Smalley v. Northwestern Terra-Cotta Co.

71 N.W. 466, 113 Mich. 141, 1897 Mich. LEXIS 739
CourtMichigan Supreme Court
DecidedMay 28, 1897
StatusPublished
Cited by27 cases

This text of 71 N.W. 466 (Smalley v. Northwestern Terra-Cotta Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smalley v. Northwestern Terra-Cotta Co., 71 N.W. 466, 113 Mich. 141, 1897 Mich. LEXIS 739 (Mich. 1897).

Opinion

Moore, J.

The defendant Schmidt, the owner of land in Detroit, in the spring of 1895, contracted with Mr. Gearing, a building contractor, for the erection of a business block théreon. In the fall of 1895, when the building was partially completed, a number of material [143]*143men filed liens against the lot and building for materials which they severally claimed to have furnished to Mr. Gearing. The original bill of complaint in this cause was filed in January, 1896, for the enforcement of one of these liens, and the other lien claimants and the defendant Schmidt, as owner of the land and building, were made defendants. On March 17, 1896, the defendant the Northwestern Terra-Cotta Company, one of the lien claimants, filed an answer in the nature of a cross-bill, praying for the enforcement of its lien, which was filed on the 14th day of November, 1895. To this answer, in so far as it claims the benefit of a cross-bill, the defendant Schmidt filed a general demurrer on the 19th day of March, 1896. On Januai’y 2, 1897, the court sustained the demurrer, upon the ground that the answer failed to show that any copy of the statement of lien filed with the register of deeds was served upon the defendant Schmidt, and that it failed to show that any proof of service of a copy of that statement upon said defendant Schmidt was filed in the office of the register of deeds before the institution of proceedings to enforce the lien. The order gave leave to amend. Upon the same day an amended answer was filed, setting up the service of a copy of the statement upon Schmidt on the 22d day of November, 1895, and averring that on the 11th day of December, 1896, proof of that service by affidavit was filed in the office of the register of deeds. Immediately upon the filing of this amended answer, a demurrer thereto was filed, setting up the following grounds of demurrer:

1. That the order permitting the filing of this amended answer in the nature of a cross-bill, and the filing thereof, were unauthorized and unwarranted by law, because the order itself was made and the amended bill was filed more than six months after the time when the statement of the lien of the Terra-Cotta Company was filed with the register of deeds.
2. Because the proof of service of said statement of lien upon the defendant Schmidt, as averred in said amended [144]*144answer in the nature of a cross-bill, was filed with the register of deeds more than six months after the time when the statement of lien was filed, and after the filing of the original answer in the nature of a cross-bill for the enforcement of said lien.
3. Because the court had no power, under an answer in the nature of a cross-bill, to grant to the defendant filing such answer any relief against a co-defendant or against the property of such co-defendant.

Upon the same day, January 22, 1897, this demurrer was sustained, and the amended answer in the nature of a cross-bill, in so far as it claims the benefit of a cross-bill against the defendant Schmidt and his property, was dismissed. From this order the Terra-Cotta Company takes the present appeal. No demurrer or other objection was filed by any other person than defendant Schmidt to this answer in the nature of a cross-bill.

It is the claim of appellee Schmidt that the law makes the following things necessary conditions precedent to the taking of proceedings for the enforcement of a lien by any person not contracting directly with the owner:

1. Filing with the register of deeds a statement of lien within 60 days after the last furnishing of labor or material.
2. Service upon the owner or his agent, personally, of a copy of the statement within 10 days after the filing, or, if neither owner nor agent can be found within the county, service by posting on the premises within 5 days more.
3. Filing proof of such service with the register of deeds before the commencement of proceedings to enforce the lien.

He contends that, as the taking of these steps is made by the statute prerequisite to the enforcement of the lien, the performance and the averment of performance of each of them are necessary allegations in any bill to enforce such a lien, and that, as an original bill could not be filed for that purpose more than six months after the lien was filed, neither could a bill filed within six months, but omitting any ■ of these necessary allegations, be . so amended as to include them after the six months had ex[145]*145pired. It will be observed that the amended answer shows that all these conditions were performed, except the filing of the proof of the service of the notice with the register of deeds, before the commencement of the proceedings to enforce the lien. The question, then, is whether, when all the steps to establish a lien have been taken, except the filing with the register of deeds of proof of service of the statement of lien on the owner before commencing proceedings to enforce the lien, the proceedings must fail.

