R & T Sheet Metal, Inc v. Hospitality Motor Inns, Inc

361 N.W.2d 785, 139 Mich. App. 249
CourtMichigan Court of Appeals
DecidedNovember 20, 1984
DocketDocket 71496
StatusPublished
Cited by14 cases

This text of 361 N.W.2d 785 (R & T Sheet Metal, Inc v. Hospitality Motor Inns, Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R & T Sheet Metal, Inc v. Hospitality Motor Inns, Inc, 361 N.W.2d 785, 139 Mich. App. 249 (Mich. Ct. App. 1984).

Opinion

Per Curiam.

Defendant Hospitality Motor Inns, Inc. (now Harley Hotels, Inc.), appeals as of right from an order of summary judgment holding that plaintiffs notice of intention to claim mechanics’ lien was timely served and from a judgment in favor of plaintiff in the amount of $15,389.43 due under the lien.

In August, 1977, Hospitality Motor Inns, Inc., contracted for Russo Ornamental Iron Products, Inc., to provide all labor, materials, equipment and supervision for the installation of metal work at five Hospitality Motor Inns under construction, *252 including one in Lansing, Michigan. On September 27, 1977, Russo subcontracted the work to plaintiff, R & T Sheet Metal, Inc.

On May 6, 1978, plaintiff delivered the necessary materials to the Lansing construction site for work to be done by plaintiff at a later date. Plaintiff commenced work at the Lansing site on June 5, 1978, and completed the project on or around August 15, 1978. Plaintiff filed a notice of intention to claim lien upon defendant on August 29, 1978.

Plaintiff and defendant brought cross-motions for summary judgment on the issue of whether plaintiff’s notice of intention to claim lien was timely served. The trial court granted summary judgment to plaintiff, holding that the notice was timely served and reserving the question of the amount of damages owed. Trial was subsequently held on the question of damages. The court found for plaintiff in the amount of $15,389.43.

I

Defendant first argues that the trial court incorrectly held that plaintiff’s notice of intention to claim lien was timely served.

The mechanics’ lien statute, MCL 570.1; MSA 26.281, 1 states in pertinent part:

"[A]nd every person who shall be subcontractor, * * * perform any labor or furnish materials * * * to such original or principal contractor * * * in carrying forward or completing any such contract, shall have a lien therefore upon such * * * building * * *: Provided, That any person, firm or corporation furnishing materials or performing labor of any kind entering into the construction of any such building * * * shall within 90 *253 days after furnishing the first of such material or performing the first of such labor * * * serve on the owner * * * or his agent * * * a written notice * * * as will inform the owner * * * that such person, firm or corporation furnishing materials or performing labor will claim a lien upon such premises for any amounts unpaid for such materials so furnished or labor performed * * *.”

The trial court found that the 90-day notice limitation period began to run when the materials were first incorporated into the building, not when they were first delivered to the job site, and, therefore, plaintiffs notice was timely served. We affirm the trial court’s ruling that plaintiffs notice was timely. The grounds for our decision, however, are different than those relied upon by the trial court.

The issue here is one of statutory construction. The notice provision in MCL 570.1; MSA 26.281 states that the notice of intent to claim lien shall be given "within 90 days after furnishing the first of such materials or performing the first of such labor”. (Emphasis added.) In construing this statutory provision, we are governed by traditional rules of construction:

"[I]f the statute is unambiguous on its face, we will avoid further interpretation or construction of its terms. Detroit v Redford Twp, 253 Mich 453; 235 NW 217 (1931). However, if ambiguity exists, it is our duty to give effect to the intention of the Legislature in enacting the statute. Melia v Employment Security Comm, 346 Mich 544; 78 NW2d 273 (1956). To resolve a perceived ambiguity, a court will look to the object of the statute, the evil or mischief which it is designed to remedy, and will apply a reasonable construction which best accomplishes the statute’s purpose. Bennetts v State Employees Retirement Board, 95 Mich App 616; 291 NW2d 147 (1980), Stover v Retirement Board of St Clair Shores, 78 Mich App 409; 260 NW2d 112 (1977). Also, ambiguous statutes will be interpreted as a whole *254 and construed so as to give effect to each provision and to produce an harmonious and consistent result. In re Petition of State Highway Comm, 383 Mich 709; 178 NW2d 923 (1970), People v Miller, 78 Mich App 336; 259 NW2d 877 (1977). Further, specific words in a given statute will be assigned their ordinary meaning unless a different interpretation is indicated. Oshtemo Twp v Kalamazoo, 77 Mich App 33, 39; 257 NW2d 260 (1977), MCL 8.3a; MSA 2.212(1).” Pittsfield Twp v City of Saline, 103 Mich App 99, 104-105; 302 NW2d 608 (1981).

