Parnell-Martin Supply Co. v. High Point Motor Lodge, Inc.

177 S.E.2d 392, 277 N.C. 312, 1970 N.C. LEXIS 600
CourtSupreme Court of North Carolina
DecidedNovember 18, 1970
Docket24
StatusPublished
Cited by16 cases

This text of 177 S.E.2d 392 (Parnell-Martin Supply Co. v. High Point Motor Lodge, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parnell-Martin Supply Co. v. High Point Motor Lodge, Inc., 177 S.E.2d 392, 277 N.C. 312, 1970 N.C. LEXIS 600 (N.C. 1970).

Opinion

*316 BRANCH, Justice.

One who has furnished materials used in the construction of a building under contract with a subcontractor may recover pursuant to Chapter 44 of the General Statutes when he proves (1) that materials were furnished to someone having contractual relations to the work, (2) a balance due him, (3) notice to the owner as required by statute prior to payment of the contract price by the owner to the principal contractor, (4) a balance due the contractor. The law requires the owner to apply the unexpended contract price due the contractor towards payment of the claims of subcontractors and material-men who have given the required notice. Oldham & Worth v. Bratton, 263 N.C. 307, 139 S.E. 2d 653; Powder Co. v. Denton, 176 N.C. 426, 97 S.E. 372; Brick Co. v. Pulley, 168 N.C. 371, 84 S.E. 513. The notice to the owner may be given in two ways: (1) The principal contractor is required by statute before receiving any part of the contract price to furnish owner with “itemized statement of the amount owing to any laborer, mechanic or artisan employed by such contractor, architect or other person, or to any person for materials furnished, . . . .” G.S. 44-8 and G.S. 44-12. (2) The subcontractor or materialmen having contractual relations with the work may give notice to the owner of the amount due, which notice shall be in the form of an itemized statement unless the contract is entire and for a gross sum. G.S. 44-9.

In instant case contractor did not give notice to owner pursuant to G.S. 44-8. Thus if required notice was received, it must have been received from plaintiff pursuant to provisions of G.S. 44-9.

It is well recognized that, as between owner and drawee bank, owner had authority to countermand or order the drawee bank to stop payment on the check at any time before drawee bank paid the check. Bank v. Bank, 118 N.C. 783, 24 S.E. 524; 10 Am. Jur. 2d, Banks, § 641. It is equally well recognized in this jurisdiction that in the absence of an agreement to the contrary, delivery of a check by a debtor to a creditor and acceptance of the check by the creditor does not constitute payment until the check is paid by the drawee bank, but if the check is paid upon presentation, the payment is deemed to have been made at the time the check was given. Paris v. Builders Corp., 244 N.C. 35, 92 S.E. 2d 405, and cases cited.

*317 The last stated rule is ordinarily applied in debtor-creditor relationships. The courts have applied the rule in determining whether payment by check of an insurance premium was timely made, Cauley v. Ins. Co., 219 N.C. 398, 14 S.E. 2d 39; whether notice was duly given in workmen’s compensation cases when notice of greater claim was required within one year from payment by employee, Paris v. Builders Corp., supra; and whether taxes were paid before required date, Tonnar v. Wade, 158 Miss. 722, 121 So. 156. However, standing alone, the above rules do not control the question of owner’s duty to stop payment. Indeed, our research fails to reveal a case which is in point on this novel question, and we therefore look to analogous relationships for guidance.

Conceding, arguendo, that the statutory notice was delivered to owner prior to payment of the check by drawee bank, we must decide whether it was incumbent upon owner to stop payment on the check when check was delivered to contractor prior to receipt of statutory notice by owner.

The statutory remedy of garnishment, recognized in many jurisdictions, creates rights and duties which are strikingly similar to those Chapter 44 of the General Statutes creates between subcontractors, owners of property, and claimants. In the usual garnishment proceeding the plaintiff seeks satisfaction of the indebtedness out of property or credits of his debtor in the possession of or owing by a third person. 6 Am. Jur. 2d, Attachments and Garnishment, § 2, at p. 561. The statutory rights conferred by Chapter 44 of General Statutes permit the plaintiff, upon giving required statutory notice, to seek satisfaction of indebtedness due him from the subcontractor from funds retained by owner and due on contract price. Analogy is further enhanced by the fact that if either the garnishee or owner pays his creditor (the principal defendant or the general contractor) after receiving proper notification of the garnishment proceeding or claim of lien, he is personally liable. Hart v. Veneer Co., 287 Ill. App. 89, 4 N.E. 2d 499.

