St John's College v. . &198tna Indemnity Co.

94 N.E. 994, 201 N.Y. 335, 1911 N.Y. LEXIS 1248
CourtNew York Court of Appeals
DecidedMarch 28, 1911
StatusPublished
Cited by34 cases

This text of 94 N.E. 994 (St John's College v. . &198tna Indemnity Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St John's College v. . &198tna Indemnity Co., 94 N.E. 994, 201 N.Y. 335, 1911 N.Y. LEXIS 1248 (N.Y. 1911).

Opinion

Chase, J.

The plaintiff, a domestic corporation, entered into a contract with John Maher & Son for the erection of a building on its college grounds for which it promised to pay $99,250. The contractors agreed to furnish the materials and *337 perform the work in accordance with the drawings and specifications made by an architect and signed by the parties and annexed to the contract.

As provided by the contract, the said contractors gave a bond to the plaintiff with the defendant as a surety in the penal sum of $20,000 upon condition “That if the said John Maher & Son shall well and truly do and perform all and singular the covenants and conditions in the said contract contained on their part to be done and performed then this obligation to be void otherwise to remain in full force and effect.”

The contractors proceeded with the execution of the contract, but after a part performance they wholly failed to further perform the contract and went into bankruptcy. Pursuant to a provision of the contract, the plaintiff proceeded to complete the same. This action is brought by the plaintiff against the defendant as the surety on said bond, alleging that the cost of completing said contract, including the payments made thereon to John Maher & Son pursuant to the terms of the contract before they abandoned the same, was $22,543.10 over and above the said contract price, and judgment was demanded against the defendant for $20,000. A trial was had and a verdict obtained in favor of the plaintiff against the defendant for $18,355.02. An appeal was taken from the judgment entered upon such verdict to the Appellate Division, where the same has been unanimously affirmed.

The pleadings, including an amendment to the complaint properly allowed by the court on motion of the plaintiff at the beginning of the trial, presented issues to be determined between the parties. The verdict of the jury thereon having been unanimously affirmed by the Appellate Division, there is riot now before us any question either as to the weight or probative force of the testimony. Many of the questions discussed by the counsel for the appellant involve, in whole or in part, questions of fact not now before us for determination, or even consideration. There is left for our consideration only questions arising from adverse rulings upon the admis *338 sion or exclusion of evidence to which an exception has been duly taken, or exceptions to erroneous charges or refusals to charge by the court in presenting the case to the jury.

The defendant objected to testimony being received to show that the plaintiff had paid to the contractors $1,000 and $1,226.05 respectively and to the same being allowed as payments on account of the cost of said building and such objections are sufficient to raise the question in this court as to whether such payments were properly allowed and also whether the making of such payments resulted in a general and complete cancellation, of the surety’s obligation.

The defendant also properly objected to the testimony relating to the first five payments made by the plaintiff to the contractors, and it is claimed by the defendant that such pay ments were not made in accordance with the terms of the contract because the certificate of the architect was not in accordance with the provisions thereof. Such questions, not including the objections to the testimony and exceptions taken to the rulings thereon, are shown by the following statements from the contract and the evidence:

By the contract it is provided that the consideration thereof as named is Payable in manner following: 80% of each $10,000.00 worth of work done, the last payment of $10,000.00 to be made 30 days after full completion and acceptance of the building. Provided that in each of the said cases a certificate shall be obtained from and signed by the said architect.”

On September 4, 1903, the architect gave a certificate as follows: “ This is to certify that John Maher & Son are entitled to first payment as per contract for new building for St. John’s College, Fordham, N. T. City, $8,000.00.” A similar certificate was given for the second payment, October 16,1903; for the third payment, November 20, 1903; for the fourth payment, December 7, 1903; and for the fifth payment, December 22, 1903. John Maher & Son were paid on said certificates by the plaintiff in the aggregate $40,000.

