Vugterveen Systems, Inc. v. Olde Millpond Corp.

533 N.W.2d 320, 210 Mich. App. 34, 1995 WL 242045
CourtMichigan Court of Appeals
DecidedApril 21, 1995
DocketDocket 154137
StatusPublished
Cited by7 cases

This text of 533 N.W.2d 320 (Vugterveen Systems, Inc. v. Olde Millpond Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vugterveen Systems, Inc. v. Olde Millpond Corp., 533 N.W.2d 320, 210 Mich. App. 34, 1995 WL 242045 (Mich. Ct. App. 1995).

Opinion

Marilyn Kelly, J.

Defendant, Olde Millpond Corporation, appeals as of right from a circuit court judgment attaching liens in favor of plaintiff, Vugterveen Systems, Inc., and cross-plaintiff, Erb *37 Lumber Company. We affirm but instruct the court to modify the amount of the liens.

i

Olde Millpond Corporation was the developer of a condominium project. Charles Hornbach, president of Olde Millpond, initiated the project in 1986. In 1988, he contracted with VanderWall Construction, Inc., to act as general contractor. Subsequently, VanderWall subcontracted with Vugterveen to do the drywall work in the project. Vugterveen installed drywall in two of the buildings, each containing two residential units. Erb provided the lumber for the project.

Vugterveen worked on the two buildings under separate agreements. The contract price for the first building was $11,600, which Olde Millpond paid in full. Vugterveen signed a waiver of lien for that building. It agreed to drywall the two units in the second building for $9,750 but stopped work for lack of payment before completing them. Vugterveen recorded a construction lien in the amount of $7,800 for the unpaid work it had done.

Erb furnished lumber for both buildings pursuant to a builder sales agreement with VanderWall. After requesting a copy of Olde Millpond’s notice of commencement from VanderWall on May 31, 1988, Erb filled out a notice of furnishing lumber. It stated that the material was being furnished to VanderWall for the "construction of 4338/4333 Olde Millpond Drive in connection with the improvement of the real property described by the Notice of Commencement a copy of which is attached.” Erb sent a copy of the notice of furnishing to VanderWall and to Hornbach. The balance due on the account was $20,239.07.

Hornbach removed VanderWall from the job on *38 October 27, 1988. On December 30, 1988, Erb filed a claim of lien for $20,239.07 "plus accruing finance charges as of November 30, 1988.”

On December 5, 1989, Vugterveen filed a complaint for foreclosure of its construction lien against Olde Millpond. On December 18, 1989, Erb filed a counterclaim and cross-claim also seeking to have its construction lien foreclosed.

The case was heard in a three-day bench trial in September 1991. In an oral opinion issued March 9, 1992, the court ruled that Erb was entitled to a lien against both buildings in the amount of $7,300.84 plus interest, costs and attorney fees. Vugterveen was entitled to a lien for the balance due on the work it had completed and for attorney fees. Each sum represents a prorated share of the original construction lien amount, in accord with the trial judge’s decision to adopt the formula for proration set forth in Smalley v Gearing, 121 Mich 190; 79 NW 1114 (1899).

Olde Millpond raises ten issues on appeal. Cross-appellant, Erb, raises three.

ii

Olde Millpond asserts that the trial court erred in denying its motion for summary disposition. When the motion was heard, the judge suggested that, since the trial date was in two weeks and the issues complex, the case would be resolved faster if tried. The parties agreed. Therefore, the judge did not directly deny the motion.

It is unnecessary for this Court to review an issue on which no ruling was made. Richmond Twp v Erbes, 195 Mich App 210, 219; 489 NW2d 504 (1992). However, were we to review it, we would find no abuse of discretion. As the judge *39 observed, the issues in the case were complex and the trial was at hand. Trial presented the most efficient method to resolve the issues.

hi

Olde Millpond asserts that the notices of furnishing by Erb and Vugterveen were improper under the Construction Lien Act. MCL 570.1101 et seq.; MSA 26.316(101) et seq. The interpretation or construction of a statute is a question of law. Smeets v Genesee Co Clerk, 193 Mich App 628, 633; 484 NW2d 770 (1992). We review questions of law de novo. In re Lafayette Towers, 200 Mich App 269, 272; 503 NW2d 740 (1993).

The Construction Lien Act requires a supplier to provide a notice of furnishing to the designee named in the notice of commencement within twenty days after furnishing the first material. MCL 570.1109(1); MSA 26.316(109X1). However, failure to provide a notice of furnishing within the time specified does not

defeat the lien claimant’s right to a construction lien for work performed or materials furnished by the lien claimant before the service of the notice of furnishing except to the extent that payments were made by or on behalf of the owner or lessee to the contractor pursuant to either a contractor’s sworn statement or a waiver of lien in accordance with this act for work performed or material delivered by the lien claimant. [MCL 570.1109(6); MSA 26.316(109X6).]

Vugterveen’s notice of furnishing was late, but Olde Millpond conceded that Vugterveen was not paid. Vugterveen substantially complied with the statute. Its lien claim is not defeated by the untimeliness of its notice of furnishing.

*40 IV

Olde Millpond also contends that the claims of lien filed by Erb and Vugterveen were unenforceable because excessive in amount. However, it has been established that a lien is not lost because the amount claimed is excessive, unless the claim was made in bad faith. In such instances, the proper remedy is to reduce the amount of the lien to the correct amount. Tempo, Inc v Rapid Electric Sales & Service, Inc, 132 Mich App 93, 104; 347 NW2d 728 (1984). Erb’s error here appears to have been made in good faith. See Currier Lumber Co v Ruoff, 298 Mich 505; 299 NW 163 (1941). The trial court reduced the amount of Erb’s lien, correcting the error. Moreover, Olde Millpond received the intended benefit of a $5,000 payment made to Erb. It was not entitled to credit for another $5,000 payment which Erb misdirected. Finally, Vugterveen’s lien claim was supported by the evidence.

v

Olde Millpond also asserts that Erb and Vugterveen failed to prove the amount of their lien claims.

A lien claimant is required to prove by a preponderance of the evidence the amount claimed to be owing to a reasonable certainty. R & T Sheet Metal, Inc v Hospitality Motor Inns, Inc, 139 Mich App 249, 255; 361 NW2d 785 (1984). The record testimony supports Vugterveen’s claim. Moreover, the trial court determined the correct amount of Erb’s lien. Since the court’s finding on the amount of Erb’s lien was not clearly erroneous, we will not set it aside. Id., p 255.

vi

Olde Millpond contends that the trial court *41 erred in attaching Erb’s construction lien to all the residential condominium units rather than to the specific units for which materials were furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E R Zeiler Excavating, Inc v. Valenti Trobec Chandler Inc
717 N.W.2d 370 (Michigan Court of Appeals, 2006)
Vugterveen Systems, Inc. v. Olde Millpond Corp.
560 N.W.2d 43 (Michigan Supreme Court, 1997)
Wechsler v. Wayne County Road Commission
546 N.W.2d 690 (Michigan Court of Appeals, 1996)
Mitchell v. Dahlberg
547 N.W.2d 74 (Michigan Court of Appeals, 1996)
Welch Foods, Inc. v. Attorney General
540 N.W.2d 693 (Michigan Court of Appeals, 1995)
Northland Wheels Roller Skating Center, Inc v. Detroit Free Press, Inc
539 N.W.2d 774 (Michigan Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
533 N.W.2d 320, 210 Mich. App. 34, 1995 WL 242045, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vugterveen-systems-inc-v-olde-millpond-corp-michctapp-1995.