Wentworth v. Tubbs

55 N.W. 543, 53 Minn. 388, 1893 Minn. LEXIS 344
CourtSupreme Court of Minnesota
DecidedJune 1, 1893
StatusPublished
Cited by27 cases

This text of 55 N.W. 543 (Wentworth v. Tubbs) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wentworth v. Tubbs, 55 N.W. 543, 53 Minn. 388, 1893 Minn. LEXIS 344 (Mich. 1893).

Opinion

Mitchell, J.

This action, which was to foreclose a mechanic’s lien, is brought here on the findings of the court, without any case or bill of exceptions, and hence the only question is whether the conclusions of law are justified by the findings of fact. Tubbs is the owner of the premises, who contracted for the construction of the building. Topliff is a mortgagee of the premises, and the other defendants and the plaintiff claim liens for labor and material performed or furnished for the construction of the building. As Sedgwick is the only' appellant, and as his assignments of error relate only to the decision of the court in favor of Topl'iff, we have only to consider the relative rights of these two parties.

Sedgwick claims a lien for labor and skill performed and furnished, at the request of Tubbs, in preparing plans for the building, and in superintending its construction. The court finds “that he commenced to draw the plans on the 1st of February, 1890, but that this work was then commenced in his office, and not upon the ground; that there was nothing upon the premises up to May 26, 1890, to indicate that any architect had been employed for any purpose in connection with the premises, or for the purpose of erecting any building or structure thereon; and that up to sa'id time said architect performed no labor, services, or skill upon said premises.” The court also finds that “after said 26th of May, 1890, said Tubbs commenced the erection of a building on said lot.” We construe this as meaning that no work had been commenced and no labor performed or materials furnished on the premises by any one until after May 26th.

There is a finding that Tubbs caused an excavation to be made on the lot about March 1, 1890, but there is none as to its extent and character, or that it had any relation to the erection of this building; hence we deem the finding wholly immaterial.

Topliff’s claim is based on two mortgages on the premises, executed by Tubbs, — one for $13,000, executed March 13, 1890, and recorded on the 26th of the same month; and the other for $10,-000, executed August 5, 1890, while the building was in process of erection, and recorded the 11th of the same month.

[394]*3941. Appellant’s first assignment of error is that the court erred in holding that his lien was inferior and subordinate to the lien of this first mortgage. This presents the question when appellant’s lien attached,, his contention being that it was acquired February 1, 1890, when he commenced drawing the plans for the building in his office. This involves the construction of the statute. The mechanic’s lien law nowhere in express terms declares when a lien attaches. Laws 1889, ch. 200, § 8, requires that the statement filed shall contain the time when the first and last items of labor or material were furnished, and provides that the statement, when filed, “shall operate to continue such lien during all the period of time from the time of the furnishing of the first item of such labor, etc., until the expiration of one year after the time of furnishing the last item of the same.”

It is on this provision that appellant relies for support for his contention. The tenth section of the act, in effect, provides that all liens for labor, material, etc., furnished for the construction of a building, without regard to the relative dates at which it was furnished, shall be co-ordinate, and without priority one over the other.

The time when a lien is to be considered as acquired depends upon the statute authorizing the remedy. The statutes are not uniform on the subject.

The larger number fix the commencement of the work on the premises — the first labor done or materials furnished on the ground' —as the date when the mechanic’s or material man’s lien attaches,

This is exceedingly fair and liberal to the mechanic, especially under our statute making all liens co-ordinate; so that all who furnish material or labor at any time during the process of construction of the building get a preference over all other liens of a date posterior to “the commencement of improvement on the land” by the one who performs the first labor or furnishes the first material on the ground. Gardner v. Leck, 52 Minn. 522, (54 N. W. Rep. 746.) This works no injustice to any one dealing-with the property, as the work itself is notice to all of the mechanics’ claims. It enables them by ocular examination to ascertain whether they can do so safely.

[395]*395But, on the other hand, it would he very unjust if the land could be afterwards swallowed up by mechanics’ liens for work which had not been commenced on the ground, and of which consequently one who might buy the property or take a mortgage upon it had no notice or means of knowledge when he took bis deed or his mortgage.