On the 9tli of January, 1904, the plaintiff paid John Maher *339 & Son $1,000. The treasurer of the corporation testified that he made the payment “ Upon the authority of the president of the corporation, to save the man from going to the wall, to try to save him. We knew at that time that he had a lot of work done, and he had written a letter showing his condition and the position of things at that time, and in order to save him from failing, in order that he might have money to pay his wages to his men, the president of the corporation authorized me to make the payment of a thousand dollars. * * * Q. Do you know of anything in the contract that authorized yon to make a payment under those circumstances ? A. It was simply to help the indemnity company. If we could save them from failing, we wanted to do it, because he had a lot of work done, and would be entitled to a thousand dollars in a few days.”

It also appears that on the 31st day of January, 1904, the plaintiff paid $1,226.05 to be used in payment of workmen of the contractors. The treasurer of the plaintiff testified: “ It was not on account of any particular payments under the contract; there were labor troubles, and we had to pay simply to save money, because in a similar case the city was obliged to pay double the price for the labor for keeping the men waiting for a few days. Q. Was this payment of $1,226.05 on account of any of .the payments provided for by the contract ? A. Specifically, no. * * * That was one of the things we were forced to do where we had very little discretion, but I did it under what I considered moral compulsion to pay the workmen.”

Both of these payments were allowed to the plaintiff and charged as payments made to John Maher & Son on account of the cost of said building, and were so taken into consideration by the jury in determining the amount of the verdict.

As we understand the argument of the defendant in opposing the allowance of all payments to the contractors, it is that the 'owner before making any payment to them should have received from the architect a certificate setting forth the amount of work done and materials furnished by the contractors, *340 to show in detail a basis for such certificate, and that without such statement included in or accompanying the certificate it does not comply with the terms of the contract or justify a payment thereon. We do not agree with such contention. We are not considering whether the form of the certificate given by the architect did not permit of guesses and even of fraud by him. The question now is simply whether the certificate given complies with the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mount Vernon City School District v. Nova Casualty Co.
968 N.E.2d 439 (New York Court of Appeals, 2012)
International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
Fireman's Fund Insurance v. United States
34 Cont. Cas. Fed. 75,538 (Court of Claims, 1988)
University Bank and Trust Co. v. Elaine D. Dunton
655 F.2d 23 (First Circuit, 1981)
Buffalo Slag Co. v. H & D Construction Co.
94 Misc. 2d 212 (New York Supreme Court, 1978)
Hunt v. Bankers & Shippers Insurance
60 A.D.2d 781 (Appellate Division of the Supreme Court of New York, 1977)
Schooley Enterprises, Inc. v. Paso Contracting Corp.
33 A.D.2d 981 (Appellate Division of the Supreme Court of New York, 1970)
Yanul v. City of New York
15 A.D.2d 828 (Appellate Division of the Supreme Court of New York, 1962)
McDonough v. Mancuso
234 A.D. 161 (Appellate Division of the Supreme Court of New York, 1931)
Peoples Bank of Hamburg v. C. L. Gates, Inc.
232 A.D. 328 (Appellate Division of the Supreme Court of New York, 1931)
In re Irving Trust Co.
136 Misc. 762 (New York Surrogate's Court, 1930)
George Colon & Co. v. Commercial Casualty Insurance
226 A.D. 525 (Appellate Division of the Supreme Court of New York, 1929)
Globe Indemnity Co. v. Southern Pac. Co.
30 F.2d 580 (Second Circuit, 1929)
Paxton v. Spencer
265 P. 751 (Utah Supreme Court, 1928)
Southern Pac. Co. v. Globe Indemnity Co.
21 F.2d 288 (Second Circuit, 1927)
Village of Canton v. Globe Indemnity Co.
201 A.D. 820 (Appellate Division of the Supreme Court of New York, 1922)
Sandusky Grain Co. v. Borden's Condensed Milk Co.
183 N.W. 218 (Michigan Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.E. 994, 201 N.Y. 335, 1911 N.Y. LEXIS 1248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-johns-college-v-198tna-indemnity-co-ny-1911.