Barker & Stewart Lumber Co. v. Marathon Paper Mills Co.

130 N.W. 866, 146 Wis. 12, 1911 Wisc. LEXIS 90
CourtWisconsin Supreme Court
DecidedApril 5, 1911
StatusPublished
Cited by43 cases

This text of 130 N.W. 866 (Barker & Stewart Lumber Co. v. Marathon Paper Mills Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barker & Stewart Lumber Co. v. Marathon Paper Mills Co., 130 N.W. 866, 146 Wis. 12, 1911 Wisc. LEXIS 90 (Wis. 1911).

Opinion

WiNsnow, C. J.

Our statute (sec.. 3314, Stats. 1898) gives a mechanic’s lien to every principal contractor who furnishes materials “for or in or about the erection, construction, repair,” etc., of any structure which becomes part of the freehold. By another-section (sec. 3315, Stats. 1898), under certain circumstances, a like lien is given to a material-man who furnishes any materials to the principal contractor “in any of the cases mentioned” in sec. 3314. In either case, [16]*16therefore, tbe lien is given for materials furnished “for or in or about” the erection of the structure, and the exact question here is whether the materials which went into the cofferdarp. were furnished for, in, or about the erection of the permanent dam. This is a new question in this state. We have been referred to no decisions in any court covering the precise point, and we readily confess that it is a question involved in more than ordinary difficulty. A decision either way could be supported by arguments fairly logical and convincing in their nature.

It will be useful at the outset to state briefly some of the general principles which this court has already laid down on the subject of mechanics’ liens. The first and perhaps the most important of these is the principle that mechanic’s lien statutes are remedial in their character and are to be liberally construed so as to effectuate their remedial purpose. Vilas v. McDonough Mfg. Co. 91 Wis. 607, 65 N. W. 488; Kendall v. Hynes L. Co. 96 Wis. 659, 71 N. W. 1039; Winslow v. Urquhart, 39 Wis. 260. Another principle is that, if material be furnished to the owner for use in the construction of a building and the construction be actually commenced, the materialman is entitled to his lien even though the owner does not use the materials at all, but disposes of them elsewhere. Esslinger v. Huebner, 22 Wis. 632; Fitzgerald v. Walsh, 107 Wis. 92, 82 N. W. 717; Halsey v. Waukesha Springs S. Co. 125 Wis. 311, 104 N. W. 94. But if a subcontractor delivers materials to the principal contractor at the latter’s place of business, which materials are neither incorporated into the structure, delivered upon the premises, nor placed under control of the owner of the structure, no lien arises, because the material cannot be said to have been furnished for, in, or about the erection of the structure. Francis & N. F. Co. v. King Knob C. Co. 142 Wis. 619, 126 N. W. 39. This last named case is claimed by the appellant to decide that a subcontractor can have no lien unless [17]*17the materials be furnishes are actually incorporated into the building, and there is language in the opinion which gives color to that idea; but the case itself was simply a case where the subcontractor who claimed a lien had delivered a wheel to the principal contractor at the latter’s place of business in Chicago, which wheel never reached the premises or the control of the owner of the building, but went into the hands of the receiver in bankruptcy of the principal contractor in Chicago and was sold by him to strangers. Under these circumstances, there being neither incorporation into the building, delivery upon the premises, nor control by the owner, it was held that there could be no lien. .Whether there would be a lien in case there had been delivery upon the premises into the control of the owner but no incorporation into the building was not decided, although the fact was considered as significant that in previous eases it had been assumed or stated in obiter remarks that incorporation into the building was necessary in order to arouse a lien on behalf of the subcontractor. The only point actually decided, however, was that the facts of that case did not constitute a furnishing of materials which would arouse the lien.

It seems equally certain that the expressions in previous cases in this court, which are supposed to justify the idea that a subcontractor’s lien is absolutely dependent upon physical incorporation of the materials furnished into the structure, do not so hold when construed with reference to the questions at issue in the cases themselves. Thus in McAuliffe v. Jorgenson, 107 Wis. 132, 82 N. W. 706, where the owner of a well-boring machine, who leased it to the principal contractor, who was digging a well, claimed a subcontractor’s lien for the hire of the machine, it was said that under no theory could it be held that the plaintiff furnished any materials which entered into or became a component part of the well, but that the machine simply was a part of the contractor’s plant. So in Rinzel v. Stumpf, 116 Wis. 287, 93 N. W. 36, the ques[18]*18tion was whether certain shelving and counters in a store were intended to he fixtures, so as to become part of the realty, or intended to be personal property alone, and the question of lien was dependent on this question. It was in this connection said that “the materials furnished must become a part of the building,” but it is very plain that in neither of these cases was it held that under no circumstances could a subcontractor acquire a mechanic’s lien unless the materials furnished by him were actually incorporated into the finished structure.