We find, in the framework of garnishment proceedings, that the courts have ruled on the duty of the garnishee to stop payment on a check when he is served with process after he had delivered the check to his creditor in final payment.

In the case of Hart v. Veneer Co., supra, the plaintiff served garnishment process upon garnishee two days after he had given a check to the principal debtor. The service was made *318 several days before the check was paid by the drawee bank. The garnishee, as an affirmative defense, asserted that he owed the defendant nothing because of delivery of the check given in final payment. The plaintiff contended that garnishee had a duty to stop payment on the check. The Illinois garnishment statute required the garnishee, after being properly served with notice of garnishment proceedings, “to thereafter hold any property, effects, choses in action or credits in their possession or power belonging to the defendant which are not exempt, subject to the court’s order.” The court, holding that the statute did not impose a duty to stop payment, said:

“In Waples on Attachments and Garnishments, the author says (section 364) : ‘One is not liable to garnishment if he has paid what he owed the defendant in attachment by a bank check, though the latter may not have presented the check to the bank and drawn the money prior to the service of the process of garnishment upon the drawer of the check. It is true that the funds in the bank are still under his control, so that he might stop payment of the check; and, so far as the bank is concerned, he has the right to control the deposit; but he has no moral right to do so, considering his relation to the payee who has taken the check in payment or earnest of payment. At all events, the drawer as garnishee, is not under the slightest obligation to countermand his own check for the purpose of enabling a professed creditor of the payee to attach the credit in his hands and suspend settlement of his account with the payee for an indefinite time.’ ”

Accord: Universal Supply Co. v. Hildreth, 287 Mass. 538, 192 N.E. 23, 94 A.L.R. 1389, and cases cited; Prewitt v. Brown, 101 Mo. App. 254, 73 S.W. 897.

In 6 Am. Jur. 2d, Attachment and Garnishment, § 517, p. 928, we find the following:

“Duty of garnishee to stop payment or delivery of check for indebtedness. — The drawer of a check is under no duty or obligation to stop payment, when garnished, for the benefit of the garnishing plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMillan v. Blue Ridge Cos., Inc.
Supreme Court of North Carolina, 2021
Hsg, LLC v. Edge-Works Manuf. Co.
2015 NCBC 87 (North Carolina Business Court, 2015)
State v. Stokes
621 S.E.2d 311 (Court of Appeals of North Carolina, 2005)
Michael Acri Boxing Promotions, Inc. v. Miles
758 So. 2d 704 (District Court of Appeal of Florida, 2000)
McCullough v. Branch Banking & Trust Co.
524 S.E.2d 569 (Court of Appeals of North Carolina, 2000)
Central Security & Alarm Co. v. Mehler
1998 NMCA 096 (New Mexico Court of Appeals, 1998)
Wilson v. Claude J. Welch Builders Corp.
444 S.E.2d 628 (Court of Appeals of North Carolina, 1994)
Electric Supply Co. of Durham, Inc. v. Swain Electrical Co.
403 S.E.2d 291 (Supreme Court of North Carolina, 1991)
Queensboro Steel Corp. v. East Coast MacHine & Iron Works, Inc.
346 S.E.2d 248 (Court of Appeals of North Carolina, 1986)
Winston-Salem Joint Venture v. City of Winston-Salem
282 S.E.2d 509 (Court of Appeals of North Carolina, 1981)
Pennington v. Flame Refractories, Inc.
281 S.E.2d 463 (Court of Appeals of North Carolina, 1981)
Faulkner v. North Carolina State Hearing Aid Dealers & Fitters Board
247 S.E.2d 668 (Court of Appeals of North Carolina, 1978)
Corrugated Industries, Inc. v. Chattanooga Glass Co.
317 So. 2d 43 (Mississippi Supreme Court, 1975)
Lafayette Transportation Service, Inc. v. County of Robeson
196 S.E.2d 770 (Supreme Court of North Carolina, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
177 S.E.2d 392, 277 N.C. 312, 1970 N.C. LEXIS 600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parnell-martin-supply-co-v-high-point-motor-lodge-inc-nc-1970.