Delray Lumber Co. v. Keohane

92 N.W. 489, 132 Mich. 17, 1902 Mich. LEXIS 540
Michigan Supreme Court·Decided December 16, 1902·No. Docket No. 99·Published·Cited by 7 cases

Opinion

Carpenter, J.

This is a chancery suit to enforce two mechanics’ liens against the property of the first-named defendant. The first-named complainant claims a lien by reason of lumber furnished in the construction of a house for the defendant Keohane. The other two complainants are partners doing business under the firm name of Hugg & Oltz. They claim a lien for the balance unpaid on a contract to do the masonwork on said house, and for labor performed in lathing said house. The court below decreed the enforcement of these claims at their full amount. [19] Defendant Keohane appeals. She claims that the decree should be reversed on two grounds: First, that the property in question was the homestead of defendant Keohane, and that, as the complainants’ contracts were verbal, it is not subject to the lien’s asserted by them; second, that complainants are not entitled to payment in full for the amount of their claims. A discussion of the questions raised by these claims will review every question presented by the record. .

1. Was the property a homestead? When the complainants’ liens attached, the property was unoccupied. If, therefore, defendant resided on other property owned by her, she could not claim a homestead in the property in question. McMonegal v. Wilson, 103 Mich., at page 268 (61 N. W. 495). Defendant testified that, when the house was built, she lived on Lansing avenue, Detroit, part of the time, and boarded part of the time; that she did not own the house in which she lived, and at that time owned no other property in Detroit than that involved in this suit. Complainants put in evidence a deed executed July 18, 1901 (this was after complainants’ liens had attached), from defendant Keohane to Thomas Gaffney and wife, conveying lot 31 of P. Williams’ subdivision of private claim 31, fronting on Lansing avenue. When this testimony was introduced, complainants’ counsel stated:

“The testimony shows she was living on Lansing avenue, and that she did not own the house. I will produce further proof of that.”

No further proof was produced either by complainants or by defendant.

The trial judge, in his decision,, stated:

“I find, also, * * * that this was not the homestead of the defendant at the time the liens were filed. Indeed, she had another and separate homestead.”

It must be admitted that the evidence respecting the homestead was left in an unsatisfactory state. It is difficult to understand why complainants’ counsel did not [20] carry out his proposed plan, which was, as we understand, to prove that defendant resided on the land subsequently conveyed to Gaffney. On the other hand, it is even more difficult to understand why, if this land was not that on which defendant lived, she did not, as she surely could, prove that fact. If this condition of the record did not furnish affirmative testimony that defendant resided on the land subsequently sold to Gaffney, it certainly did justify the trial judge in discrediting, as he did,'defendant Keohane’s testimony that she did not own the house in which she lived. This decision we will not disturb.

2. Are complainants entitled to payment in full ? Defendant James Scheel was the principal contractor. The contract price was $1,100. About June 1, 1901, and after $550 had been paid him, Scheel abandoned his contract, leaving the building incomplete. Of the amount so paid, Scheel had paid out to laborers and materialmen $405.02, though this had not been distributed as required by the principles announced in Fairbairn v. Moody, 116 Mich. 65 (75 N. W. 469), and Smalley v. Gearing, 121 Mich. 190 (79 N. W. 1114, 80 N. W. 797). At that time he owed the first-named complainant $312.50, the amount of its claim .asserted in this case, for material used in the building. He also owed the other complainants, Messrs. Hugg & Oltz, but just how much it is impossible, by this record, to state; and the building at that time was very far from completion. After this abandonment, defendant Keohane proceeded and completed the building at an additional expenditure of $1,016.35. The complainants insist that the rule for determining the" amount of claims announced in Fairbairn v. Moody, 116 Mich. 65 (75 N. W. 469), and Smalley v. Gearing, 121 Mich. 190 (79 N. W. 1114, 80 N. W. 797), should not be applied, for two reasons: First, themontract between Keohane and Scheel was so vague and indefinite that it must be disregarded; second, defendant Keohane, in completing her house, made a different house from that contemplated by the original contract, and thereby waived all rights under said contract.

[21] There is no merit in the first contention. While the contract is informal, its meaning is made sufficiently clear by the accompanying plans and specifications.

In completing the house after the abandonment by defendant Scheel, defendant Keohane did make some changes in the original contract, which obtained for her a house, as she stated, “a little better” than was originally contemplated. These changes, however, were simply such changes as an owner, in good faith, not infrequently makes during the process of construction. For instance, a window was extended out; grills were put in; inside woodwork was filled and oiled, when the specifications called for three coats of paint; bevel plate glass was put in the front door, when the specifications required No. 1 glass. Surely, these changes do not justify a disregard of the principles of the case of Smalley v. Gearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Delray Lumber Co. v. Keohane, 92 N.W. 489, 132 Mich. 17, 1902 Mich. LEXIS 540 (Mich. 1902).

92 N.W. 489 (Delray Lumber Co. v. Keohane) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chapel State Theatre Co. v. Hooper
175 N.E. 450 (Ohio Supreme Court, 1931)
Lazenby v. Wright
229 N.W. 437 (Michigan Supreme Court, 1930)
Cosden v. E. E. Paul Co.
196 A.D. 68 (Appellate Division of the Supreme Court of New York, 1921)
Zilz v. Wilcox
157 N.W. 77 (Michigan Supreme Court, 1916)
Frohlich v. Ashton
123 N.W. 1130 (Michigan Supreme Court, 1909)
Godfrey Lumber Co. v. Cole
114 N.W. 1018 (Michigan Supreme Court, 1908)
Kotcher v. Perrin
113 N.W. 284 (Michigan Supreme Court, 1907)