H. & M. HEATING CO. v. Andrae

150 N.W.2d 379, 35 Wis. 2d 1, 1967 Wisc. LEXIS 1177
CourtWisconsin Supreme Court
DecidedMay 9, 1967
StatusPublished
Cited by5 cases

This text of 150 N.W.2d 379 (H. & M. HEATING CO. v. Andrae) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. & M. HEATING CO. v. Andrae, 150 N.W.2d 379, 35 Wis. 2d 1, 1967 Wisc. LEXIS 1177 (Wis. 1967).

Opinion

Heffernan, J.

Duty of subcontractor to owner.

Under the Wisconsin statutes, 1 a subcontractor has a lien for his materials and labor directly on the property of the owner. He does not acquire that lien by subrogation to the lien rights of the general contract. Sec. 289.02 (5), Stats., 2 specifically provides that it shall be the duty of the contractor to protect and defend the owner against a lien claim of a subcontractor; and if he fails to successfully defend the owner, he is obliged to make the owner whole in the amount claimed. It is thus apparent that our statutory scheme recognizes the fact that the principal contractor is the agent of the owner, vis-a-vis, a subcontractor. The builder or principal contractor is thus automatically a party adverse to a lien-claiming subcontractor. The contractual obligation to pay the subcontractor is the responsibility of the contractor, but the owner’s property is the hostage for the payment.

*8 As a consequence, the owner can assert as defenses to a subcontractor’s claim any defenses that the principal contractor might have against the subcontractor, but he cannot assert defenses that he, the owner, might have only against the principal contractor.

Because the subcontractor’s lien is independently granted by statute and is not dependent on the general contractor’s lien:

“. . . the fact that the principal contractor has not complied with the conditions of his contract so as to enable him to enforce a lien on the building will not militate against the subcontractor enforcing such a lien if the subject of the subcontractor’s lien might in any event be lienable in favor of the principal contractor.” W. H. Pipkorn Co. v. Tratnik (1915), 161 Wis. 91, 95, 152 N. W. 141, 16 A. L. R. 975; Taylor v. Dall Lead & Zinc Co. (1907), 131 Wis. 348, 355, 111 N. W. 490.

In Seeman v. Biemann (1900), 108 Wis. 365, 379, 84 N. W. 490, this court noted:

“A subcontractor’s lien is not dependent under our statutes upon whether there is anything due the principal contractor. If in any event a claim would be lienable under the principal contract in favor of the contractor, it is lienable in favor of his subcontractor, and the right in that regard cannot be impaired by any default of the principal contractor.”

The Wisconsin court, over the years, has taken the position that the principal contractor is the owner’s agent for the purpose of securing materials and subcontracted services; hence, the defaults of the contractor are in no way chargeable to the subcontractor. We said in Pipkorn, supra, page 93:

“The principal contractor is the agent of the owner . . . The owner consents that the principal contractor may do what is necessary to carry out the principal con *9 tract and makes his property liable therefor in accordance with the statute, which becomes a part of the contract.”

The rule is well recognized that:

“. . . the failure of the principal contractor . . . does not of itself defeat the right of the subcontractor, workman, or materialman to a mechanic’s lien.” 57 C. J. S., Mechanics’ Liens, p. 616, sec. 112.

The same encyclopedia cites the Pipkorn Case, supra, for the rule:

. . that a subcontractor or materialman may be entitled to a lien even though, owing to the contractor’s default, the improvement is worthless.” 57 C. J. S., Mechanics’ Liens, p. 617, sec. 112; accord 36 Am. Jur., Mechanic’s Liens, p. 40, sec. 38.

2 Jones, Liens (3d ed.), p. 521, sec. 1304, points out that:

“Under statutes which give to subcontractors a direct lien, the amount for which the property may be charged is not limited by the amount that may be due from the owner to the contractor, nor does it in any way depend upon the state of the account between them. It is sufficient that the liens are created through the owner’s contract, from which his consent is implied.”

The salutary effect of these rules is to preserve the integrity of a subcontractor’s lien and prevent the security interest afforded therein from being eroded by claims against the general contractor accruing to the owner through no fault of the subcontractor. The subcontractor’s right to look to the owner’s property for security against the contractor’s failure to pay him should not be conditioned on the contractor’s faultless performance of the main contract. His only duty in the three-cornered contractual setup is to faithfully perform his own con *10 tract. The only defenses to an action for the foreclosure of his lien are the defenses available to the general contractor.

It is thus clear that Andrae, the owner, can assert the same defenses against the plaintiff, H. & M., that Wilde could, i.e., that it failed to perform its subcontract. However, Andrae cannot reduce the claim of H. & M. as the result of Wilde’s default in the principal contract with him as the owner. He can reduce the liability of the property to the subcontractor’s claim by the amount of damages attributable to any breach of the plaintiff’s contract with Wilde that he or Wilde can establish.

Thus the question before the trial court and this court on appeal is whether the subcontractor discharged his obligation to Wilde.

Did H. & M. perform its subcontract with Wilde?

The record abounds in evidence of Andrae’s dissatisfaction with his heating system; and though that dissatisfaction be justified, it does not necessarily follow that the infirmities or defects of the system were the result of any breach of H. & M.’s contract with Wilde. Rather, there is evidence of the satisfactory completion of the work contracted for. H. & M.’s vice-president, Harry L. Mushall, testified that H. & M. performed its contract exactly according to the contract specifications. Wilde himself testified that the system installed in the Andrae home was the one agreed upon in the contract as orally amended, that these amendments were specifically agreeable to Andrae, and that the installation was correct.

Mushall testified that the Hart & Crouse oil-fired boiler complied with the contract with Wilde and Andrae knew that the boiler would be a Hart & Crouse and specifically approved of it before installation.

*11 While the domestic coil failed to produce an adequate supply of hot water, it is undisputed that Andrae initiated the request for it in lieu of an ordinary water heater.

Much is made of the unusual and, perhaps, inefficient location of the boiler. In this case the boiler could not be placed next to the existing chimney because Andrae wanted additional room at that location so he could have the type of door that would permit him to bring his boat into the basement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waukesha Concrete Products Co. v. Capitol Indemnity Corp.
379 N.W.2d 333 (Court of Appeals of Wisconsin, 1985)
Wozniak v. Wozniak
359 N.W.2d 147 (Wisconsin Supreme Court, 1984)
La Velle v. De Luca
180 N.W.2d 710 (Wisconsin Supreme Court, 1970)
Kobayashi v. Meehleis Steel Co.
472 P.2d 724 (Colorado Court of Appeals, 1970)
Burger v. Wood
446 S.W.2d 436 (Missouri Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
150 N.W.2d 379, 35 Wis. 2d 1, 1967 Wisc. LEXIS 1177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-m-heating-co-v-andrae-wis-1967.