiff in the sum of $2192.38, the value of the materials sold and delivered between August 26, 1914, and January 16, 1915. As a conclusion of law, it denied the plaintiff a lien, but rendered judgment against the defendant Welch in the sum named.

The finding that the agreement upon the original estimate constituted "a separate and independent contract” embracing more than one account was erroneous, because it gave no effect to the contemporaneous agreement that such additional material as might be needed for the completion of the building were to be furnished at the same rate and upon the same terms. That understanding comprehended but one indivisible contract, one account, and the foundation for but one lien. The difficulty in anticipating the precise quantity of material required for a job of that character is clearly indicated by the disparity between the original estimate and the materials finally found to be needed to complete the work. Indeed, the entire indebtedness resulted from a contract to furnish articles for a single building, to be delivered from time to time as the work progressed and until the job was finished. The uncertain element entering into a transaction of this nature make it a case similar to one arising upon a contract where no definite time is fixed for the completion of the work, and where the account is to run until the last item required is furnished.

As is very well understood, a builder or owner of property is rarely able to anticipate the exact amount of material he may require for the erection of a building. Unless, therefore, there is room for a different conclusion, when it is found necessary, as the work advances, to order more materials, the items should all be deemed to have been ordered upon an account current, and the aggregate, when they have all been furnished, constitute the lien. (Helena S. H. & S. Co. v. Wells, [290]*29016 Mont. 65, 40 Pac. 78; Frankoviz v. Smith, 34 Minn. 403, 26 N. W. 225; Taylor v. Dall Zinc & Lead Co., 131 Wis. 348, 111 N. W. 490; David v. Doughty, 96 Kan. 556, 152 Pac. 660; Ballou v. Black, 17 Neb. 389, 23 N. W. 3.)

A substantial, rather than a technical, view should be taken [2,3] of the question whether the lien claim is founded upon one or more divisible contracts, or involves one or more accounts. (American Bridge Co. v. Honstain, 120 Minn. 329, 139 N. W. 619.) The lien statute is remedial in its nature, and to effectuate the purpose of its enactment, after the lien has once attached, it should be given a liberal construction. (Crane & Ordway Co. v. Baatz, 53 Mont. 438, 164 Pac. 533.)

The work was one continuous job, although materials were furnished at different times after the original estimate had been satisfied, and, although they may have been furnished under separate orders, each order was a related contract for some part- of the work and formed the basis for but one lien. A lien filed within ninety days preserves a lien for all the items, and all of them together furnished but one account. (Taylor v. Dall Zinc & Lead Co., supra; Northwestern Lumber Co. v. Parker, 125 Minn. 107, 145 N. W. 964.) In the latter case the court said: “This work was done under several little contracts, each for some small part of the work. One lien statement was filed covering all the contracts. The whole work was part of one general improvement, or one job, and was practically continuous in point of time.”

In finding No. 13 the court found that none of the items under date of December 26, 28, and 29, 1914, and January 4 and 16, 1915, were used in the construction of the building, and none “were sold and delivered on said dates.” For this finding there is no support in the evidence. After a careful reading of all of the evidence, we are satisfied that it was clear and convincing enough to sustain the opposite conclusion, and the court should have so found.

[291]*291In view of the unbroken continuity of the deliveries and the statements of the witnesses that all the materials for which the court gave judgment against Welch actually went into the building and became a component part of the permanent structure, it is clear that the controlling findings are at variance with the evidence and the inferences properly to be deduced therefrom. There is no circumstance discrediting the claim that the material was delivered and used in the building, and nothing to overcome the prima facie case of the plaintiff in that respect. The plaintiff is therefore entitled to a lien in the amount for which judgment was entered against Welch, less $183.03, the value of the nonlienable items.

In conclusion, we recommend a careful reading of the case of Taylor v. Dall Zinc & Lead Co., supra. A comparison of its facts with those in the present case will convince the most skeptical of the justness and the soundness of the conclusion reached above. In almost every particular the facts are similar to those found in the record before us. The only distinguishing feature we are able to discern is that in the Wisconsin case the parties had no contemporaneous understanding that any additional items needed after the filing of the original estimate should be supplied at the same price and upon the same terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Lumber Co. v. Rider
19 P.2d 644 (Montana Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
208 P. 600, 63 Mont. 287, 1922 Mont. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rogers-templeton-lumber-co-v-welch-mont-1922.