Lampert Yards, Inc. v. Thompson-Wetterling Construction & Realty, Inc.

223 N.W.2d 418, 302 Minn. 83, 1974 Minn. LEXIS 1164
CourtSupreme Court of Minnesota
DecidedNovember 8, 1974
Docket43935
StatusPublished
Cited by13 cases

This text of 223 N.W.2d 418 (Lampert Yards, Inc. v. Thompson-Wetterling Construction & Realty, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lampert Yards, Inc. v. Thompson-Wetterling Construction & Realty, Inc., 223 N.W.2d 418, 302 Minn. 83, 1974 Minn. LEXIS 1164 (Mich. 1974).

Opinion

Peterson, Justice.

This is an appeal from the judgment of the district court and a request for review of that judgment. The trial court awarded priority to the mortgage of plaintiff Northwestern National *85 Bank of Mankato on a bankrupt apartment project, over various mechanics liens, according to the provisions of Minn. St. 1971, § 514.05. 1 However, the trial court made certain deductions from the amount of the statutory priority and also failed to order foreclosure of liens against the bankrupt project which had been assigned to Northwestern. Northwestern’s appeal arises: out of these latter actions. Respondents are mechanics lienholders who seek reversal of the trial court’s judgment granting statutory priority to Northwestern.

On October 2, 1969, Thompson-Wetterling Construction & Realty, Inc., executed a note and mortgage in the amount of $119,000 in favor of Northwestern, to secure a loan for the construction of an apartment building on real estate owned by the construction company. On the same day, a building permit issued for construction and two of the respondents at the request of Thompson-Wetterling spent several hours on the property outlining the building on; the lot. These respondents drove new stakes in the ground at the four comers of the proposed building. Batter boards consisting of 2 x 4’s were nailed to the stakes horizontally, and test string was run around the perimeter of the proposed building and nailed to the batter boards. The elevation of the batter boards and the string was approximately 1 % *86 feet off the ground. The site of the proposed building was set back 50 feet from the front of the lot. The batter board construction could not be seen from the edge of the field because the lot was covered with weeds about 3 feet high.

On October 3, 1969, the mortgage was recorded. Excavation of the site for sewer and water began 3 days later. The total mortgage money of $119,000 was disbursed in three payments between October 23, 1969, and February 5, 1970. At no time during the disbursements did Thompson-Wetterling possess lien waivers from its laborers and materialmen in the amount of even 50 percent of the total mortgage money which it received. The trial court found that Northwestern was negligent in its authorization and supervision of the loan, violating its own customary standards for construction lending.

On May 11, 1970, Thompson-Wetterling filed a petition in bankruptcy. Lien statements were filed by various subcontractors and materialmen between May 8, 1970, and June 11, 1970. On July 2, 1970, plaintiff Lampert Yards, Inc., one of the lien claimants, commenced an action to foreclose its lien. On July 27, 1970, Northwestern commenced its mortgage foreclosure action. The two actions were consolidated for trial.

Before trial, Northwestern made two factually relevant purchases. On July 20, 1970, the bank purchased the bankruptcy trustee’s interest in the property for $2,500. The bank went into possession of the building, invested additional money to complete the construction, and rented it, obtaining rental income of approximately $10,000 by the date of trial. The bank also purchased, for “good and valuable consideration,” six of the smaller mechanics liens, the face value of which aggregated $9,911.17.

The trial court determined that Northwestern’s mortgage had priority over the lienholders because the mortgage was executed and recorded before the “actual and visible beginning of the improvement” within the meaning of Minn. St. 1971, § 514.05. However, the trial court also determined that the carelessness of the bank in managing the loan approval and disbursements *87 created an equitable estoppel. Consequently, the trial court reduced the amount of the bank’s priority to only that amount for which Thompson-Wetterling had received lien waivers, evidently on the theory that mortgage disbursements not made against lien waivers were negligently paid. The court further reduced the priority of Northwestern by the amount of rent which it had received from the completed building following its purchase of the bankruptcy trustee’s interest in the project, ruling that such rent monies should have been applied by Northwestern against the mortgage debt.

