Sacchetti v. Recreation Co.

7 N.W.2d 265, 304 Mich. 185, 1943 Mich. LEXIS 434
CourtMichigan Supreme Court
DecidedJanuary 4, 1943
DocketDocket No. 48, Calendar No. 41,957.
StatusPublished
Cited by8 cases

This text of 7 N.W.2d 265 (Sacchetti v. Recreation Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sacchetti v. Recreation Co., 7 N.W.2d 265, 304 Mich. 185, 1943 Mich. LEXIS 434 (Mich. 1943).

Opinion

Boyles, C. J.

Bill of complaint was filed in the circuit court for Dickinson county to obtain an accounting on a certain contract, and to enforce an alleged material and labor lien, under 3 Comp. Laws 1929, § 13101 et seq. (Stat. Ann. § 26.281 et seq.). (Subsequent amendment by Act No. 266, Pub. Acts 1941 [Comp. Laws Supp. 1942, § 13101 et seq., Stat. Ann. 1942 Cum. Supp. § 26.281 et seg.], .has no application to the case at bar.)

The bill of complaint alleges that the defendant was the owner of certain vacant lots in Iron Mountain, Dickinson county; that in 1939 defendant contracted for plaintiff to excavate on said land for a foundation and to build new basement walls and a concrete floor, for $1,500; that after plaintiff had partly completed the work defendant stopped the work and entered into a new contract for plaintiff to enlarge the excavation to include additional property, build foundation walls and concrete floors, and *188 set wood joists according to certain blueprints, for $1,700, plus payment for what work had already been done’. Plaintiff claims that after part performance he was again prevented from completion by defendant, that the work was completed by a third party and accepted by defendant, and that plaintiff had fully performed his contract until prevented. The bill alleges that plaintiff gave defendant a statement under oath pursuant to statute, to comply with 3 Comp. Laws' 1929, § 13104 (Stat. Ann. § 26.284), that he filed a statement of account and the amount due him, with the register of deeds, that the amount due him is $1,084.85, and the bill seeks foreclosure of a lien on defendant’s land for that amount. Defendant answered, denied the material allegations of the bill, claimed that the plaintiff had abandoned .the job, denied that the statement of lien complied with the statute or that it had been filed in the office of the register of deeds within 60 days after the last of the labor had been performed or materials furnished. Defendant also filed a cross bill asking for damages for plaintiff’s failure to perform his contract, and set up as a special defense that plaintiff had failed to comply with the statute in furnishing the statement and filing a statement of lien.

At the conclusion of the trial the circuit judge dictated an opinion analyzing the testimony and after discussing the various claims and counterclaims concluded that a balance of $299.55, plus $15 interest, was due plaintiff, “and the plaintiff will be held to have established a lien for that amount.” Decree was entered for plaintiff in the amount of $314.55, giving plaintiff a lien on the premises as described, “in accordance with the statute in like case provided.” The decree contains the usual provisions for sale of the land by circuit court commis *189 sioner at public sale in event of nonpayment, deed to tbe purchaser, period of redemption, and disposal of surplus, if any, from sale.

On appeal, defendant insists that the claim of lien was not filed in time to satisfy the statute, that the statement of lien was grossly and intentionally excessive and incorrect, and that the court erred in his findings as to the amount due. Appellee has not filed a brief in this court.

It is conceded that plaintiff had a contract to excavate, build walls and a cement floor or bed for bowling alleys for the defendant. Plaintiff started work in November, 1939, and had performed to the extent of $285 when the second contract increased the amount of work and the contract price was raised to $1,700. Plaintiff continued work'in December and testified that the defendant moved sand, brick and other material into the basement so he could not complete the work without moving it out, that defendant refused to move it, that plaintiff waited a month or more, and that on January 23d he wrote defendant that he was waiting for notice to complete the job. Defendant, claiming that the plaintiff abandoned his contract, went ahead and had some other contractor complete the work. Plaintiff claims that after the floor was laid he finished his work, pointed up the wall,' put the joists in place on March 7, 8, 9, 1940. The sworn statement and claim of lien was filed and served on May 7th. Subsequently (June 1st) plaintiff admitted an error in the statement, amounting 'to $11.25, by the inadvertent omission of an item for some used blocks that he had not put on his books.

There was a sharp issue of fact whether plaintiff abandoned the work, or was forced to discontinue by acts of the defendant. The record is plain that plaintiff waited for some time to complete the work, *190 and performed essential services on March 7, 8, 9, 1940, toward completing his .contract. The statement and claim of lien filed and served May 7th was within the statutory period of 60 days from the date on which the last of the materials were furnished and tfie last of the labor performed. The evidence is sufficient to sustain the finding of the circuit judge that the work done on March 7th, 8th and 9th was a necessary part of the contract and done in good faith. Zils v. Wilcox, 190 Mich. 486. A question of fact was raised and the testimony supports the finding.

“Whether labor and material furnished within the statutory period but after the contract had been substantially completed were in good faith and for the purpose of completing the contract, or colorably to revive the lien is a question of fact. Turner v. Wentworth, 119 Mass. 459.” Neely v. International Corn Products Corp., 232 Mich. 81, 86.

See, also, Vander Horst v. Kalamazoo Apartments Corp., 239 Mich. 593.

Plaintiff claimed he was entitled to a decree for $1,084.85, the balance of $1,700-due and owing on the contract, on the ground.that defendant had wrongfully prevented its completion. The defendant claimed abandonment of contract, asserted a claim of $300 for offset; recoupment of damages for delay, $3,000; for improper performance, $500; payment in excess of work actually performed; other bills contracted, $109.74. All this was denied by plaintiff in reply. The proofs as to these various claims and counterclaims are in direct conflict and the record bears out the comment of the circuit judge:

“You well know it is impossible for me to harmonize the testimony here. * * * There appeared enough exaggeration to render it difficult for the court to get at the actual facts.”

*191 A cross bill may be maintained to recoup for damages caused by failure to complete contract, since a court of equity has" jurisdiction to settle all disputes relating to the same subject matter between tbe parties to the suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Minnesota v. Jonathan Lamont Davis
Court of Appeals of Minnesota, 2015
Tempo, Inc v. Rapid Electric Sales & Service, Inc
347 N.W.2d 728 (Michigan Court of Appeals, 1984)
J Propes Electric Co. v. DeWitt-Newton, Inc.
293 N.W.2d 801 (Michigan Court of Appeals, 1980)
Georgia-Pacific Corp. v. Central Park North Co.
228 N.W.2d 380 (Michigan Supreme Court, 1975)
G. O. Lewis Co. v. Erving
145 N.W.2d 368 (Michigan Court of Appeals, 1966)
Priddy v. KERNERSVILLE LUMBER COMPANY
129 S.E.2d 256 (Supreme Court of North Carolina, 1963)
E. S. Gaynor Lumber Co. v. Morrison
60 N.W.2d 83 (South Dakota Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
7 N.W.2d 265, 304 Mich. 185, 1943 Mich. LEXIS 434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sacchetti-v-recreation-co-mich-1943.