Zilz v. Wilcox

157 N.W. 77, 190 Mich. 486, 1916 Mich. LEXIS 894
CourtMichigan Supreme Court
DecidedMarch 30, 1916
DocketDocket No. 133
StatusPublished
Cited by7 cases

This text of 157 N.W. 77 (Zilz v. Wilcox) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zilz v. Wilcox, 157 N.W. 77, 190 Mich. 486, 1916 Mich. LEXIS 894 (Mich. 1916).

Opinion

Steeee, J.

Defendant Mary Wilcox appeals from a decree of the Wayne county circuit court in chancery adjudicating a lien upon a lot in the city of Detroit, belonging to her, in favor of complainant, Zilz, in the sum of $409.50, and of cross-complainant, Mohr, in the sum of $113.33, for labor and material done and furnished in the construction of a building upon said lot.

In 1911 defendant Wilcox decided to erect a two-, family flat building upon said lot, and, not being a resident of Detroit, engaged her sister, Mrs. Williams, [488]*488who resided there, to act as her agent, giving Mrs. ■Williams a power of attorney'to contract in her name and represent her generally in the project. Mrs. Williams entered into an oral contract with defendants Huth, who were general contractors doing business under the firm name of Huth & Son, to erect the desired building. Complainant, Zilz, had a subcontract with Huth & Son for the masonwork in said building, and Mohr for the plumbing. None of the contracts involved in this inquiry was in writing.

In the negotiations between Mrs. Williams and Huth & Son, William Huth submitted to her plans for a frame duplex house which he was proposing to build for other parties at a cost of $3,000, and it is her contention that their contract was to build a house for Mrs. Wilcox like the plans submitted for $4,500, except that it was to be brick veneer and without a bay window as shown in those plans. She testified that Huth promised to take the plans of the frame building and work them over (to show a duplex house in accordance with their agreement and later submit them to her, but the plans which he finally submitted after the work had progressed for some time differed materially from those shown her when the contract was entered into.

Huth & Son soon entered upon the performance of their contract, having sublet the masonwork to Zilz for $1,140, and the plumbing and gas-fitting to Mohr for $325. These subcontractors were governed by plans and specifications furnished by the principal contractors with whom they dealt and under whose supervision they did work and furnished material. They had no business relations with Mrs. Williams and she did not assume any authority over them, although she was daily upon the premises as the representative of Mrs. Wilcox watching the work as it progressed, and made payments to the principal contractors from time to time, amounting to about $1,500, who, however, [489]*489never furnished her any sworn statement of laborers, subcontractors, materialmen, etc., as provided for under the mechanic’s lien law (3 Comp. Laws 1915, § 14800). After the building had progressed until the basement was practically completed and ready for the superstructure, Huth & Son quit their contract without paying their subcontractors for work then done. They make no defense in this case, and neither do they appear as witnesses. Both of these subcontractors performed their contracts with labor and material so far as accompanying construction of the building would permit, but, when the principal contractors stopped and abandoned it, they could go no further, and, being unable to otherwise collect pay for what- they had already done, filed liens upon the premises.

Defendant Mary Wilcox contends that the decree appealed from is erroneous for the following reasons:

“1. The court had no jurisdiction to .grant a lien in favor of complainant or cross-complainant because: (1) The bill shows that the statement was not filed within 60 days as required by the statute; (2) was not properly verified; (3) not filed within the time limited; (4) not served on the owner; (5) and no proper substituted service was made by cross-complainant.
“2. There was a fatal variance between the allegations in the bill and the proofs, in that the bill alleged a contract for the foundation of the building only and the proofs disclosed a contract for the whole job.
“3. Neither lienor was entitled to a lien on the grounds that (1) neither complainant, nor (2) cross-complainant had completed his contract.
“4. Fraud was practiced upon the owner by the principal contractor and the subcontractor in that: (1) they were in collusion; (2) and practiced fraud on the owner; and (3) the owner received a substantially different building from what she contracted for.
“5. The defendant was entitled to file a supplemental bill to introduce a defense arising subsequent to the entry of the decree.”

[490]*490We find no error in the denial of defendant’s petition for leave to file a supplemental bill. The petition was filed long after defendant had given notice of appeal from the decree rendered by the trial court, and no appeal was taken from the order denying such petition. If that order were properly here for review, we see no occasion to disturb the discretion of the court in denying the petition.

Neither do we find any substantial support in the testimony for defendant’s contention that the subcontractor in collusion with the principal contractor perpetrated a fraud upon her by which she received a substantially different building from that she contracted for. While Mrs. Williams’ evidence is to the effect that the plans Huth & Son adopted varied in certain particulars from those shown her when they contracted and as a result the building finally completed upon the property was but 47 feet long instead of 55, the excavation for the basement was lengthened on her insistence to 55 feet, and she testified that she was at the building several times every day while the work was in progress, looking after it. Neither she nor defendant found any fault with the work of the subcontractors, and Mrs. Wilcox testified that after she found the building had been shortened she wanted Huth & Son to go ahead and finish it at the contract price. Whatever may be contended as to the conduct of the principal contractors, we discover no foundation for the charge that the subcontractors were guilty of any fraudulent or dishonest conduct.

Under the undisputed facts there is no force in defendant’s third contention that neither of the lienors is entitled to enforce his lien because he did not complete his subcontract.

“It is well established as a general rule that the failure of the principal contractor to complete his contract does not of itself defeat the right of the subcon[491]*491tractor, workman, or materialman to a lien.” 27 Cyc. p. 100.

They are entitled to protection for what they have done or furnished under the contract. Delray Lumber Co. v. Keohane, 132 Mich. 18 (92 N. W. 489).

Defendant’s contention that the court had no jurisdiction to grant a lien because of defective service is clearly well founded as to cross-complainant Mohr. Section 6 of the lien law (section 10715, 3 Comp. Laws; '3 Comp. Laws 1915, § 14803) expressly provides that in cases of this nature the person filing a lien “shall, within ten days * * * thereof, serve on the owner, * * * or in case of his absence from the county, on his agent having in charge of such premises within the county * * * a copy of such statement or claim.” Only jn case neither can be found in the county within the ten days can a substituted service be had by posting the copy in a conspicuous place on the premises.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Moors, Inc. v. Pine Lake Shopping Center, Inc.
253 N.W.2d 652 (Michigan Court of Appeals, 1977)
Spartan Asphalt Paving Co. v. Grand Ledge Mobile Home Park
247 N.W.2d 589 (Michigan Court of Appeals, 1976)
Hatten v. City of Houston
373 S.W.2d 525 (Court of Appeals of Texas, 1963)
Sacchetti v. Recreation Co.
7 N.W.2d 265 (Michigan Supreme Court, 1943)
Bezold v. Beach Development Co.
244 N.W. 204 (Michigan Supreme Court, 1932)
Martin v. Trautz
187 N.W. 370 (Michigan Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
157 N.W. 77, 190 Mich. 486, 1916 Mich. LEXIS 894, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zilz-v-wilcox-mich-1916.