For reasons not made clear in its memorandum opinion, the court failed to order foreclosure of the mechanics liens assigned to Northwestern.

1. Respondents seek review of the district court’s conclusion that Northwestern was entitled to statutory priority. Minn. St. 1971, § 514.05, allows mortgage lienholders priority over mechanics lien claimants whenever the mortgage is executed and recorded “prior to the actual and visible beginning of the improvement on the ground.” The trial court determined that such actual and visible beginning commenced on October 6, 1969, 3 days after the mortgage had been recorded. The court relied upon the authority of Reuben E. Johnson Co. v. Phelps, 279 Minn. 107, 156 N. W. 2d 247 (1968), in concluding that the batter board construction in place before the recording of the mortgage was not an actual and visible beginning within the meaning of the statute.

In Phelps, we held that the presence of a few grade or fill stakes not readily visible to observers who walked the field in question did not constitute such actual and visible notice as required by § 514.05. We said (279 Minn. 112, 156 N. W. 2d 251):

“* * * In order to have priority over a mortgage duly recorded, the material or labor furnished for the improvement must represent an actual beginning of the improvement on the ground and it must be visible; that is, a person using reasonable diligence in examining the premises must be able to see it.”

*88 Respondents argue that, by implication from the facts of Phelps, the rule of law should be that reasonable diligence is required in physically examining the property and that notice is given to potential mortgagors if the beginnings of construction are observable by actually walking on the property. Since anyone inspecting the property by walking on it would have encountered the strings, and eventually the batter board construction, respondents argue that the legal conclusion of the district court that the beginning of construction was not visible must be reversed and that they should be awarded priority over the mortgage.

We do not agree. The legislative intent behind the statute would not be served by a rule of law which established statutory notice whenever such slight structures as then existed could be discovered only by tramping the fields of an intended construction site. Several of the lienors admitted that the batter board structure was not visible from the edge of the field. The terrain was flat, and the edge of the field constituted a reasonable position from which to make inspection. The statute is intended to provide fair notice to mortgagees of improvements “on the ground.” Wentworth v. Tubbs, 53 Minn. 388, 55 N. W. 543 (1893). We hold, in agreement with the trial court, that such notice is not given where nothing can be seen of the construction from the edge of the field. .

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savannah Place, Ltd. v. Heidelberg
122 S.W.3d 74 (Missouri Court of Appeals, 2003)
GBJ, Inc. v. First Avenue Investment Corp.
520 N.W.2d 508 (Court of Appeals of Minnesota, 1994)
Wietzki v. Wietzki
437 N.W.2d 449 (Nebraska Supreme Court, 1989)
Estate of Frantz v. Page
426 N.W.2d 894 (Court of Appeals of Minnesota, 1988)
Cox v. First National Bank of Aitkin
415 N.W.2d 385 (Court of Appeals of Minnesota, 1987)
In Re Zachman Homes, Inc.
47 B.R. 496 (D. Minnesota, 1984)
Jesco, Inc. v. Home Life Insurance Co.
357 N.W.2d 123 (Court of Appeals of Minnesota, 1984)
Town Board of Marshan v. City Council of Hastings
298 N.W.2d 353 (Supreme Court of Minnesota, 1980)
R. M. Shoemaker Co. v. Southeastern Pennsylvania Economic Development Corp.
419 A.2d 60 (Superior Court of Pennsylvania, 1980)
Rm Shoemaker v. Southeast. Pa. Econ.
419 A.2d 60 (Superior Court of Pennsylvania, 1980)
Mesaba Aviation Division of Halvorson of Duluth, Inc. v. County of Itasca
258 N.W.2d 877 (Supreme Court of Minnesota, 1977)
Stofferahn v. Great American Insurance
244 N.W.2d 160 (Supreme Court of Minnesota, 1976)
Kloster-Madsen, Inc. v. Tafi's, Inc.
226 N.W.2d 603 (Supreme Court of Minnesota, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
223 N.W.2d 418, 302 Minn. 83, 1974 Minn. LEXIS 1164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lampert-yards-inc-v-thompson-wetterling-construction-realty-inc-minn-1974.