Mount Vernon City School District v. Nova Casualty Co.

968 N.E.2d 439, 19 N.Y.3d 28
CourtNew York Court of Appeals
DecidedApril 3, 2012
StatusPublished
Cited by37 cases

This text of 968 N.E.2d 439 (Mount Vernon City School District v. Nova Casualty Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mount Vernon City School District v. Nova Casualty Co., 968 N.E.2d 439, 19 N.Y.3d 28 (N.Y. 2012).

Opinions

OPINION OF THE COURT

Ciparick, J.

On this appeal, we are called upon to determine whether defendant Nova Casualty Company (Nova) is discharged from its surety obligation to plaintiff Mount Vernon City School District (the School District) on the bases that the School District allegedly violated New York’s Lien Law by improperly diverting construction contract payments constituting trust fund assets to a nonbeneficiary and breached the terms of the parties’ performance bond. We hold that under the facts of this case, Nova has not demonstrated that discharge of its surety obligation is warranted. We also consider whether the School District is entitled to attorneys’ fees expended in the prosecution of this litigation, and conclude that the request for attorneys’ fees was properly denied.

L

On December 26, 2003, the School District and defendant DJH Mechanical Associates, Inc. (DJH) contracted for DJH to perform heating, ventilation and air conditioning (HVAC) work at A.B. Davis Middle School for a price of $919,000. The contract mandated that the School District make progress payments to DJH based upon DJH’s application for payment for work performed during the preceding calender month. The School District was permitted to terminate the contract if DJH, among other things, failed to furnish adequate assurance that DJH could complete the work.

The contract also required DJH to obtain a performance bond, which DJH secured from Nova, a compensated surety. The performance bond incorporates the terms of the underlying construction contract and provides that “[t]he Surety shall not [32]*32be liable to the Owner or others for obligations of the Contractor that are unrelated to the Construction Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations.”

As relevant to the School District’s cross appeal, the contract between the School District and DJH further provides:

“The costs of finishing the Work include, without limitation, all reasonable attorney’s fees, additional title costs, insurance, additional interest because of any delay in completing the Work, and all other direct and indirect and consequential damages incurred by the Owner by reason of the termination of the Contract as stated herein.”

The performance bond as it relates to legal costs provides that

“[t]o the limit of the amount of this Bond, but subject to commitment by the Owner of the Balance of the Contract Price to mitigation of costs and damages on the Construction Contract, the Surety is obligated without duplication for: . . .
“[ajdditional legal, design professional and delay costs resulting from the Contractor’s Default, and resulting from the actions or failure to act of the Surety.”

In June 2004, while the contract work was underway, the School District received a notice to withhold/release payment (notice of cross-withholding) from the Department of Labor (DOL). The notice stemmed from DOL’s investigation of alleged prevailing wage violations by DJH on a previously performed public works project1 and requested that the School District withhold $863,197.40 in contract payments pending completion of the investigation. A November 2004 application summary indicates that DJH had submitted nine applications for progress payments. In January 2005, DOL gave the School District notice that it could release $649,197.40 to DJH, but directed the School District to send the balance of $214,000 to DOL in satisfaction of DJH’s debt. The president of DJH signed a provision of the notice assigning to DOL $214,000 in earned progress payments. The School District subsequently remitted that amount to DOL. Work ostensibly progressed but at a very slow pace [33]*33and, in July 2006, the School District terminated its contract with DJH due to the contractor’s failure to substantially complete the HVAC work. When the School District turned to Nova to perform under the bond and fund the work left remaining upon DJH’s default, Nova disclaimed liability and refused to complete the project.

The School District commenced this breach of contract action against Nova, seeking damages for the cost of completing the project and also attorneys’ fees, and against DJH, seeking damages for its failure to complete the contracted-for work. DJH defaulted.

Nova answered and moved for summary judgment, arguing, among other things, that the School District violated article 3-A of the Lien Law2 by diverting $214,000 of trust fund assets reserved for completion of the HVAC work to satisfy debts incurred on the Mahopac project. Nova contended that but for the improper payment to DOL, the School District would have had sufficient funds to complete its HVAC project and Nova’s surety obligation would not have been triggered. Nova further alleged that the School District breached the performance bond by “illegally reducing the contract funds,” thereby discharging Nova from its duty to perform. In response, the School District admitted that it released $214,000 to DOL upon DJH’s [34]*34authorization, and. asked the court to search the record to grant it partial summary judgment on the issue of Nova’s liability.