It is very easy to see why, in case a subcontractor delivers materials to the principal contractor and the latter immediately sells them elsewhere, no1 lien should exist; but it is not easy to see why, in case the materials actually come into'the possession and control of the owner and he retains or disposes of them, there should not result a lien just as well as in the case where the principal contractor makes a like delivery into the possession of the owner. The statute gives the subcontractor a lien for furnishing materials “in any of the cases” named in the section giving a lien to the principal contractor, and under the decisions of this court the delivering of materials into the control of the owner, regardless of the subsequent disposition of them by such owner, is one of the cases in which the principal contractor is given a lien.

We have thus dealt somewhat at length with the Francis Case because it is confidently claimed to be decisive of the present case, in that it holds that actual physical incorporation of the materials into the structure is essential to every subcontractor’s lien. Inasmuch as it does not so hold, the court approaches the present case in no way hampered by anything which is said in that case, nor by the remarks in the previous cases cited in the Francis Case. In none of the cases was it necessary to decide, nor did the court attempt to decide, that physical incorporation of the materials was in all cases essential to the lien. Starting from this basis, the [19]*19question bere really is whether this cofferdam, after its construction, is properly to be considered as an appliance or a part of the contractor’s plant, like a portable engine, a derrick, a steam shovel, or tool shed, or as a collection of materials furnished “for or in or about” the erection and construction of the permanent dam. If it be an appliance, or, as said in the McAuliffe Case, a part of tire contractor’s plant, then it is very clear that there can be no lien for the materials which went into it. Appliances are, generally speaking, things which are expected to be used again and again. They are in effect tools.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goebel v. National Exchangors, Inc.
277 N.W.2d 755 (Wisconsin Supreme Court, 1979)
Builder's Lumber Co. v. Stuart
94 N.W.2d 630 (Wisconsin Supreme Court, 1959)
Fidelity & Deposit Co. v. Mattingly Lumber Co.
4 A.2d 447 (Court of Appeals of Maryland, 1939)
Trapp v. Seaboard Surety Co.
161 Misc. 428 (New York Supreme Court, 1936)
Thew Shovel Co. v. Massachusetts Bonding & Insurance
88 S.W.2d 960 (Court of Appeals of Kentucky (pre-1976), 1935)
American Tank & Equipment Co. v. T. E. Wiggins, Inc.
1934 OK 661 (Supreme Court of Oklahoma, 1934)
Marion Steam Shovel Co. v. Union Indemnity Co.
75 S.W.2d 541 (Court of Appeals of Kentucky (pre-1976), 1934)
White v. United States Fidelity & Guaranty Co.
256 N.W. 694 (Wisconsin Supreme Court, 1934)
Century Indemnity Co. v. Shunk Manufacturing Co.
68 S.W.2d 772 (Court of Appeals of Kentucky (pre-1976), 1934)
Union Indemnity Co. v. Pennsylvania Boiler Works
55 S.W.2d 367 (Court of Appeals of Kentucky (pre-1976), 1932)
Tway v. Thompson
1932 OK 595 (Supreme Court of Oklahoma, 1932)
Board of Public Education v. Aetna Casualty & Surety Co.
159 A. 367 (Superior Court of Delaware, 1932)
Walker v. Collins Construction Co.
236 N.W. 334 (Nebraska Supreme Court, 1931)
Standard Oil Co. v. Federal Surety Co.
28 F.2d 489 (Eighth Circuit, 1928)
Mid-Continent Petroleum Corp. v. Southern Surety Co.
9 S.W.2d 229 (Court of Appeals of Kentucky (pre-1976), 1928)
Neumann v. Strandt
219 N.W. 348 (Wisconsin Supreme Court, 1928)
National Surety Co. v. Arizona Grocery Co.
259 P. 404 (Arizona Supreme Court, 1927)
Maryland Casualty Co. v. Ohio River Gravel Co.
20 F.2d 514 (Fourth Circuit, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.W. 866, 146 Wis. 12, 1911 Wisc. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barker-stewart-lumber-co-v-marathon-paper-mills-co-wis-1911.