Dorestan v. Krieg

29 N.W. 576, 66 Wis. 604, 1886 Wisc. LEXIS 81
CourtWisconsin Supreme Court
DecidedOctober 12, 1886
StatusPublished
Cited by8 cases

This text of 29 N.W. 576 (Dorestan v. Krieg) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dorestan v. Krieg, 29 N.W. 576, 66 Wis. 604, 1886 Wisc. LEXIS 81 (Wis. 1886).

Opinion

Taylor, J.

The material questions arising on this appeal are (1) whether the plaintiffs, as subcontractors under Krieg, have a lien for the value of all the goods furnished to Krieg, the contractor, and which were used by him in the work done upon the defendant Gross's house, or whether [608]*608their lien is limited to the value of such articles only as were furnished to Krieg within thirty days next previous to serving their notice of claim of lien upon Gross. (2) Whether HeeM, as creditor of Krieg, having served his process of garnishment upon the defendant Gross before the plaintiffs served their notice of lien upon the said Gross, should be preferred to said plaintiffs for the amount found due to him from Krieg in such garnishee action, out of such sums of money as should be found due from Gross to Krieg at the time the garnishee action was commenced.

It would seem, from the statement of the law as made by the -learned county judge, that he wTas of the opinion that the plaintiffs should be preferred, notwithstanding their notice of lien was not served until after the garnishee proceedings were commenced by the service of the summons and notice of garnishment upon Gross. . Such finding did not, however, if erroneous, prejudice the respondent Keoht, if the other finding of the learned judge was correct, viz.: that the plaintiffs and appellants had a lien and claim against the defendant Gross, only for the value of the articles furnished to Krieg within thirty daj^s previous to the service of his'notice of claim for a lien; as the evidence shows that the value of-the goods so furnished was less than the difference between the claim of Keoht, as allowed by the court, and the sum of $190, which Gross had paid into court for the benefit of the plaintiffs and the defendants Keoht and Krieg'. We must therefore determine the two questions above stated.

Were the plaintiffs limited in the extent of their claims for a lien, as against Gross, to the value of the articles furnished to Krieg within thirty days next previous to the giving of his notice as required by the statute ? After a careful reading of the statute, we think this question should be answered in the negative. Sec. 3314, R. S., gives a lien to the original contractor upon the building and premises [609]*609which is to have preference to all other liens placed on the premises after the commencement of the work by the contractor, -without giving any notice whatsoever. Sec. 3315 provides that a subcontractor of. the original contractor, who “performs work or labor for, or furnishes any materials to, a principal contractor, in any of the cases mentioned in section 3314, shall be entitled to the lien and remedy given by this chapter, if within thirty clays after performing such work or labor, or furnishing such materials, he shall give notice in writing to the owner or his agent of the property to be affected by such lien, setting forth that he has been employed by such principal to furnish and has furnished such work, labor, or materials, with a statement of the labor or materials furnished, and the amount due therefor from such principal contractor, and that he claims the lien by this chapter; but the claim of such subcontractor shall not constitute such lien, except so far as such owner shall, at the time of giving such notice, be, or shall thereafter become, indebted to such principal contractor for work done or materials furnished under the principal contract.” Sec. 3316 declares that all claims for lien, and rights of action to recover therefor, under this chapter, shall be assignable. Sec. 3317 provides that the taking of a note, or other evidence of indebtedness, for any such work, labor, or materials done or furnished, shall not discharge the lien thereby given, etc.; and then sec. 3318 limits the time within which an action to enforce such lien must be commenced, and prescribes that no lien shall be enforced “ unless, within six months from the date of the last charge for performing such work and labor, or of the furnishing of such materials, a claim for such lien shall be filed, as hereafter provided, in the office of the clerk of the circuit court of the county in which 'the lands affected thereby lie, nor unless such action be brought within one year from such date.” Sec. 3319 provides how the lien shall be docketed, etc. Sec. 3320 pro-[610]*610Tides what the claim for lien, which is required to be hied, shall state in order to secure the benefits of the act; and this section also provides, among other things, that there shall be a statement in the claim of “ the' last date of the performance of labor or furnishing of materials.” The other sections of the act prescribe the maimer of foreclosing the liens when perfected as prescribed by the foregoing-sections.

Under the provisions of the chapter the original contractor has a lien by virtue of the fact that he perforins the work or furnishes the materials, and no notice to the owner or agent is required to create the lien. And this is reasonable, because the original contractor treats with the owner as agent, and such o vvner or agent has full knowledge of what has been done under such contract. The subcontractor does not deal with the owner or agent, and such owner or agent is not supposed to know of the dealings of the contractor with those he employs or deals with. Hence, in order to create a lien in favor of such subcontractor, it is necessary that he should give notice of his claim for a lien; and as some time must be fixed within which such notice must be given in order to create the lien in his favor, the statute irequires that such notice must be given within thirty days after the performance of such work or labor, or furnishing such materials.

When such notice has been given, the lien is created in favor of the subcontractor to the full extent that it is in favor of the original contractor, and to no greater extent; as he can only have a lien for the amount due, or to become due, to the original contractor, at or subsequent to the time the notice is served. All the subsequent sections of the act relate as fully to the lien of the • subcontractor as they do to the original contractor, and, unless he files his claim for a lien within the time prescribed by sec. 3318, and in the form prescribed by sec. 3320, he loses his lien notwithstand[611]*611ing he may have given notice as required by sec. 3315; and by sec. 3318 every person having a lien, whether as original contractor or subcontractor, and who has filed his claim as required by that section, shall lose it unless he commences an action to enforce it within one year from the date of the last charge for performing the work or for furnishing such materials. The original contractor loses his lien unless he files his claim for lien -within six months after the date of the last charge, etc., and so the subcontractor loses his lien, which he creates by giving the notice required by sec. 3315, unless he files his claim within six months after the date of his last charge, and commences his action within one year from the same date, and not from the date of his giving notice of his lien.

We see, therefore, no good reason for holding that he should be restricted as to the extent of his claim for a lien after he has given his notice, any more than the original contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mueller ex rel. Ahrens & Ott Manufacturing Co. v. Kroll
207 Ill. App. 306 (Appellate Court of Illinois, 1917)
People ex rel. Quisenberry v. Ellis
97 N.E. 697 (Illinois Supreme Court, 1912)
Taylor v. Dall Lead & Zinc Co.
111 N.W. 490 (Wisconsin Supreme Court, 1907)
Coleman v. Oregonian R. R.
35 P. 656 (Oregon Supreme Court, 1894)
Ryerson & Son v. Smith
51 Ill. App. 270 (Appellate Court of Illinois, 1893)
Hall v. Banks
48 N.W. 385 (Wisconsin Supreme Court, 1891)
McCorkle v. . Herrman
22 N.E. 948 (New York Court of Appeals, 1889)
Wilson v. Rudd
35 N.W. 321 (Wisconsin Supreme Court, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
29 N.W. 576, 66 Wis. 604, 1886 Wisc. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dorestan-v-krieg-wis-1886.