Supreme Court declined to grant either party summary judgment. In denying Nova’s motion, the court observed that the instant case was distinguishable from Matter of RLI Ins. Co., Sur. Div. v New York State Dept. of Labor (97 NY2d 256 [2002]), where the surety had completed the project at issue and was therefore subrogated to the rights of article 3-A trust fund beneficiaries. The court stated that “if Nova had undertaken to complete DJH’s performance, it would have been subrogated to the rights of both Plaintiff and DJH, and if the $214,000.00 payment involved payment of underpaid wages on an unrelated job, Nova would have a claim against Plaintiff for improper diversion of trust assets” (30 Misc 3d 1231 [A], 2008 NY Slip Op 52725[U], *11 [2008]). As Nova did not complete DJH’s performance, it “therefore . . . has no right as a subrogee to unpaid contract . . . and trust fund monies” (id. at *13). The court determined that questions of fact remained as to whether the payment to DOL was an improper diversion of trust fund assets and whether the payment violated the bond by increasing Nova’s risk of liability.

Both Nova and the School District appealed, and Supreme Court ordered bifurcated trials. The liability phase was tried before a jury in March 2009. The jury returned a verdict in the School District’s favor, finding that DJH breached its contract with the School District by failing to complete its work and waived its right to terminate the contract.

The issues before Supreme Court post-trial were: (1) whether the School District’s $214,000 payment to DOL relieved Nova of liability under the performance bond and (2) whether the School District could recover attorneys’ fees for completing the project and prosecuting its claim in this litigation. Supreme Court held that the School District’s payment to DOL did not excuse Nova’s performance under the bond. The court again emphasized that Nova had not completed performance, and thus had “no right as a subrogee to [the] unpaid Contract Price or any Trust Fund monies that were wrongfully diverted” (30 Misc 3d 1233[A], 2009 NY Slip Op 52793[U], *11 [2009]).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Park E. Constr. Corp. v. Uliano
2024 NY Slip Op 06353 (Appellate Division of the Supreme Court of New York, 2024)
Cruz v. JKS Ventures, Inc.
S.D. New York, 2024
J.S.S. v. H.S.
2024 NY Slip Op 50447(U) (New York Supreme Court, Kings County, 2024)
Cedeno v. Bollyky
2024 NY Slip Op 30899(U) (New York Supreme Court, New York County, 2024)
Alpha Energy v. GEC, LLC
Virgin Islands, 2024
Michelen v. IEEE Globalspec
N.D. New York, 2021
Board of Mgrs. of Fishkill Woods Condominium v. Gottlieb
2020 NY Slip Op 3491 (Appellate Division of the Supreme Court of New York, 2020)
Ritchie v. Ritchie
2020 NY Slip Op 3316 (Appellate Division of the Supreme Court of New York, 2020)
Congel v. Malfitano
101 N.E.3d 341 (Court for the Trial of Impeachments and Correction of Errors, 2018)
ZELASKO CONSTRUCTION, INC. v. MERCHANTS MUTUAL INSURANCE COMPANY
Appellate Division of the Supreme Court of New York, 2016
Zelasko Construction, Inc. v. Merchants Mutual Insurance
142 A.D.3d 1328 (Appellate Division of the Supreme Court of New York, 2016)
Chicago Title Insurance v. LaPierre
140 A.D.3d 821 (Appellate Division of the Supreme Court of New York, 2016)
Sim v. Farley Equipment Company LLC
138 A.D.3d 1228 (Appellate Division of the Supreme Court of New York, 2016)
THE WHARTON ASSOCIATES, INC. v. CONTINENTAL INDUSTRIAL CAPITAL LLC
Appellate Division of the Supreme Court of New York, 2016
Wharton Associates, Inc. v. Continental Industrial Capital LLC
137 A.D.3d 1753 (Appellate Division of the Supreme Court of New York, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
968 N.E.2d 439, 19 N.Y.3d 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mount-vernon-city-school-district-v-nova-casualty-co-ny-2012.