The injustice of this would be forcibly illustrated by the facts of this case, where appellant claims a lien as of the date of February 1st, when he perhaps began the mental labor or skill of designing the plans of the proposed building, which furnished ho visible trace of work or labor on the ground itself. If the date of the lien could thus antedate the actual commencement of operations on the premises three months, there is no reason why it might not antedate it three years.

The injustice of this would be intensified under our statute, in view of the fact that the date of the lien of the person who furnished the first material or labor would fix the date of all other mechanics’ liens, regardless of the dates at which such material or labor was in fact furnished. Hence we ought not to give to the statute the construction contended for by appellant, unless it will not reasonably admit of any other; and in determining the meaning of the phrase “time of furnishing,” as used in the eighth section, reference should be had to all the other provisions of the act, as well as its general scope and plan. Of course, as against the owner who contracts for the erection of the building, the question when a mechanic’s lien attaches is of no practical importance. It only becomes material with reference to subsequent purchasers and mortgagees. Taking into consideration all the different provisions of the statute, as well as oúr previous decisions construing it, we are of the opinion that, as regards the date of acquiring a lien, the word “furnished” or “furnishing,” as used in the law, means furnished on the premises, and that the liens of mechanics or material men all attach as of the date of the performance of the first work or the delivery of the first material on the ground.

This was the view taken in Glass v. Freeburg, 50 Minn. 386, (52 N. W. Rep. 900,) and Gardner v. Leck, supra, and it was upon this theory of the law that in the latter case it was held that all liens for labor or material furnished by any one, at any time during the [396]*396progress of the work, attach as of the date of the commencement of improvement on the land.

Our decisions to the effect that a party might, under certain circumstances, have a lien for material which was never actually delivered on the premises, or not actually used in the building, are not inconsistent with this view. In all these cases it will be found that not only was no question of bona fide

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens State Bank v. Raven Trading Partners, Inc.
786 N.W.2d 274 (Supreme Court of Minnesota, 2010)
Carlson-Grefe Construction, Inc. v. Rosemount Condominium Group Partnership
474 N.W.2d 405 (Court of Appeals of Minnesota, 1991)
In Re Zachman Homes, Inc.
47 B.R. 496 (D. Minnesota, 1984)
Jesco, Inc. v. Home Life Insurance Co.
357 N.W.2d 123 (Court of Appeals of Minnesota, 1984)
Lampert Yards, Inc. v. Thompson-Wetterling Construction & Realty, Inc.
223 N.W.2d 418 (Supreme Court of Minnesota, 1974)
Dunham Associates, Inc. v. Group Investments, Inc.
223 N.W.2d 376 (Supreme Court of Minnesota, 1974)
Drilling Service Co. v. Baebler
484 S.W.2d 1 (Supreme Court of Missouri, 1972)
M. E. Kraft Excavating & Grading Co. v. Barac Construction Co.
156 N.W.2d 748 (Supreme Court of Minnesota, 1968)
Reuben E. Johnson Co. v. Phelps
156 N.W.2d 247 (Supreme Court of Minnesota, 1968)
First National Bank v. Schunk
276 N.W. 290 (Supreme Court of Minnesota, 1937)
Union Trust Co. of Maryland v. Rodeman
264 N.W. 508 (Wisconsin Supreme Court, 1936)
Anderson v. Peterson State Bank
254 N.W. 459 (Supreme Court of Minnesota, 1934)
Schroeter Bros. Hardware Co. v. Croatian "Sokol" Gymnastic Ass'n
58 S.W.2d 995 (Supreme Court of Missouri, 1933)
Kingery v. Kingery
241 N.W. 583 (Supreme Court of Minnesota, 1932)
Oman v. Balfany
201 N.W. 916 (Supreme Court of Minnesota, 1925)
Crane Co. v. Naylor
1918 OK 138 (Supreme Court of Oklahoma, 1918)
Stravs v. Steckbauer
161 N.W. 259 (Supreme Court of Minnesota, 1917)
Erickson v. Ireland
158 N.W. 918 (Supreme Court of Minnesota, 1916)
Minneapolis Sash & Door Co. v. Hedden
154 N.W. 511 (Supreme Court of Minnesota, 1915)
Lamoreaux v. Andersch
150 N.W. 908 (Supreme Court of Minnesota, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
55 N.W. 543, 53 Minn. 388, 1893 Minn. LEXIS 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wentworth-v-tubbs-minn-1893.