J Altman Companies, Inc. v. Saginaw Plumbing and Heating Supply Co.

202 N.W.2d 707, 42 Mich. App. 747, 1972 Mich. App. LEXIS 989
CourtMichigan Court of Appeals
DecidedSeptember 26, 1972
DocketDocket 11455
StatusPublished
Cited by7 cases

This text of 202 N.W.2d 707 (J Altman Companies, Inc. v. Saginaw Plumbing and Heating Supply Co.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J Altman Companies, Inc. v. Saginaw Plumbing and Heating Supply Co., 202 N.W.2d 707, 42 Mich. App. 747, 1972 Mich. App. LEXIS 989 (Mich. Ct. App. 1972).

Opinion

Bronson, P. J. J.

Altman Companies, Inc., plaintiff, filed an action in the circuit court to quiet title of certain property. Saginaw Plumbing and Heating Supply Company defended this action, claiming the attachment of an enforceable mechanics’ lien. MCLA 570.1 et seq.; MSA 26.281 et seq. Plaintiff filed a motion for summary judgment, which was granted by the trial judge. Defendant appeals.

The facts of the present case are essentially undisputed. Plaintiff is the owner of a piece of property on which a 155-unit apartment complex was built. Plaintiff contracted with Altman Construction Corporation (the general contractor) for the construction of this facility. The general contractor subcontracted the plumbing work for this project to the Newberry Plumbing & Heating Supply Company, which in turn hired defendant to supply the necessary plumbing materials.

Pursuant to these contractual relationships, defendant began supplying plumbing material to the apartment project on August 27, 1969. Subsequently, the Newberry Plumbing & Heating Supply Company became insolvent, causing defendant *749 concern about receiving payment for the materials previously delivered. Defendant attempted to seek security for this outstanding debt by filing a notice of intention to claim a mechanic’s lien on July 21, 1970, some 11 months after the first materials were furnished. Plaintiff responded by filing an action to quiet title in the Ingham County Circuit Court. Thereafter defendant joined the general contractor as a third-party defendant and plaintiff filed a motion for summary judgment. During the hearing upon plaintiff’s motion, defendant conceded that his notice of lien was not timely filed within the 60-day limitation and proof of service was not recorded as required by the statute. However, defendant contended that this noncompliance was excused because the owner had actual knowledge of his claim. This argument was predicated upon an allegation that since the general contractor was the alter ego of the owner, its knowledge was imputed to the owner. Plaintiff accepted, for purposes of argument on the motion only, that the owner and general contractor were the same organization, consisting of the same officers and directors. Plaintiff followed this approach believing that there were no currently recognized exceptions to strict compliance with the procedural prerequisites of the statute.

The trial judge accepted plaintiff’s argument and granted summary judgment in its favor. Defendant appeals this decision upon the basis that strict compliance with the procedural requirements of the mechanics’ lien act is excused when the owner either (1) "deals directly” with the materialman or (2) possesses actual knowledge of its claim. Defendant’s contention of "direct dealing” is raised for the first time on this appeal. Since the failure to raise the issue before the trial judge precluded the *750 necessary findings of fact, it was dismissed from the present appeal by an order of this Court entered February 23, 1972.

Defendant’s second contention is merely an astute recharacterization of the first. The nature of defendant’s alleged exception depends exclusively upon the existence of knowledge on the part of the owner. Little difference can be perceived between imputing such knowledge to the owner by finding "direct dealing” and recognizing the existence of such knowledge when gained by another source. Upon the facts before us, knowledge can only be attributed to the plaintiff by the alleged coexistent identity of the owner and general contractor. This single vehicle for imputing knowledge to the plaintiff depends upon the same evidence and testimony regardless of the theory employed. Thus, defendant’s attempted recharacterization fails upon the present record to raise a substantively distinct theory and would be controlled by our ruling upon the claim of "direct dealing”. The entire appeal would be dismissed and remanded for the necessary findings of fact but for the trial court’s ruling that no exceptions to strict compliance with the statute are currently recognized. We cannot agree that this constitutes a correct statement of law.

The standard for construing the mechanics’ lien act was set forth in Smalley v Northwestern Terra-Cotta Co, 113 Mich 141, 148 (1897). Therein the Court enunciated the governing rule by citation to hornbook authority as follows:

" 'Mechanics’ liens are in derogation of the common law, depending for their existence wholly upon statutes, and therefore, upon the question whether a lien attaches at all, a strict construction is proper. ’
"Section 1556 of the same author reads:
" But, after the lien has once attached, a liberal *751 construction should be put upon the statute, for the purpose of fulfilling its objects. * * * ’ ” (Emphasis added.)

Thus, a distinction was drawn between the construction of the statute for purposes of attachment and enforcement. The statute is to receive a strict construction until the lien attaches and once it attaches, a liberal construction to fulfill its remedial character. This approach was recently reaffirmed by the Court in Wallich Lumber Co v Golds, 375 Mich 323, 326 (1965). 1

Compliance with the procedural provisions of the act were generally interpreted liberally prior to 1929. This approach was predicated upon the holdings of the early courts that several procedural requirements fell into the latter category of enforcement and were not conditions precedent to the attachment of a lien. 2 In this manner the purpose of the act to protect subcontractors, laborers, and materialmen was fulfilled. 3 It is not necessary to detail the distinctions between these early cases or define the limitations of their holdings. This body of case law was substantially modified in 1929 when the mechanics’ lien act was amended as follows:

*752 "No person shall have a right to claim a lien as in this act provided, unless and until he shall have served a notice as in this section provided, and proof of service of such notice shall be attached to the verified statement or account when filed with the registrar of deeds as provided in section five [5] of this act.” (Emphasis added.) 1929 CL 13101. 4

The effect of this language was considered in Webster v Cooper Development Co, 266 Mich 505, 507 (1934), where a lien was challenged for failure to comply with the statute by filing a proof of service. Therein the Court found this error fatal stating:

"Compliance with this provision of the act is a condition precedent to the acquisition of the lien. The question here is not one of the construction of a statute, it is a question of compliance. There was no compliance with this provision of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams & Works, Inc. v. Springfield Corp.
265 N.W.2d 328 (Michigan Court of Appeals, 1978)
P. H. I. Construction Co. v. Riverview Commons Associates
264 N.W.2d 50 (Michigan Court of Appeals, 1978)
William Moors, Inc. v. Pine Lake Shopping Center, Inc. 1
253 N.W.2d 658 (Michigan Court of Appeals, 1977)
Hodgkiss & Douma, Inc. v. Woodward Development Co.
245 N.W.2d 725 (Michigan Court of Appeals, 1976)
Burton Drywall, Inc. v. Kaufman
244 N.W.2d 367 (Michigan Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
202 N.W.2d 707, 42 Mich. App. 747, 1972 Mich. App. LEXIS 989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-altman-companies-inc-v-saginaw-plumbing-and-heating-supply-co-michctapp-1972.