It is the contention of the appellee that, as this is a proceeding in derogation of the common law, the statute must be strictly construed, and, as the pleadings do not show a compliance with the law, the proceeding must fail. It is admitted on the part of the appellant that, as to all those requirements of the statute necessary to create the lien, the statute is mandatory, and must be followed; but it is claimed that, after the lien is once established, its provisions are directory, and that if such steps are taken as fully protect the owner, as in this instance, by giving him notice of the claim within the time fixed by statute, he is not harmed, and cannot complain.

It has long been the settled law in this State that these proceedings are purely statutory, and that, to create a lien under them, the statute must be followed in all its essentials. Wagar v. Briscoe, 38 Mich. 587; Peninsular General Electric Co. v. Norris, 100 Mich. 496; Hannah & Lay Mercantile Co. v. Mosser, 105 Mich. 18. In the case of Sheridan v. Cameron, 65 Mich. 680, which was a proceeding to enforce a mechanic’s lien, where the proceedings were attacked on the ground that they were prosecuted too late and irregularly, the petition was filed within the 60 .days allowed by statute, but it did not contain a prayer for process. The notice of lis pendens was filed after the 60 days expired. It was claimed that for these reasons the proceeding must fail. In discussing the case, Justice Campbell said:

[146]*146“The plea does not set up a failure to file notice of lis pendens as a defense, and it is not, therefore, in issue; but, taking the whole statute together, it seems that its chief purpose is to bind subsequent interests, and to serve the same purpose as notices of lis pendens under the general chancery practice. At all events, no other purpose is indicated on the face of the statute, and it hardly seems necessary as against the original parties to the bill, unless, possibly, during the interval before service of process or other • notice to come in. * * * The claim made that the lien law is to be rigidly construed is not correct, in- the full extent claimed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams & Works, Inc. v. Springfield Corp.
257 N.W.2d 160 (Michigan Court of Appeals, 1977)
Spartan Asphalt Paving Co. v. Grand Ledge Mobile Home Park
253 N.W.2d 646 (Michigan Supreme Court, 1977)
William Moors, Inc. v. Pine Lake Shopping Center, Inc.
253 N.W.2d 652 (Michigan Court of Appeals, 1977)
Spartan Asphalt Paving Co. v. Grand Ledge Mobile Home Park
247 N.W.2d 589 (Michigan Court of Appeals, 1976)
Burton Drywall, Inc. v. Kaufman
244 N.W.2d 367 (Michigan Court of Appeals, 1976)
J Altman Companies, Inc. v. Saginaw Plumbing and Heating Supply Co.
202 N.W.2d 707 (Michigan Court of Appeals, 1972)
Mohawk Lumber & Supply Co. v. Petix
84 N.W.2d 467 (Michigan Supreme Court, 1957)
Webster v. Cooper Development Co.
254 N.W. 186 (Michigan Supreme Court, 1934)
Hart v. Reid
219 N.W. 692 (Michigan Supreme Court, 1928)
Washtenaw Lumber Co. v. Belding
208 N.W. 152 (Michigan Supreme Court, 1926)
Whitehead & Kales Co. v. Taan
208 N.W. 148 (Michigan Supreme Court, 1926)
Martin v. Trautz
187 N.W. 370 (Michigan Supreme Court, 1922)
International Mill & Timber Co. v. Kensington Heights Homes Co.
183 N.W. 793 (Michigan Supreme Court, 1921)
Acme Lumber Co. v. Modern Construction Co.
183 N.W. 192 (Michigan Supreme Court, 1921)
Boomer v. Shewitz
178 N.W. 707 (Michigan Supreme Court, 1920)
Carland v. United Engineering Co.
176 N.W. 564 (Michigan Supreme Court, 1920)
Zilz v. Wilcox
157 N.W. 77 (Michigan Supreme Court, 1916)
Central Trust Co. v. George Lueders & Co.
221 F. 829 (Sixth Circuit, 1915)
Brown v. Detroit United Railway
146 N.W. 278 (Michigan Supreme Court, 1914)
Godfrey Lumber Co. v. Kline
133 N.W. 528 (Michigan Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
71 N.W. 466, 113 Mich. 141, 1897 Mich. LEXIS 739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smalley-v-northwestern-terra-cotta-co-mich-1897.