Hennessey v. Fleming Bros.

90 P. 77, 40 Colo. 27
CourtSupreme Court of Colorado
DecidedApril 15, 1907
DocketNo. 5288; No. 2920 C. A.
StatusPublished
Cited by1 cases

This text of 90 P. 77 (Hennessey v. Fleming Bros.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hennessey v. Fleming Bros., 90 P. 77, 40 Colo. 27 (Colo. 1907).

Opinion

Mr. Justice Maxwell

delivered the opinion of the court;

Appellees entered into a written contract with appellant to build five two-story dwelling houses.

[28]*28The complaint, setting forth in full the contract and the specifications which were embodied therein, was based upon three causes of action: 1st, a balance due upon the contract; 2nd, a bill of extras furnished over and above the requirements of the contract; 3rd, work and labor done for defendant at his request, upon his residence. The complaint alleged performance upon the part' of plaintiffs of all precedent conditions contained in the contract upon their part to. be. performed. The contract price for the five dwelling houses was $9,591.00.

■ The answer admitted the making of the contract; denied that the same is correctly set out in the complaint; admitted the payments alleged; denied performance by plaintiffs; alleged damage by reason of inferior workmanship and material, and alleged a settlement between the parties, before suit. As to the third cause of action, the answer alleged that plaintiffs paid defendant in full settlement and discharge thereof.

A replication put in issue all the material new matter alleged in the answer. Trial to a jury resulted in a verdict and judgment in favor of plaintiffs against defendant in the sum of $1,240.00, to reverse which is this appeal. Numerous errors are assigned. A consideration of those based upon the admission of evidence hereinafter noticed necessitates a reversal of the judgment.

Portions of the specifications embodied in the contract material to a determination of this case are as follows:

The ground to be excavated to a depth to make the cellars seven feet from the cement floor to the first floor joist. The ground removed from the excavation to be graded around the houses after the walls are up. * # * Foundations to go to solid ground. [29]*29* # * The cellar to be cemented over the entire bottom, the cement to be laid on three inches of con-. crete well mixed with Louisville cement and well pounded down, the top coat to be mixed with B. & S. cement in proper proportions to make a strong job.”

The foregoing specifications determine three things: 1st, that the foundations were to go to solid ground; 2nd, that the cellars were to be seven feet high from the cement floor, which was to be laid on three inches of concrete; 3rd, that the ground removed from the excavations was to be graded around the houses.

Over the objection of defendant, plaintiffs were allowed to introduce testimony to prove that, by reason of the character of the ground, it was necessary to excavate more than seven feet in depth to secure solid ground for the foundations; that such excavation necessitated the removal of an increased amount of earth and rubbish; that the foundation walls, by reason of such increased excavation, required the laying of more brick; that it was necessary for plaintiffs to fill in the enlarged excavation with sand and gravel in order to secure a foundation for the concrete floor to be laid in the cellars, and that the increased excavation necessitated the removal from the premises of an increased amount of earth and rubbish.

The testimony objected to showed, that the total amount claimed by plaintiffs on account of the increased excavation, the extra brick used in the foundations, and the filling of the cellars was $683.08; and that the amount claimed for the removal of extra earth and debris taken from the cellars was $150.00.

The evidence discloses that, after the excavation for the dwellings had been commenced, it was discovered that the site of the proposed buildings was an old dump which had been filled in with rubbish of various lands.

[30]*30■ One of the plaintiffs testified, that after this discovery was made, he talked the matter over with defendant and that defendant told him that the rubbish would have to be taken out; that witness told defendant that it would cost more than they figured on, but that defendant said it would have to come out at any rate. Upon cross-examination, this witness testified that he told defendant, at or about the time the contract was signed, that there might be some fill in there, because he had known of people hauling stuff in there from other jobs.

The testimony of this witness also shows, that the words “Foundations to go to solid ground” were inserted in the contract, at the request of defendant over the protest of plaintiffs, plaintiffs finally consenting thereto, and that at the time the contract was so amended, both parties knew that the site upon which the houses were to be built was, in part at least, made ground.

There is no claim that defendant agreed to pay any part of the alleged extras.

It is the contention of defendant that the extras claimed for increased excavation, increased material in the foundation walls, the filling in necessary to bring the cellar floors to within seven feet of the first floor joists, and the expense of removing' the earth and rubbish taken from the enlarged excavation, should not be allowed, as all such work and material was provided for by the express terms of the contract. On the other hand, plaintiffs claim, that all such work and material was not contemplated by the contract, or the parties, at the time the same was entered into, and that such work and materials come clearly within the definition of extras, as the same is used in building contracts.

“The question of what constitutes extra work depends of course, as a general rule, upon the con[31]*31struction of the working contract, and when the construction of an entire work is called for, at a fixed compensation, the hazards of the undertaking are assumed by the contractor and he cannot recover for increased cost, as extra, work, upon discovering that he has made a mistake in his estimate of the cost, or that the work is more difficult and expensive than he anticipated.” — 30 Am. & Eng. Enc. Law (2d ed.) 1279. -

The rule laid down in Fitzgerald v. Walsh, 107 Wis. 92-95, meets with the approval of counsel for both parties:

“It is well settled that where a builder is ordered to make changes from the original contract plans, which are really extras, or to do work in some way connected with the original contract but substantially independent of it, and the circumstances are such that the proprietor must know that the execution of such orders will cause extra labor and expense to the builder not contemplated by either party in the original contract, he is liable to compensate the builder therefor in the absence of some express provision in such original contract to the contrary.”

Under the above definitions the work and materials now under consideration, except the removal of the rubbish, were not extras, for the reasons, that they were not caused by changes from the original contract plans and were not substantially or in any manner independent of such plans, but under plaintiffs ’ testimony must have been contemplated by both parties to the contract at the time the contract was entered into.

The words “Foundations to go to solid ground” are plain and unambiguous. They were inserted at the instance of defendant and over the protest of plaintiffs, with knowledge upon the part of both [32]*32parties that the nature and character' of the ground might require increased excavation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hahl v. Langfur Construction Corp.
529 P.2d 1369 (Colorado Court of Appeals, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
90 P. 77, 40 Colo. 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hennessey-v-fleming-bros-colo-1907.