Section 27 of the mechanics’ lien act declares that the act is a remedial statute intended to benefit and protect subcontractors, materialmen, and laborers and should be construed liberally in order to carry out the intent of the Legislature. MCL 570.27; MSA 26.307. Georgia-Pacific Corp v Central Park North Co, 394 Mich 59, 66; 228 NW2d 380 (1975).

The disjunctive "or” recognizes two distinct events which trigger the 90-day limitations period, depending on whether the lien is being claimed for materials or labor. Plaintiffs claim herein is for labor performed. All parties agree that plaintiff had been paid for the materials and their fabrication prior to delivery of the materials to the various job sites. Therefore, upon delivery of the materials to the job sites, plaintiff was not entitled to claim a lien and had absolutely no reason to do so. It was only after plaintiff had completed labor on four of the jobs, and had not been paid for the labor performed on the fifth (Lansing) job site, that plaintiff could and did file a lien claim. To hold, as defendant urges, that plaintiff is precluded from claiming a lien because it did not file notice at a time when it had no right or reason to do so is illogical and violates the act’s remedial purpose.

Plaintiffs lien is claimed solely for labor performed. Since notice was served within 90 days *255 after "performing the first of such labor”, the notice was timely served.

II

It was undisputed that plaintiff fully performed its contract for the fabrication, production and installation of certain materials at the Lansing construction site. The trial court found that the amount owed to plaintiff was $15,389.43. Defendant claims that insufficient evidence was introduced to establish the amount owed with reasonable certainty. This Court will not set aside the trial court’s finding unless it was clearly erroneous. Detroit Independent Sprinkler Co v Plywood Products Corp, 311 Mich 226, 230; 18 NW2d 387 (1945); Loranger v Citizens Mutual Ins Co, 100 Mich App 681, 684; 300 NW2d 369 (1980).

Plaintiff was required to prove by a preponderance of the evidence the sum claimed owing to a reasonable certainty. Wheelmakers, Inc v Flint,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vugterveen Systems, Inc. v. Olde Millpond Corp.
533 N.W.2d 320 (Michigan Court of Appeals, 1995)
Gebhardt v. O'ROURKE
510 N.W.2d 900 (Michigan Supreme Court, 1994)
People v. Freybler
434 N.W.2d 187 (Michigan Court of Appeals, 1988)
Fortune v. Crime Victims Compensation Board
426 N.W.2d 773 (Michigan Court of Appeals, 1988)
Central Advertising Co. v. Department of Transportation
413 N.W.2d 479 (Michigan Court of Appeals, 1987)
Hagen v. Department of Education
398 N.W.2d 485 (Michigan Court of Appeals, 1986)
Santia v. Board of State Canvassers
391 N.W.2d 504 (Michigan Court of Appeals, 1986)
Hinton v. Parole Board
383 N.W.2d 626 (Michigan Court of Appeals, 1986)
In Re Spencer Estate
383 N.W.2d 266 (Michigan Court of Appeals, 1985)
Mich. Mut. Ins. Co. v. Allstate Ins. Co.
382 N.W.2d 169 (Michigan Court of Appeals, 1985)
Michigan Mutual Insurance v. Allstate Insurance
382 N.W.2d 169 (Michigan Court of Appeals, 1985)
People v. Chatfield
372 N.W.2d 611 (Michigan Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
361 N.W.2d 785, 139 Mich. App. 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-t-sheet-metal-inc-v-hospitality-motor-inns-inc-michctapp-1984.